Addendum 2
2 MB Posted
- Attached to
- LAMAR REESE ELEM. HVAC AND PLUMBING UPGRADES
- Solicitation number
- 22-FAC-014
- Issued by
- Douglas County, Georgia
About this file
This is Addendum No. 2 to the original bid specifications and drawings for the Dougherty County Board of Education's HVAC and Plumbing Upgrades project at Lamar Reese Elementary School in Albany, Georgia, issued on June 6, 2022. The addendum modifies the original contract documents dated May 20, 2022, and requires all bidders to acknowledge receipt on their Bid Price Form to avoid disqualification. The project encompasses HVAC and plumbing system replacements at the school located at 1215 Lily Pond Road. A mandatory pre-bid conference was scheduled for June 23, 2022, with staggered attendance times between 12:45 p.m. and 2:15 p.m. at 601 Flint Ave, Albany, Georgia. The addendum includes a pre-bid sign-in sheet documenting attendance from various contractors, engineers, and school officials representing organizations including Andrews, Hammock & Powell, Inc.; Albany Air; Waters Mechanical; Newell Construction; Lang Mechanical; SafeAire; Metro Power entities; and other local contractors and consultants.
The addendum implements three primary changes to the original specifications and drawings: revisions to Section 230514 regarding closeout document requirements for HVAC, specifically modifying the transfer of extra materials and spare parts table to include one cylinder of R-410a refrigerant; additions to Section 230900 requiring DDC system monitoring of bipolar ionization unit fault outputs with alarms sent to the Owner's control system; and modifications to Section 234100 specifying that particulate air filtration and bipolar ionization units must be equipped with dry contact output capable of connection to the Building Automation System for fault condition monitoring. Additionally, three mechanical demolition plan sheets (MD101, MD102, and MD103) were completely replaced with revised versions dated June 6, 2022, detailing demolition requirements across five sectors of the school, including removal and reinstallation procedures for existing bipolar ionization units and comprehensive notes on equipment disposal and coordination with the school owner.
Text of this file
Lamar Reese Elementary School May 20, 2022
HVAC & Plumbing Upgrades
Dougherty County Board of Education
Albany, Georgia
Addendum No. 2- Page 1 of 2
ANDREWS, HAMMOCK & POWELL, INC. 250 CHARTER LANE, SUITE 100, MACON, GA 31210
ADDENDUM NUMBER: TWO DATED: June 6, 2022
To: All contract bidders of record.
This addendum forms a part of the Contract Documents and modifies the original Specifications and Drawings dated May 20, 2022, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Price Form; failure to do so may subject bidder to disqualification.
GENERAL INFORMATION
1. A copy of the Pre-Bid Sign-in Sheet is included with this addendum.
CHANGES TO SPECIFICATIONS
1. SECTION 230514 - CLOSEOUT DOCUMENT REQUIRMENTS FOR HVAC
A. On page 230514-5, paragraph 1.10.A, delete the table in its entirety and replace with the following:
TRANSFER OF EXTRA MATERIALS AND SPARE PARTS
Spec Section Total Quantity
Received
Owner's
Rep. Initials
Date
Received
ADDITIONAL REFRIGERANT
Provide one (1) cylinder of R-410a refrigerant.
"I certify that the above list of spare parts and materials have been turned over to the Owners
Representative."
Company:
Name:
Title:
Signature:
Date:
2. SECTION 230900 - INSTRUMENTATION AND CONTROL FOR HVAC
A. On page 230900-16, add the following as paragraph 3.12.N.3.:
“3. Bipolar Ionization Unit Monitoring: DDC system shall monitor fault output of all bipolar ionization units. All alarms shall be sent to the Owner's control system.”
Lamar Reese Elementary School May 20, 2022
HVAC & Plumbing Upgrades
Dougherty County Board of Education
Albany, Georgia
Addendum No. 2- Page 2 of 2
3. SECTION 234100 - PARTICULATE AIR FILTRATION AND BI-POLAR IONIZATION
UNITS
A. On page 234100-3, paragraph 2.3.A, add the following sentence before the last sentence of this paragraph.
“Unit shall be equipped with dry contact output capable of connection to BAS for monitoring a fault condition.”
CHANGES TO DRAWINGS
1. MD101 - MECHANICAL DEMO PLAN - SECTOR A
A. Delete Sheet MD101 in its entirety and replace with Sheet MD101, revised 06/06/2022, included herewith.
2. MD102 - MECHANICAL DEMO PLAN - SECTOR B
A. Delete Sheet MD102 in its entirety and replace with Sheet MD102, revised 06/06/2022, included herewith.
3. MD103 - MECHANICAL DEMO PLAN - SECTORS C, D & E
A. Delete Sheet MD103 in its entirety and replace with Sheet MD103, revised 06/06/2022, included herewith.
END OF ADDENDUM #2
Dougherty County School System - Facilities Services Department 1711 Schilling Avenue, Albany, Georgia 31705
Phone: (229) 431-1301 Fax: (229) 431-1252
Bid Number:
Bid Name:
Bid Date:
Bid Location:
NAME Prime COMPANY NAME PHONE EMAIL Tony Reese N/A DCSS Facilities 229-431-1301 treese@docoschools.org
Jake Andrews N/A Andrews, Hammock & Powell, Inc. 478-832-6372 jandrews@ahpengr.com
Jim Hughes N/A Andrews, Hammock & Powell, Inc. 478-832-6368 jhughes@ahpengr.com
Will Fox N/A Andrews, Hammock & Powell, Inc. 478-832-6383 wfox@ahpengr.com
Holden Parker N/A Andrews, Hammock & Powell, Inc. 478-832-6382 hparker@ahpengr.com
Bob Montgomery Yes Albany Air 229-894-0682 bmontgomery@albanyair.com
Rebecca Greer Yes Waters Mechanical 912-654-2829 rgreer@watersmechanical.net
Rick Newell Yes Newell Construction 229-347-3220 rick.newell@newellconstruction.com
Ashley Lang Yes Lang Mechanical 229-403-0645 clayton@langmechanical.org
Cole Sumner No ESS-Metro Power 229-206-0292 cole.sumner@metropower.com
Davy Youmans No Metro Power 229-357-1191 davy.youmans@metropower.com
Jayson Meyers Keith Lawson Company 850-879-3300 jayson@keithlawson.com construction@keithlawson.com
David Kolody No Metro Power Plumbing 229-439-5779 david.kolody@metropower.com
Clay Griffith Georgia Electric 229-869-6126 clay@geaelec.com
Bill Guin Yes SafeAire 229-343-5304 bguin@safeaire.com
Ricky Spence Yes SafeAire 229-343-5304 rspence@safeaire.com
Jason Griffin Johnson Electronics 229-869-9502 jason@jesystemsinc.com
601 Flint Ave, Albany Ga.
Mandatory Pre-Bid Sign-In Sheet 22-FAC-012, 22-FAC-013, 22-FAC-014, 22-FAC-015, 22-FAC-016, and 22-FAC-017 HVAC and Plumbing Upgrades at Alice Coachman, International Studies, Lamar Reese, MLK Jr., Morningside, and West Town Elementary Schools June 23, 2022 @ 12:45, 1:00, 1:15, 1:30, 1:45, 2:00, and 2:15 mailto:treese@docoschools.org mailto:jandrews@ahpengr.com mailto:jhughes@ahpengr.com mailto:wfox@ahpengr.com mailto:hparker@ahpengr.com mailto:bmontgomery@albanyair.com mailto:rgreer@watersmechanical.net mailto:rick.newell@newellconstruction.com mailto:clayton@langmechanical.org mailto:cole.sumner@metropower.com mailto:davy.youmans@metropower.com mailto:jayson@keithlawson.com mailto:jayson@keithlawson.com mailto:david.kolody@metropower.com mailto:clay@geaelec.com mailto:bguin@safeaire.com mailto:rspence@safeaire.com mailto:jason@jesystemsinc.com
Dougherty County School System - Facilities Services Department 1711 Schilling Avenue, Albany, Georgia 31705
Phone: (229) 431-1301 Fax: (229) 431-1252
Bid Number:
Bid Name:
Bid Date:
Bid Location:
NAME Prime COMPANY NAME PHONE EMAIL 601 Flint Ave, Albany Ga.
Mandatory Pre-Bid Sign-In Sheet 22-FAC-012, 22-FAC-013, 22-FAC-014, 22-FAC-015, 22-FAC-016, and 22-FAC-017 HVAC and Plumbing Upgrades at Alice Coachman, International Studies, Lamar Reese, MLK Jr., Morningside, and West Town Elementary Schools June 23, 2022 @ 12:45, 1:00, 1:15, 1:30, 1:45, 2:00, and 2:15
Mark Gordon No Gordon Electric Co. 229-436-9659 gordonr29@aol.com
Rod Carter No Flint River Construction 229-449-1343 flintrivercc@yahoo.com
Larry Griffin Yes LRA Constructors 229-349-2276 lgriffin@lraconstructors.com mailto:gordonr29@aol.com mailto:flintrivercc@yahoo.com mailto:lgriffin@lraconstructors.com
MUSIC LAB
ART LAB
MEDIA CENTER
CONF. RM.
114F
AV. STOR.
114E
BOOK STOR.
114D
PRODUCTION ROOM
114C
WORK RM.
114B
MEDIA SPEC. OFFICE
114A
LOBBY
CONF. ROOM
PRINC. OFF.
TLT.
104A
TLT.
108A
ASST. PRINCIPAL
COUNSELOR
VAULT
RM.
103B
OFFICE MANAGER
CLINIC
TLT.
103A
WORK RM.
DATA ROOM
111A
COMPUTER LAB
CLOSET
STOR.
118A
KILN RM.
116A
STOR.
116B
DATA RM.
LOBBY
PROJECT NUMBER:
DATE:
DRAWN BY:
CHECKED BY:
TITLE:
SUBJECT TO GENERAL
COPYRIGHT LAWS ©
REVISIONS
A B
C D
E
2021203
05/20/2022
GA DOE ID #: 0199
MD101
MECHANCAL DEMO PLAN -
SECTOR A
L A
M A
R R
E E
S E
E L E
M E
N T
A R
Y S
C H
O O
L
H V
A C
P
L U
M B
IN
G
U P
G R
A D
E S
WBF
JA3
L ily P o n d R d A lb a n y G
A
1/8" = 1'-0"1 MECHANICAL DEMO PLAN - SECTOR A
NOTES: (THIS SHEET ONLY)
1 . REMOVE CEILING MOUNTED CASSETTE TYPE DUCTLESS FAN COIL
UNIT AND ASSOCIATED REFRIGERANT PIPING. REMOVE
CONDENSATE PIPING AND MAKE NOTE OF ROUTING. SEE NEW
WORK PLAN FOR INSTALLATION OF NEW CEILING MOUNTED
DUCTLESS FAN COIL UNIT IN SAME LOCATION.
2 . REMOVE EXISTING ROOF MOUNTED DUCTLESS HEAT PUMP AND
ASSOCIATED PIPING. EXISTING EQUIPMENT SUPPORT PLATFORM
TO REMAIN.
3 . REMOVE EXISTING ROOFTOP HEAT PUMP AND ASSOCIATED
CONDENSATE DRAIN. REMOVE EXISTING GPS BIPOLAR IONIZATION
UNIT AND STORE FOR REUSE IN NEW ROOFTOP HEAT PUMP.
EXISTING ROOF CURB TO REMAIN. SEE NEW WORK PLAN FOR
INSTALLATION OF NEW ROOFTOP UNIT IN SAME LOCATION.
4 . REMOVE EXISTING ROOF MOUNTED CENTRIFUGAL EXHAUST FAN.
EXISTING ROOF CURB TO REMAIN. SEE NEW WORK PLAN FOR
INSTALLATION OF NEW ROOF MOUNTED EXHAUST FAN.
5 . EXISTING ROOFTOP UNIT, DRAIN, ETC. TO REMAIN.
6 GENERAL: UNLESS OTHERWISE NOTED, ALL DUCTWORK, GRILLES,
DIFFUSERS, ETC ARE TO REMAIN. CLEAN EXISTING DUCTWORK AS
SPECIFIED. CLEAN ALL DIFFUSERS AND GRILLES TO REMOVE ALL
DUST, DIRT, SMUDGES, ETC.
7 GENERAL: CONTRACTOR SHALL REMOVE ALL EXISTING BIPOLAR
IONIZATION UNITS IN EXISTING EQUIPMENT FOR REINSTALLATION
IN NEW EQUIPMENT. ALL BIPOLAR IONIZATION UNITS NOT REUSED
SHALL BE TURNED OVER TO THE OWNER.
8 . EXISTING POWER CIRCUIT FOR RTU/CONVENIENCE OUTLET RISES
THROUGH EXISTING PITCH POCKET. SEE ELECTRICAL DRAWINGS
FOR REMOVAL OF POWER CIRCUIT TO BELOW ROOF DECK, AND
JUNCTIONING BELOW ROOF LEVEL AND ROUTING CIRCUIT UP
INSIDE ROOF CURB ADAPTER OF NEW EQUIPMENT. FILL PITCH
POCKET FOLLOWING POWER CIRCUIT REMOVAL. PROVIDE 18
GAUGE METAL CAP TO COVER EXISTING PITCH POCKET. SEAL AIR
& WATER TIGHT.
GENERAL NOTE: OWNERSHIP OF ALL REMOVED EQUIPMENT NOT RETAINED BY
THE OWNER SHALL BECOME PROPERTY OF THE CONTRACTOR. COORDINATE
WITH OWNER FOR SALVAGE OF ANY EQUIPMENT TO BE RETAINED BY THE OWNER.
1 No. Description Date
1 ADDENDUM #2 06/06/22
CAFETERIA
SERVING
KITCHEN
OFFICE
JAN.
LAUNDRY
TLT.
132A
LOCKER
DRY STOR.
STOR.
MECH.
113A
MEN
115A
MECH.
100A
OFF.
STOR.
150A
STOR.
100C
ELECT.
100B
STOR.
112A
P.E. FACILITY
LIFT
122B
PROJECT NUMBER:
DATE:
DRAWN BY:
CHECKED BY:
TITLE:
SUBJECT TO GENERAL
COPYRIGHT LAWS ©
REVISIONS
A B
C D
E
2021203
05/20/2022
GA DOE ID #: 0199
MD102
MECHANCAL DEMO PLAN -
SECTOR B
L A
M A
R R
E E
S E
E L E
M E
N T
A R
Y S
C H
O O
L
H V
A C
P
L U
M B
IN
G
U P
G R
A D
E S
WBF
JA3
L ily P o n d R d A lb a n y G
A
1/8" = 1'-0"1 MECHANICAL DEMO PLAN - SECTOR B
NOTES: (THIS SHEET ONLY)
1 . REMOVE CEILING MOUNTED CASSETTE TYPE DUCTLESS FAN COIL
UNIT AND ASSOCIATED REFRIGERANT PIPING. REMOVE
CONDENSATE PIPING AND MAKE NOTE OF ROUTING. SEE NEW
WORK PLAN FOR INSTALLATION OF NEW CEILING MOUNTED
DUCTLESS FAN COIL UNIT IN SAME LOCATION.
2 . REMOVE EXISTING ROOF MOUNTED DUCTLESS HEAT PUMP AND
ASSOCIATED PIPING. EXISTING EQUIPMENT SUPPORT PLATFORM
TO REMAIN.
3 . REMOVE EXISTING ROOFTOP HEAT PUMP AND ASSOCIATED
CONDENSATE DRAIN. REMOVE EXISTING GPS BIPOLAR IONIZATION
UNIT AND STORE FOR REUSE IN NEW ROOFTOP HEAT PUMP.
EXISTING ROOF CURB TO REMAIN. SEE NEW WORK PLAN FOR
INSTALLATION OF NEW ROOFTOP UNIT IN SAME LOCATION.
4 . REMOVE EXISTING ROOF MOUNTED CENTRIFUGAL EXHAUST FAN.
EXISTING ROOF CURB TO REMAIN. SEE NEW WORK PLAN FOR
INSTALLATION OF NEW ROOF MOUNTED EXHAUST FAN.
5 . REMOVE EXISTING DUCTLESS HEAT PUMP MOUNTED ON
CONCRETE PAD, ASSOCIATED PIPING, ETC. SEE NEW WORK PLAN
FOR INSTALLATION OF NEW DUCTLESS HEAT PUMP TO REUSE
EXISTING PIPE ROUTING.
6 . COMPLETELY REMOVE EXISTING LOUVER AND ASSOCIATED DUCT
ABOVE LOW ROOF. SEE NEW WORK PLAN FOR REUSE OF
EXISTING OPENING. TEMPORARILY SEAL OPENINGS DURING
CONSTRUCTION AS REQUIRED TO PREVENT AIR & WATER
INFILTRATION.
7 . COMPLETELY REMOVE EXISTING SUSPENDED AIR HANDLING UNIT,
ASSOCIATED SUPPORTS, CONDENSATE PIPING, REFRIGERANT
PIPING, ETC.
8 . COMPLETELY REMOVE EXISTING CONCRETE PAD MOUNTED HEAT
PUMPS, ASSOCIATED PIPING, ETC. PATCH PIPING PENETRATIONS
TO MATCH EXISTING BRICK EXTERIOR.
9 . COMPLETELY REMOVE EXISTING DUCTWORK, SUPPORT,
INSULATION, ETC. UP TO LOCATION SHOWN.
10 . COMPLETELY REMOVE EXISTING REFRIGERANT PIPING,
CONDENSATE PIPING, SUPPORTS, INSULATION, ETC. SERVING AIR
HANDLING UNITS.
11 . REMOVE EXISTING KITCHEN HOOD EXHAUST FAN MOUNTED ON
ROOF. SEE NEW WORK PLAN FOR INSTALLATION OF NEW
EXHAUST FAN SAME LOCATION.
12 . EXISTING KITCHEN HOOD SUPPLY FAN ABOVE COOLER / FREEZER.
REMOVE A SHORT PORTION OF DUCT AS REQUIRED TO REMOVE
EXHAUST FAN. SEE NEW WORK PLAN FOR INSTALLATION OF NEW
EXHAUST FAN SAME LOCATION.
13 . EXISTING DISHWASHER EXHAUST FAN TO REMAIN.
14 . REMOVE EXISTING INLINE EXHAUST FAN MOUNTED ABOVE
CEILING AT THIS APPROXIMATE LOCATION. SEE NEW WORK PLAN
FOR INSTALLATION OF NEW EXHAUST FAN SAME LOCATION.
15 . REMOVE EXISITNG SUPPLY DUCTWORK AS REQUIRED FOR
REMOVAL OF AIR HANDLER. REMAINDER OF EXISTING SUPPLY
DUCTWORK TO REMAIN. SEE NEW WORK PLAN FOR CONNECTION
OF NEW DUCTWORK TO EXISTING DUCTWORK AT THIS LOCATION.
16 . GENERAL: UNLESS OTHERWISE NOTED, ALL DUCTWORK, GRILLES,
DIFFUSERS, ETC ARE TO REMAIN. CLEAN EXISTING DUCTWORK AS
SPECIFIED. CLEAN ALL DIFFUSERS AND GRILLES TO REMOVE ALL
DUST, DIRT, SMUDGES, ETC.
