addendum 2.pdf
PDF 220 KB Posted
- Attached to
- RFB-58-19 CHILLER PRE-PURCHASE, DOCJT RICHMOND
- Solicitation number
- RFB 785 1900000203 1
- Issued by
- Marion County, Kentucky
About this file
This is an addendum to an Invitation to Bid issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration for a chiller pre-purchase at the DOCJT Law Enforcement Training Center in Richmond, Kentucky. Addendum No. Two, dated September 10, 2018, modifies the specifications and requirements outlined in the original RFB-58-19. The addendum establishes binding changes that bidders must incorporate into their proposals, including modifications to chiller specifications, dimensional requirements, electrical harmonic standards, evaporator configuration, and water connection specifications for the condenser and evaporator systems.
The addendum specifies four key specification changes and one layout modification for the chiller equipment. Item 1 requires bidders to submit service task information, frequency, downtime estimates, and technician hours with preliminary manufacturer data, explicitly noting these costs are for informational purposes only and not included in the purchase price or life-cycle calculations. Item 2 limits the maximum chiller height to 6 feet 10 inches without disassembly. Item 3 revises harmonic distortion requirements to reference IEEE 519 recommendations and require input filtering based on the manufacturer's harmonic analysis study. Item 4 changes the evaporator configuration from a 3-pass to a 2-pass system. Item 5 modifies the chiller room layout drawing to specify condenser water connections on the opposite side of evaporator connections, with allowances for connections at bundle ends or water box sides.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| terms and conditions COMMODITIES.pdf | ||
| addendum 1.pdf | ||
| Final_RFB_785_1900000203_1_SO_FORM.PDF | ||
| Sec15700 - Chiller Specifications - LETC.pdf | ||
| addendum 3.pdf | ||
| official bid document.pdf | ||
| Sec01050 - Special Conditions - LETC.pdf | ||
| NOTICE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-58-19
FOR: Chiller Pre-Purchase - DOCJT Law Enforcement Training Center Richmond, Kentucky
DATE: September 10, 2018
ADDENDUM NO. Two (2)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Section 15700 – Chiller Specifications; Page 3, Lines 19-22:
Service Task(s), Frequency/Milestone; Estimated Downtime for task(s) and Estimated technician hours for task(s) shall be submitted with preliminary manufacturer’s data as described in Section 01050 – Special
Conditions, Pages 6-8. Costs for such task(s) are for the owner’s information and are not part of the purchase price nor the life-cycle calculations. Do not add this information to the Form of Proposal
Item 2: Section 15700 – Chiller Specifications; Page 6, Line 31:
Maximum height of chiller (without disassembly) is 6’-10”.
Item 3: Section 15700 – Chiller Specifications; Page 16, Lines 1-3:
Replace: “The AFD shall not produce more than 10% notching and 3% total harmonic current distortion, measured at the input lugs, per IEEE-54-2014.”
With: “Based on the manufacturer's harmonic analysis study and report, provide input filtering, as required, to limit total demand (harmonic current) distortion and total harmonic voltage demand at the defined point of common coupling to meet IEEE 519 recommendations.”
CONTINUED
Invitation to Bid No. RFB-58-19 For: Chiller Pre-Purchase - DOCJT Law Enforcement Training Center Richmond, Kentucky
Kristi Sharp, CPPB, Statewide Procurement Analyst II Division of Engineering and Contract Administration
Addendum 2
9/10/18
Item 4: Section 15700 – Chiller Specifications; Page 18, Line 18:
Change evaporator from 3-pass to 2-pass.
Item 5: Chiller Room Layout Drawing:
Connection for condenser water shall be on the opposite side evaporator connections
Connection for evaporator may be out of the end of the bundle
Connection for condenser may be out the side of the water box.
END OF ADDENDUM