Addendum 2.pdf

PDF 97 KB Posted

Attached to
751/19239. RWG; Gaylord DHQ - Multi-Div. Storage Facility
Solicitation number
RFQ 171 220000000085 6
Issued by
Ottawa County, Fruitport Village, Michigan

About this file

This is an Addendum 2 issued by the State of Michigan Department of Natural Resources (DNR) for the DNR Multi-Division Storage Facility project located at 757 S. Wisconsin Avenue, Gaylord, Michigan 49735. The addendum was issued on January 7, 2021, with a bid date of January 12, 2021, and clarifies utility service line locations for the new storage facility. The primary clarification addresses the location of gas and electrical service lines for the project, with Plan Sheet C-300 being issued to indicate these utility locations. Meter and service panel locations remain unchanged from the mechanical and electrical plans. All bidders are required to include the work described in this addendum in their proposals, and all incidental work necessary to complete the project must be included in contractor quotations.

This addendum supersedes previously issued specifications and drawings related to utility service lines and forms an integral part of the contract documents. Contractors are responsible for reviewing Plan Sheet C-300 and incorporating the utility service line requirements into their bids. No specific pricing information, set-asides, funding amounts, or contract term details are provided in this addendum document.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM 2

757 S. WISCONSIN AVENUE ▪ GAYLORD MI 49735

p h o n e 989.705.8400 ▪ f a x 989.705.8403

‐1‐

Addendum Number: 2

Date: 1.7.21

Project Name: DNR Multi-Division Storage Facility

SG Project Number: 519251 DTMB File No.: 751/19239RWG

Bid Date: 1.12.21

This Addendum is being issued for the purpose of clarifying and/or modifying the original Bidding Documents and shall take precedence over them. Each Bidder’s proposal shall include the Work described herein. All requirements contained in the Contract Documents shall apply to this Addendum. All incidental work necessary to complete the Work shall be included in the Contractor’s quotation even though not particularly mentioned. Parts of the Specifications and Drawings referred to herein supersede previously issued data and form a part of this Addendum.

CLARIFICATIONS:

1. Location of utilities for the new storage facility.

ATTACHMENTS:

The following documents are a part of this Addendum:

1. Plan Sheet C-300.

STATEMENT OF WORK: DNR Gaylord Storage Building Utility Service Lines

Sheet C-300 is being issued with the locations of the gas and electrical service lines indicated for the new storage facility.

Meters and service panels are located on the mechanical and electrical plans with no revisions.

END OF ADDENDUM