This is Addendum 2 to a Statement of Need (SON) issued by the Georgia Technology Authority for Independent Verification and Validation (IV&V) services related to the Georgia Registry of Immunization Transactions and Services (GRITS) project. The addendum updates the procurement schedule and key requirements for qualified contractors. The primary deliverable consists of 15 monthly dashboard reports to be prepared between July 2022 and September 2023, with the IV&V contractor responsible for reviewing project deliverables, assessing key performance indicators, and providing written feedback and recommendations to the agency. The final deadline for SON responses was June 20, 2022, at 5:00 PM EST, with answers to contractor questions distributed on June 6, 2022. The anticipated award date was to be posted on the Georgia Procurement Registry following the response deadline.

Pricing for this solicitation is not to exceed $600,000, with offerors required to submit detailed cost bids using the provided Attachment H cost response template. The contract targets qualified contractors that were previously evaluated and awarded GTA Master Agreements through an earlier Request for Qualified Contractors process. All deliverables must be submitted for agency approval within 10 days of completion, with the agency responding within 10 days with acceptance, rejection with comments, or notice of extension. Approved deliverables and associated forms must be submitted for payment with invoices within 30 days of agency approval unless exceptions are mutually agreed upon.

Text of this file

Revised 04/08/22 GTA-SPR2022

SON Addendum Form

SON Number: 98000-0000005896 SON Title: Georgia Registry of Immunization

Transactions and Services (GRITS) IVV Requesting State Entity: Georgia Technology Authority Issuing Officer: Rachael Allen SON Initially Posted to GPR on 05/26/22 E-mail Address: procurement@gta.ga.gov

Telephone: 470-764-5538

Addendum Number: 2 Date: 6/6/22

All updates are highlighted below:

1) Schedule of Events

The schedule of events set out herein represents the Georgia Technology Authority’s best estimate of the schedule that will be followed. However, delays to the procurement process may occur which may necessitate adjustments to the proposed schedule. If a component of this schedule is adjusted, the rest of the schedule may be shifted as appropriate. Any changes to the dates up to the closing date of the Statement of Need (herein after called “SON”) will be publicly posted prior to the closing date of this SON. After the close of this SON, GTA reserves the right to adjust the remainder of the proposed dates on an as needed basis with or without notice.

SON Schedule of Events

Event DATE

Release of SON 05/26/2022 2:00 PM EST

Final Day to submit Questions to GTA 06/02/2022 2:00 PM EST

Answers Distributed to Qualified Contractors 06/06/2022 2:00 PM EST

SON Response Due to GTA 06/20/2022 5:00 PM EST

Anticipated Award Date As posted on the Georgia Procurement Registry (GPR)

2) Revised: 6.3 SON Key Assumptions

O. Deliverables must be submitted for Agency approval within 10 days after deliverable is completed. Agency must respond within 10 days of receipt with acceptance, rejection with comments or notice of extension.

Approved DAF must be submitted for payment with the invoice within 30 days after Agency approval unless exceptions are agreed upon.

See Exhibit C: Sample Deliverables Completion Form.

mailto:procurement@gta.ga.gov

Revised 04/08/22 GTA-SPR2022

3) 1.4 Deliverables

The IV&V Contractor will review project deliverables and provide written feedback and recommendations to the agency. This is not an exhaustive list. The IV&V Contractor is expected to determine what is required for each deliverable to determine success.

Refer to Attachment E GRITS Background and Scope of Work for a complete list of deliverables as a reference only. Each deliverable below should include a unit cost in the cost spreadsheet. (Attachment H)

Monthly Dashboard Reports – Oversight (15)

• The IV&V Contractor will prepare and deliver a monthly dashboard report using the template provided by GTA. Contractor will review all project deliverables and artifacts required to assess all KPIs.

The IV&V contractor may utilize various available artifacts/documents as input to provide recommendations on any of the dashboard KPIs.

Those various available artifacts may include but limited to Risk and Issue Management (RAID logs), Planning documentation including Charter, Budget and Financial Tracking plans and Governance Models, Data governance framework, Scope Change management, Capacity management, including consideration of existing support and release plans for underlying databases, software, and hardware, Communications Strategy Plans and Organizational Change Management Plan

• (15 dashboards) July 2022 – September 2023. The number of dashboards may change based on start date and schedule changes.

Note: In the event of a conflict between previously released information and the information contained herein, the latter shall control.

A signed acknowledgment of this addendum (this page) should be attached to your SON response.

Supplier’s Name

Signature

Printed Name and Title

Other files

File Type Posted
Attachment C IV&V Performance —
DPH GRITS IVV- SON 5896 —
Attachment H-Cost Response New —
Attachment D Skills Table —
Attachment A Q&A Template —
Award Information —
NOIA - GRITS IVV 5896 —
Attachment E GRITS Background —
Attachment F Resource Commit —
Attachment G IVV Dashboard —
Addendum 1 GRITS IVV 5896 —
Attachment B Mandatory Resp —
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .