Addendum 2_PFAS.pdf
PDF 97 KB Posted
- Solicitation number
- RFP_07_24_24
- Issued by
- Sedgwick County, Colorado
About this file
This document is Addendum No. 2 to the Request for Proposals (RFP) for Preconstruction Services related to the Frisco PFAS Mitigation project, issued by the Town of Frisco, Colorado. The addendum modifies key dates in the original RFP, specifically extending the proposal deadline from August 14, 2024, to August 23, 2024, at 4:00 pm. The addendum also adds a requirement for proposers to submit a schedule showing milestones and dates for preconstruction services, with the clarification that a full construction schedule will not be required at this stage but will be needed after a proposer is selected and a contract is executed.
The preconstruction services are specifically for a water treatment facility project at the existing Well 7 location, which will involve constructing a new building, media pressure vessels, associated piping and equipment, electrical and instrumentation systems, approximately 400 linear feet of 8-inch buried pipe, chemical storage rooms, a new driveway, and site improvements. This RFP is solely for preconstruction consulting services, with the Town already having a design consultant contracted, and a separate future RFP anticipated for construction services. The addendum ensures potential bidders have updated information and clear expectations for the proposal submission process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum to RFP Documents Preconstruction Services – Frisco PFAS Mitigation RFP August 9, 2024
Addendum No. 2
This addendum summarizes additions and/or changes made to the RFP documents.
The following additions and/or changes to the RFP documents for the Frisco Fiberoptic Broadband Network shall be made:
Sheet/Section Modification Cover Sheet (Page 1) Delete “August 14, 2024 at 4:00 pm” and replace with
“August, 23, 2024 at 4:00 pm”
5. Schedule (Page 6) Delete “August 14, 2024 at 4:00 pm” and replace with
“August, 23, 2024 at 4:00 pm” under proposal deadline
6. Instructions (Page 6) Delete “4:00 pm on Wednesday, August 14, 2024” and replace with “4:00 pm on Friday, August 23, 2024 at 4:00 pm” in the first paragraph
7.7 Project Schedule (Page
7)
Add “Proposer shall submit a schedule showing milestones and dates for preconstruction services. A construction schedule submittal will not be required from proposers, but it will be required during the preconstruction services phase after a proposer is selected and a contract is executed.”
File details come from the government source that posted it. Updated .