Addendum_1_-_RFB260330-01_MEP_Reno_Phs_1.pdf
PDF 814 KB Posted
- Attached to
- Terminal MEP/HVAC Renovations
- Solicitation number
- ITB 2026-0330
- Issued by
- Brevard County, Miramar Beach CDP, Florida
About this file
This addendum document pertains to a lump sum procurement for Terminal MEP/HVAC Renovations issued by the Melbourne Airport Authority for Melbourne Orlando International Airport in Brevard County, Florida. The project encompasses the replacement of mechanical, electrical, and plumbing systems in the main terminal building, with this first phase focusing on the purchase and installation of HVAC and electrical equipment for the central energy plant, including two 500-ton water-cooled chillers, two 500-ton cooling towers, chilled and condenser water pumping systems, new 4000-ampere electrical service with automatic transfer switch and standby generator capability, distribution panels, lighting systems, fire protection modifications, and building automation controls integration. The procurement was posted on March 31, 2026, with sealed bids due on May 5, 2026, at 2:00 PM EDT. A non-mandatory pre-bid conference was conducted on April 9, 2026, at 11:00 AM EDT, with mandatory site visits available between April 14-23, 2026, on Tuesdays through Thursdays in the secure airport area. Written questions were accepted only through April 28, 2026. The anticipated construction timeline is 20 calendar weeks for permitting and construction completion.
The budgeted fund allocation for the project is $3,000,000, with financing provided through grants from the Federal Aviation Administration (FAA) and the Florida Department of Transportation (FDOT). The procurement requires compliance with Davis-Bacon prevailing wage rates and Buy American requirements. A bid bond or certified check equal to 5% of the total bid must accompany each proposal, and a public construction bond equal to 100% of the contract amount is required prior to contract execution. Liquidated damages of $1,000 per day are assessed for schedule non-compliance, and bids cannot be withdrawn for 60 calendar days following bid opening. The contract will incorporate AIA Document A101-2017 and AIA Document A201-2017. No specific set-asides for disadvantaged enterprises are indicated. The successful bidder must demonstrate financial responsibility and relevant experience, and must coordinate activities with Airport Operations, existing tenants, and other contractors while maintaining airport operations throughout the construction period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ITB_20260330_Bid_Tabulation_Intended_Award.pdf | ||
| Addendum_2_-_RFB260330-01_MEP_Reno1.pdf | ||
| 260330_Specifications_1.pdf | ||
| 260330_Bid_Set.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 1/PAGE 1 OF 4
ADDENDUM 1
FOR
REQUEST FOR BIDS
For
TERMINAL MEP/HVAC RENOVATIONS
At
MELBOURNE ORLANDO INTERNATIONAL AIRPORT
RFB 260330-01
April 14, 2026
This addendum is issued as part of the Bidding Documents for the above described project. The changes incorporated in this addendum shall be considered as a part of the documents and shall supersede, amend, add to, clarify, or subtract from those conditions shown in the original documents. The Bidder shall take care to coordinate modifications herein with all trades and disciplines related to the work. The Bidder shall acknowledge receipt of this addendum in their Bid Package by addendum number and date. Failure to do so may subject Bidder to disqualification.
SENT VIA EMAIL – 9 PAGES TOTAL (including attachments)
________________________________________(NAME OF YOUR COMPANY)
NOTE:
PLEASE SIGN_______________________________AND RETURN THIS FIRST SHEET ONLY VIA
E-MAIL OR FAX to SANDRA ACEVEDO, sacevedo@mlbair.com or (321) 723-1194 Fax
THIS VERIFIES THAT YOU HAVE RECEIVED THE ADDENDUM.
GENERAL
1. THE BID DATE REMAINS TUESDAY, May 5, 2026, at 2:00 PM (EDT).
SPECIFICATIONS
1. See attached Pre-Bid Agenda (2 pages) dated 4/9/26.
2. See attached Pre-Bid Sign-In sheet (Total of 3) from 4/9/26.
DRAWINGS
1. N/A.
QUESTIONS AND RESPONSES:
1. CIF-001: Who is unloading equipment? Is the purchaser unloading or the Phase 2 contractor?
RESPONSE: The Phase 2 contractor will be responsible for the unloading and storage of the equipment.
2. CIF-002: The Equipment will be purchased "Freight on Board" so the purchaser will be responsible for any damage that may occur once the equipment leaves the Factory. If unloaded by Phase 2 contractor, how will liability be determined should damage be found or identified at mailto:sacevedo@mlbair.com
REQUEST FOR BID for TERMINAL MEP/HVAC RENOVATION PROJECT at the MELBOURNE ORLANDO INTERNATIONAL AIRPORT
RFB260330-01
ADDENDUM 1/PAGE 2 OF 4
a later date?
RESPONSE: The Phase 2 contractor will be responsible for verifying any damage to the equipment before unloading.
3. CIF-003: Where will the equipment be unloaded?
RESPONSE: The equipment will be unloaded on airport property in an area near the new Central Energy Plant. Exact location will be determined at the time of delivery.