17 . GENERAL: CONTRACTOR SHALL SALVAGE ALL EXISTING BIPOLAR
IONIZATION UNITS IN EXISTING EQUIPMENT FOR REINSTALLATION
IN NEW EQUIPMENT. ALL BIPOLAR IONIZATION UNITS NOT REUSED
SHALL BE TURNED OVER TO THE OWNER.
18 . REMOVE EXISTING DOOR AIR CURTAIN, SEE NEW WORK PLAN FOR
NEW DOOR AIR CURTAIN IN SAME LOCATION.
19 . REMOVE EXISTING FENCING AS REQUIRED FOR INSTALLATION OF
NEW DUCTLESS HEAT PUMPS. SEE NEW WORK PLAN.
20 . EXISTING POWER CIRCUIT FOR RTU/CONVENIENCE OUTLET RISES
THROUGH EXISTING PITCH POCKET. SEE ELECTRICAL DRAWINGS
FOR REMOVAL OF POWER CIRCUIT TO BELOW ROOF DECK, AND
JUNCTIONING BELOW ROOF LEVEL AND ROUTING CIRCUIT UP
INSIDE ROOF CURB ADAPTER OF NEW EQUIPMENT. FILL PITCH
POCKET FOLLOWING POWER CIRCUIT REMOVAL. PROVIDE 18
GAUGE METAL CAP TO COVER EXISTING PITCH POCKET. SEAL AIR
& WATER TIGHT.
GENERAL NOTE: OWNERSHIP OF ALL REMOVED EQUIPMENT NOT RETAINED BY
THE OWNER SHALL BECOME PROPERTY OF THE CONTRACTOR. COORDINATE
WITH OWNER FOR SALVAGE OF ANY EQUIPMENT TO BE RETAINED BY THE OWNER.
No. Description Date
1 1
TT TT
TTTT
TT
TT
TT
TT
TT
TT TT
TT TT
TT
TT TT
TT
TTTT
TT TT
TTTT
TTTT
TT TT
TT
TT
TT
TT
TT TT
TT
TT
4 4 4 4
4 4
4 4
3 3
6 6
8 8
F.D./S.D. F.D./S.D.
F.D./S.D. F.D./S.D.
F.D./S.D. F.D./S.D.
F.D./S.D.
F.D./S.D.
F.D./S.D.
F.D./S.D. F.D./S.D. F.D./S.D.
9 9
9 9
K-1 CLASSROOM
K-1 CLASSROOM
K-1 CLASSROOM
K-1 CLASSROOM
K-1 CLASSROOM
2-3 CLASSROOM
2-3 CLASSROOM
2-3 CLASSROOM
2-3 CLASSROOM
K-1 CLASSROOM
K-1 CLASSROOM
K-1 CLASSROOM
K-1 CLASSROOM
SPECIAL ED.
SPECIAL ED.
TITLE ONE
CLASSROOM
TLT.
205A
TLT.
205B
WORK ROOM
BOOK STOR.
2-3 CLASSROOM
2-3 CLASSROOM
TITLE ONE
CLASSROOM
TITLE ONE
CLASSROOM
2-3 CLASSROOM
2-3 CLASSROOM
4-5 CLASSROOM
4-5 CLASSROOM
4-5 CLASSROOM
4-5 CLASSROOM
SPECIAL EDUCATION
WORK RM.
BOOK STOR.
SPECIAL EDUCATION
4-5 CLASSROOM
4-5 CLASSROOM
4-5 CLASSROOM
4-5 CLASSROOM
ELECT.
TLT.
210A
TLT.
210B
TLT.
211A
TLT.
209A
TLT.
213A
TLT.
213B
TLT.
214A
TLT.
214B
STOR.
TLT.
201A
TLT.
201B
TLT.
202A
TLT.
202B
GIRLS
306B
WORK RM.
BOOK STOR.
ELECT.
STOR.
BOYS
306A
TLT.
310B
TLT.
310A
JAN.
ELEC.
STOR.
TLT.
405C
TLT
405B
KITCHEN
405A
JAN.
TLT.
