Addendum 1, Technical Questions ARFQ VNF 26-02.xlsx
XLSX spreadsheet 10 KB Posted
- Attached to
- Addendum 1, Flat Roof Replace and Gutter Clean
- Solicitation number
- ARFQ-0618-BVH2600000002-2
- Issued by
- Cabell County, West Virginia
About this file
This document is Addendum 1 containing technical questions for ARFQ VNF 26-02, a rubber roof replacement project. The addendum provides clarifications on various technical aspects of the roofing project, including site inspection opportunities, with interested bidders able to contact Amber Higginbotham or Steve Cain at 304-736-1027 to arrange a pre-bid roof inspection.
The addendum confirms several critical project details, including Davis-Bacon wage requirements due to federal funding, confirmation that no prior asbestos testing or core drilling has been completed, and specification of project requirements such as coping/termination bar implementation. The warranty expectations align with industry standards, with an anticipated 20-year manufacturer's material warranty and 5-year vendor labor warranty. Bidders are advised to submit warranty documents to the agency project manager at final inspection, and the project does not require a tapered roofing system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_ARFQ_0618_BVH2600000002_1_WV_ARFQ_FORM.PDF | ||
| Provisions for Federally Funded Procurements (2).pdf | ||
| Final_ARFQ_0618_BVH2600000002_2_WV_ARFQ_FORM.PDF | ||
| Pricing Page-Flar Rubber Roof replace.xlsx | XLSX spreadsheet | |
| TCA (5).pdf | ||
| Roof Replacement.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| TECHNICAL QUESTIONS ARFQ VNF 26*02-Rubbber Roof Replace | |||
| QUESTION # | QUESTION | SPECIFICATION REFERENCE | ANSWER |
| 1 | Are Davis-Bacon wages required? Box is not marked, but solicitation says Federal Funds to be used and in that document Davis-Bacon wages required. | TCA | Yes, Davis-Bacon wages are required. |
| 2 | Has there been an asbestos test and if so, what were the results? | N/A | No, an asbestos test has not been completed. |
| 3 | Has there been a core drill? If so, what materials are expected to exist and how many layers? | N/A | No, a core drill has not been completed. |
| 4 | Tapered system requested? | N/A | No, a tapered systme is not being requested. |
| 5 | Coping or termination bar requested? | N/A | Yes, coping or termination bar is requested where applicable. |
| 6 | What type/length of warranty is requested? | 10.4.2 | As per Spec 10.4.2 "The vendor shall submit any warranty documents to the Agency project manager at final inspection". Industry standard is 20 years for material (manufacturer's warranty) and 5 years for labor (vendor warranty). |
| 7 | Can there be an inspection of the roof prior to bidding? | N/A | Yes, an inspection of the roofs is allowable prior to bidding. Please call 304-736-1027 and ask for Amber Higginbotham or Steve Cain. |
File details come from the government source that posted it. Updated .