4. CIF-004: Will the owner provide storage as needed to comply with manufacturers warranty requirements on stored materials?
RESPONSE: The Owner will have the Phase 2 contractor comply with the manufacture’s stored materials requirements.
5. CIF-005: How long will the equipment be in storage before installation? The manufacturers IOM may require specific measures be implemented if "Long-Term Storage" will be the case...in that scenario, will the phase 2 contractor take care of those requirements?
RESPONSE: It is assumed that the notice to procure the equipment will not start until July 2026.
Assuming current industry manufacturing time frames, most of the major equipment will not be delivered until November 2026 (Generator most likely May 2027). The Phase 2 contractor should be given a NTP in late October 2026, pending grant funding becoming available. If “Long- Term Storage is required, the Phase 2 contractor will be responsible.
6. CIF-006: Is the purchaser required to rent Con-X boxes for storage of Pumps, AHU's and similar equipment or will owner provide all storage of equipment?
RESPONSE: The Owner and Phase 2 contractor will be responsible for the unloading and storage of all equipment.
7. CIF-007: Proposal Bid Form states "to furnish all materials, equipment, and labor and to perform all work in accordance with the Contract Documents" . Please confirm that this is a singular bid for all the contract documents and will not be rebid after the equipment is procured.
RESPONSE: This is a singular bid for the purchase of the equipment listed in the bid form.
Phase 2 will be the construction of the Central Energy Plant and installation of the equipment procured in this Phase 1 bid.
8. CIF-008: RFB Due Date on the Cover Page of the ITB stated May 7, 2026 which conflicts with page 1 of the ITB stating May 5, 2026. Please confirm if May 7 at 2pm is the correct date. For RFIs due on April 28 and Bid Opening on May 5 it only allows 6 days prior to bid opening date so May 7 would allow time for Responses to RFI within the 7 day window.
RESPONSE: As stated above, the bid date is TUESDAY, May 5, 2026 at 2:00 PM EDT. Last
ADDENDUM 1/PAGE 3 OF 4
day for bidder questions is Tuesday, April 28, 2026. Last addendum will be issued on Wednesday, April 29, 2026.
9. CIF-009: Please verify if 60 per Page 1 of ITB or 90 days per 004116-2 is the duration for valid proposals.
RESPONSE: Project bids on May 5, 2026. Award will be June 24, 2026. As long as the NTP is issued before July 4, 2026, which it should be, 60 days should be sufficient.
10. CIF-010: The bid documents contain conflicting descriptions of the project scope.
• 00 21 16 – Part 1 defines this project as a multi year, multi phase effort, with Phase 1 limited to procurement of HVAC and Electrical equipment for the Central Energy Plant (CEP) under a Lump Sum contract.
• 00 21 16 – Part 3 describes reroofing construction work, including demolition, temporary relocation of active systems, a defined construction schedule, liquidated damages, and a stated project budget.
As written, these sections describe different projects and risk profiles. Clarification is required to prevent bidders from assuming materially different scopes.
1.Phase 1 Scope Confirmation - Please confirm that the scope of this RFB is limited solely to procurement of HVAC and Electrical equipment for the CEP, and that reroofing or other construction activities are excluded from this bid package.
2.Reroofing Scope Status- Please confirm that the reroofing scope described in Part 3:
o Is not part of this RFB, and o Will be issued under a separate phase and/or future procurement.
RESPONSE: This bid is for procurement only of the equipment identified in the bid form. No roofing material is part of this bid.
11. CIF-011: 1. Equipment Delivery Requirements - Identify the required delivery location(s) for CEP equipment and confirm whether delivery occurs within secure or airside areas, including escort requirements.
2. Equipment Storage Responsibility - Please clearly state whether equipment storage is the responsibility of the Owner or Contractor, and whether off site storage is permissible prior to Owner acceptance.
3. Installation Scope - Explicitly confirm whether Phase 1 includes:
o Procurement only, o Procurement and setting, or o Full installation, connections, and commissioning.
RESPONSE: Equipment delivery will be on airport property in a secure location. Delivery will require escorts that will be provided by Airport Operations. A 24 hour notice for deliveries will be required. The Phase 2 contractor will be responsible for receiving the equipment and storing it until it is ready to be installed. This first phase of work is the procurement only of the equipment stated in the bid form.
ADDENDUM 1/PAGE 4 OF 4
12. CIF-012: Temporary Relocation Language - Confirm that references to temporary relocation of mechanical, electrical, and antenna systems do not apply to this RFB and are associated with a future construction phase.
RESPONSE: Temporary relocation does not apply to this bid.
13. CIF-013: Please confirm that the $3,000,000 budget referenced in Part 3 does not apply to this
RFB, and instead corresponds to a future phase of work.
RESPONSE: The budget for the Phase 1 procurement is $3,000,000. Total Project cost is $12,000,000.
14. CIF-014: Schedule and Liquidated Damages - Confirm whether the 20 week schedule and liquidated damages apply to this procurement phase.
If applicable, identify the contractual milestone defining substantial completion (e.g., delivery, acceptance, or storage).
RESPONSE: The schedule of the procurement was based on one manufacturer providing shop drawings within two weeks, Engineer’s review of two weeks, fabrication of mechanical equipment (excluding the generator), and delivery. Once a contractor is selected and a manufacturer(s) is/are determined, a schedule will be developed to determine the substantial completion date. Substantial completion will be defined as the delivery of the accepted equipment.
END OF ADDENDUM #1
Issued by Melbourne Airport Authority
One Air Terminal Parkway, Suite 220, Melbourne, FL 32901 USA 321.723.6227 www.mlbair.com K:\CAPITAL PROJECTS\Airport Projects\Terminal Upgrades - MEP Renovation\01 SOLICITATION\01.5 Construction\Phase 1\260409 Pre Bid Agenda - HVAC Equip Phs 1.docx
PRE-BID MEETING – NON-MANDATORY Thursday, 9 APR 2026 @ 11:00AM
PROJECT…………….. Terminal MEP/HVAC Renovations
RFB 260330-01
MAA Project No. 50025
LOCATION: Melbourne Airport Authority Board Room
AGENDA
1) Introductions
a) Sign in sheet - please sign in
b) Melbourne Airport Authority
c) Others
2) Proposals due Tuesday, May 5, 2026 @ 2:00 PM - EDT.
a) Turn in proposals to the receptionist on the second floor at the Executive offices.
b) DO NOT turn in proposals to anyone on the ground level.
c) This is a public bid opening. Bids will be opened and read aloud.
d) Verify that you have all the required attachments included with your bid.
i) Bid Bond
ii) Proof of Agent’s Authority
iii) Non-Collusion (00 45 19)
iv) Tax Delinquency Felony Convictions (00 45 51)
v) Public Entity Crimes (00 45 53)
vi) Debarment (00 45 56)
vii) Conflict of Interest (00 45 59)
viii) Certificate of Current Capacity (00 45 63)
ix) Work Opportunity Tax Credit WTW (00 45 73)
x) E-Verify Certificate (00 45 83)
xi) n/a
xii) Copy of Bidder’s Contractor License
xiii) List of Subcontractors and Suppliers
xiv) Additional Principals not listed in Section I
e) Bids will be read and only the bid bond will be verified at the time of the bid opening.
f) If proposals are not typed, make sure they are legibly written.
3) Review RFB
a) Pre-Bid is not mandatory.
b) Proposal package available through the Executive Assistant – Sandra Acevedo.
c) Project budget is $3,000,000.
d) THIS BID IS FOR EQUIPMENT PURCHASING ONLY.
e) Bid Bond required. Use what is in package or Standard AIA form acceptable.
f) READ the entire Package. No changes allowed.
g) READ the Contract. Modified A101-2017 Standard Form of Agreement with a Stipulated Sum.
h) A Public Construction Bond (Payment and Performance) is required upon award.
i) Project will start on or around July 1, 2026.
j) Project is currently set up in multiple phases:
i) Phase 1 – Procure equipment
ii) Phase 1A – Construct Central Energy Plant & install equipment
iii) Phase 2 – CHW piping Install
iv) Phase 2A – AHU Replacement
PRE-BID MEETING
Terminal MEP/HVAC Renovations Tuesday, 9 April 2026
v) Phase 3 – Old CHW Piping Removal
k) Liquidated damages are $1,000 per day.
l) Addenda – Issue date to be determined as required. All will be sent via e-mail.
i) First Addendum to be issued NLT Tuesday 4/14/26.
m) Last addendum to be issued no later than COB Wednesday, April 29, 2026.
4) Proposal Questions
a) Use Contractor Inquiry Form in package.
b) Only one question per form.
c) All questions must be in writing.
d) All questions are to be directed to Sandra Acevedo.
e) Questions can be e-mailed (preferred) or faxed.
f) All questions must be submitted by COB Tuesday, April 28, 2026.
g) Questions submitted within the specified time frame will be answered in an Addendum.
h) Do not call Airport Staff or Board Members.
5) General Information
a) This project is Federally funded and Davis-Bacon rates apply.
b) Owner Direct Purchase orders will be required for all major purchases for sales tax saving.
c) Project will be confirmed at the either May or June Board Meeting. (FAA Grant dependent).
Selected firm is welcome to attend. Meeting starts at 8:30 AM.
d) Other construction projects will be on-going during this project.
i) In-Line Baggage Handling Facility, including temporary facility.
ii) Fire Sprinklers
iii) Main Terminal Finishes upgrade
iv) Atrium Skylight
6) Questions & Answers
7) Site Visit
| Addendum 1 - RFB260330-01 MEP Reno1 |
| ADDENDUM 1 |
| At |
| MELBOURNE ORLANDO INTERNATIONAL AIRPORT |
| April 14, 2026 |
| Issued by |
| Melbourne Airport Authority |
| 260409 Pre Bid Agenda - HVAC Equip Phs 1 |
| Sign in Sheet 260409 |