410A
TLT.
410B
GIRLS
406B
BOYS
406A
CORRIDOR
CORRIDOR
CORRIDOR
PROJECT NUMBER:
DATE:
DRAWN BY:
CHECKED BY:
TITLE:
SUBJECT TO GENERAL
COPYRIGHT LAWS ©
REVISIONS
A B
C D
E
2021203
05/20/2022
GA DOE ID #: 0199
MD103
MECHANCAL DEMO PLAN -
SECTORS C, D, & E
L A
M A
R R
E E
S E
E L E
M E
N T
A R
Y S
C H
O O
L
H V
A C
P
L U
M B
IN
G
U P
G R
A D
E S
WBF
JA3
L ily P o n d R d A lb a n y G
A
1/8" = 1'-0"1 MECHANICAL DEMO PLAN - SECTORS C, D, & E
NOTES: (THIS SHEET ONLY)
1 . REMOVE EXISTING WALL HUNG HEAT PUMP. REMOVE EXISTING
GPS BIPOLAR IONIZATION UNIT AND STORE FOR REUSE IN NEW
WALL HUNG HEAT PUMP.
2 . EXISTING 4"Ø DRYER WALL CAP TO REMAIN.
3 . EXISTING 8" X 6" EXHAUST WALL CAP TO REMAIN.
4 . REMOVE EXISTING CEILING MOUNTED EXHAUST FAN AND
ASSOCIATED DUCTWORK UP TO LOCATION SHOWN. SEE NEW
WORK PLAN FOR INSTALLATION OF NEW EXHAUST FAN SAME
LOCATION.
5 . EXISTING PROPELLER EXHAUST FAN IN ATTIC TO REMAIN.
6 . REMOVE EXISTING ROOF MOUNTED CENTRIFUGAL EXHAUST FAN.
SEE NEW WORK PLAN FOR INSTALLATION OF NEW EXHAUST FAN
SAME LOCATION.
7 . REMOVE EXISTING HORIZONTAL FAN COIL UNIT, ASSOCIATED
REFRIGERANT PIPING, CONDENSATE PIPING, ETC. MOUNTED ON
PLATFORM IN ATTIC. NOTE EXISTING REFRIGERANT PIPE AND
CONDENSATE PIPE ROUTING, EXISTING PIPE ROUTINGS TO BE
REUSED. SEE NEW WORK PLAN FOR INSTALLTION OF NEW FAN
COIL UNIT SAME LOCATION. FIELD VERIFY INSTALLATION OF
EXISTING BIPOLAR IONIZATION UNIT AND REMOVE AND STORE
FOR REUSE IN NEW FAN COIL UNIT.
8 . REMOVE EXISTING PAD MOUNTED HEAT PUMP AND ASSOCIATED
PIPING. SEE NEW WORK PLAN FOR INSTALLATION OF NEW HEAT
PUMP IN SAME LOCATION.
9 . EXISTING 16" X 14" FIRE/SMOKE DAMPER IN ATTIC PARTITION TO
REMAIN.
GENERAL NOTE:OWNERSHIP OF ALL REMOVED EQUIPMENT NOT RETAINED BY
THE OWNER SHALL BECOME PROPERTY OF THE CONTRACTOR. COORDINATE
WITH OWNER FOR SALVAGE OF ANY EQUIPMENT TO BE RETAINED BY THE OWNER.
No. Description Date
| 22-FAC-014_Addendum No. 2_06062022 |
| Pre-Bid Sign In Sheet_06022022 |
| Pre-Bid Sign-In |
| Mechanical Drawings |
| Sheets |
| MD101 - MECHANCAL DEMO PLAN - SECTOR A |
| MD102 - MECHANCAL DEMO PLAN - SECTOR B |
| MD103 - MECHANCAL DEMO PLAN - SECTORS C, D, & E |
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 3 | — | |
| Award Information | — | |
| Addendum 1 | — | |
| Addendum 4 | — | |
| Bid Invitation | — | |
| DRAWINGS | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .