This Addendum #1 is issued by the Colorado Department of Military and Veterans Affairs (DMVA) and addresses twenty-seven questions from contractors who attended the mandatory pre-bid meeting for Project 082411, BID #RFP1 2027*0078, which involves lead dust remediation at the Montrose Indoor Firing Range. The project is a Design-Build engagement requiring comprehensive lead contamination remediation based on a 2018-2019 survey, including removal of HVAC systems, suspended ceilings (approximately 7,220 square feet), drywall ceilings (approximately 1,560 square feet), carpet (approximately 3,465 square feet), and cove base (approximately 830 linear feet), along with roof and building cleaning. The design submittal sequence consists of 35%, 95%, and 100% milestones with standard 14-calendar-day DMVA review periods, and substantial completion is targeted for December 2027, though alternative design start dates beginning in March/April 2027 will not negatively impact proposal scoring if an accelerated, feasible schedule is demonstrated. Submissions are due as outlined in the RFP Step I and Step II processes, with shortlisted firms receiving detailed instructions for interviews and sealed cost proposals.

The evaluation weighting is 60% qualifications and 40% fee. A bid bond or proposal guaranty of at least 5% of the total bid is required, with payment and performance bonds of not less than 50% of the contract value required upon award, as the project exceeds $150,000. Contractors must demonstrate bonding capability up to $2,000,000 for individual projects and provide a letter from their surety affirming this capacity. The cost proposal must be a lump-sum contract price within the $1,800,000 construction budget; contractor-defined allowances are not permitted, though unit pricing for waste disposal and additional cleaning may be included to establish baselines for potential changed work. No liquidated damages will apply to this project. State prevailing wages, Davis-Bacon requirements, registered-apprenticeship participation, and apprenticeship contribution requirements do not apply. The Design-Build entity is responsible for waste characterization testing (TCLP), independent industrial hygienist services for final clearance, asbestos testing if materials may be disturbed, and compliance with zero-discharge requirements for all wet-cleaning wastewater. Normal work hours are 0700-1700, Monday through Friday, with minimum 14-calendar-day advance notice required for disruptive work or utility outages.

View the file

Other files

File Type Posted
Appendix C Montrose Lead Specification 2024.pdf PDF
IPD_Appendix A 2025 R1.pdf PDF
SC8.1 DB LS GC_2026.pdf PDF
SBP6.18 Labor Burden Calc R8-2023.docx DOCX document
SC8.0 DBLS A_2026_1.pdf PDF
Signin Sheets 11-5-26.pdf PDF
082411 Montrose IFR RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF COLORADO

DEPARTMENT OF MILITARY AND VETERANS AFFAIRS

Purchasing and Contracts 6848 South Revere Parkway Centennial, Colorado 80112 Phone (720) 250-1542 Fax (720) 250-1579

ADDENDUM #1

PROJECT 082411

BID # RFP1 2027*0078

Project Montrose Indoor Firing Range Lead Dust Remediation

Questions received from Contractors that attended the MANDATORY Pre-Bid Meeting:

1. Is Substantial Completion no later than December 2027 acceptable to DMVA?

Our proposed Architect/Engineer team has prior experience at this facility with the DMVA. However, due to existing commitments, our proposed Architect/Engineer team cannot begin design work until March/April 2027. Company remains confident in completion by December 2027, but does not want the alternate completion date to negatively affect our proposal scoring.

We would like the target Substantial Completion to be December 2027 but is flexible. Proposing an alternative design start date will not negatively affect scoring, provided the Design-Build entity demonstrates a highly feasible, accelerated schedule that guarantees final completion close to the December 2027 deadline.

2. Evaluation Formula. The RFP Project Overview and Section XII identify a 60% qualifications and 40% fee weighting, while Section IX identifies a 70% qualitative and 30% fee weighting. Appendix A states that its example uses a 60%/40% split, but the example calculations assign 40 points to qualifications and 60 points to fee. Please identify the controlling evaluation formula and issue corrected evaluation and ranking instructions by addendum.

The controlling evaluation weighting for this solicitation is 60% Qualifications and 40% Fee, as identified in the SOW and RFP Project Overview. Corrected scoring templates/calculations will be utilized during the evaluation process.

3. Proposal and guaranty bonds. SC-8.1 requires performance and labor and material payment bonds in the full amount of the Lump Sum Contract Price within ten days after Notice of Award. The RFP separately references a proposal guaranty of at least 5% and payment and performance bonds of not less than

Jared Polis Governor

Major General Robert B. Davis The Adjutant General

50%. Please confirm the required amount, form, and submission timing for the Step II proposal guaranty or bid bond and reconcile the RFP bond percentages with SC-8.1.

Please refer to the solicitation for applicable detail. There is a difference between Bid Bonds and Contract Performance Bonds which apply if awarded.

Per C.R.S. §24-105-201 If the construction value is $50,000 or greater a Bid Bond and Power of Attorney or Proposal Guaranty is required in an amount not less than 5% of the total Bid.

III. Minimum Requirements(5) Demonstrated bonding capability up to $2,000,000.00 for an individual project coincidentally with current and anticipated workloads; provide letter from surety that affirms this capacity.

XII. Fee Proposals (3) Per C.R.S. §38-26-106, if a contract amounts to $150,000 or more, the awarded contractor shall provide payment and performance bonds not less than 50% of the value of the contract. The costs associated with this bond are to be included in the contractor’s proposal.

4. Allowances and unit prices in cost proposal. SC-8.0 and SC-8.1 permit designated allowances, unit prices, and other methods for valuing changed work.

Separate from the treatment of differing conditions addressed in RFI-11, please confirm whether the initial Step II Cost Proposal may include owner-designated allowances or unit prices for concealed contamination, additional cleaning, stored-content services that cannot be quantified from the information provided in response to RFI-10, unforeseen demolition, and waste quantities that cannot be established before final design.

Contractor-defined allowances are not permitted. The Cost Proposal must be a Lump Sum Contract Price within the $1,800,000 Construction Budget.

Contractors may include specific unit pricing for waste disposal and additional cleaning to establish a baseline for any potential changed work. Unforeseen concealed conditions will be managed via Change Order per SC-8.1.

5. Design milestone conflict. The RFP requires 35%, 95%, and 100% design submittals, while the uncompleted SC-8.0 template describes 30%, 60%, and 100% Construction Document submittals. Please confirm that the project-specific 35%, 95%, and 100% sequence controls and identify the required review periods and number and format of submittal sets for each milestone.

The project-specific 35%, 95%, and 100% design submittal sequence controls, as outlined in SOW Section 3.1. Standard DMVA review periods are 14 calendar days per milestone. Submittals must be provided in electronic PDF format, with final AutoCAD drawing files required at project closeout.

6. Contract terms and proposed exceptions. Is the State willing to negotiate the terms of SC-8.0 and SC-8.1? If so, please confirm whether proposed exceptions or requested revisions must be submitted with the Step II proposal, or whether the selected Design/Build Entity will have an opportunity to negotiate contract terms after selection and before execution of the Agreement.

Per I. Notices (4)

The respondent has reviewed Appendix B: Sample Design/Build Lump Sum Agreement (Form SC-8.0) and General Conditions (SC-8.1) and by responding has agreed that the terms and conditions of the sample are expressly workable without reservation. Any exceptions to the contract must be communicated formally in writing before the bid closes.

7. Liquidated damages. SC-8.1 Article 46 establishes the procedure for assessing liquidated damages, but the daily liquidated-damages rate is not populated in SC-

8.0 Section 6.7. Please confirm whether liquidated damages will apply to this project and, if so, state the daily rate, the milestone or completion date to which liquidated damages will apply, and any applicable cap.

No liquidated damages

8. Previous remediation records. Appendix C describes a 2024 remediation specification based on the 2018 survey. Please provide records of any cleaning, demolition, HVAC work, repair, sampling, or other remediation performed after the November 2018 survey, including contractor reports, waste documentation, clearance results, and the dates and locations of subsequent exceedances.

No additional cleaning, demolition, or remediation has occurred. The current project scope is based entirely on the 2018–2019 comprehensive lead dust survey results and the 2024 lead dust remediation specifications.

9. Complete building record documents. Appendix C includes lead sample maps and selected mechanical, lighting, and remediation drawings. Please provide available record drawings and current system information for architectural, structural, mechanical, electrical, plumbing, fire-protection, and controls systems that are not included in Appendix C. Roof-drain, stormwater, and civil information is requested separately in RFI-13.

The layouts compiled within Appendix C are sufficient to develop a project proposal. The selected Design-Build entity is responsible for performing comprehensive field verifications during the 35% Pre-Design phase. Any additional record drawings needed during the project will be provided if available.

10. Other hazardous-material surveys. Please provide existing asbestos, lead-based paint, PCB-containing equipment, refrigerant, mold, or other hazardous-material surveys applicable to the ceilings, pipe insulation, flooring, mastics, roofing, HVAC equipment, ductwork, and anticipated access routes.

No other hazardous material surveys are available. If suspected hazardous materials (e.g., asbestos or PCB-containing components) must be disturbed to perform the lead remediation, the Design-Build entity is responsible for performing necessary testing and analysis as part of their investigation phase.

11. Mechanical operating records. Please provide current HVAC equipment schedules, control sequences, maintenance and filter records, testing and balancing reports, equipment condition assessments, and information identifying systems currently in service, abandoned, or shared with occupied areas.

The building is unoccupied no recent schedules, sequences, maintenance, testing, etc., are available besides the HVAC information provided in Appendix C.

The Design-Build entity must evaluate, verify, and document the condition of all active and abandoned mechanical systems during their initial field assessment.

12. Appendix C baseline scope and restoration. Appendix C directs removal of the two IFR exhaust fans, two evaporative coolers, all applicable HVAC units and associated ductwork, approximately 7,220 square feet of suspended ceilings, approximately 1,560 square feet of drywall ceilings, approximately 3,465 square feet of carpet, and approximately 830 linear feet of cove base, together with roof and building cleaning. Please confirm whether these quantities and removal limits are mandatory baseline requirements, preliminary design criteria subject to validation, or historical recommendations. Please also define the expected replacement and restoration scope for removed HVAC, ceilings, flooring, insulation, and roof penetrations.

The quantities and systems designated for removal in Appendix C represent the baseline requirements for a complete remediation. The contractor may validate and adjust these limits during the 35% design phase subject to DMVA approval.

Replacement scope must restore all affected systems, ceilings, flooring, and roof penetrations to a fully finished, operational, and code-compliant state.

13. Stored property and furnishings. Appendix C requires furnishings to be cleaned and removed from each Work Area and requires cleaning and protection of movable and non-movable goods. Please identify the approximate type and quantity of stored military equipment, shelving, lockers, furnishings, and other contents, and clarify the Design/Build Entity’s responsibility for inventory, sampling, cleaning, packaging, temporary storage, relocation, reinstallation, testing, and disposal. Please identify who will authorize disposition of government property.

The former IFR is currently utilized for military gear and equipment storage.

DMVA personnel will inventory and relocate all sensitive military equipment, IT gear, and personal belongings prior to mobilization. The Design-Build entity is responsible for cleaning, protecting, and relocating remaining larger furniture, lockers, and heavy shelving units within the designated Work Areas.

14. Known lead scope versus newly discovered hazards. SC-8.1 Article 35.3 states that the Principal Representative has determined no hazardous substances will be reasonably encountered and requires work to stop when unrendered hazardous substances are discovered. Lead contamination is expressly identified and is the central project scope. Separate from any proposal allowances or unit prices addressed in RFI-03, please provide the project-specific modification distinguishing known lead-contaminated work included in the Lump Sum Contract

Price from newly discovered hazardous materials or materially different lead conditions eligible for differing-site-condition or change-order treatment.

The known lead scope encompasses all surfaces and systems identified in Appendix C and the Lead Specification. Unforeseen hazardous materials (such as asbestos) or materially different site conditions that could not be reasonably inferred will be handled under SC-8.1 Article 35 (Changes in Work) and Article

35.3 (Hazardous Materials).

15. Existing waste-characterization data. Please provide available TCLP or other waste-characterization results for lead dust, HVAC filters and equipment, ductwork, ceiling materials, carpet, drywall, pipe insulation, roof materials, solid cleaning residue, used wipes, disposable PPE, HEPA-vacuum contents, and other anticipated waste streams.

No prior TCLP or waste-characterization testing has been conducted. The Design-Build entity is responsible for performing all required waste characterization, profiling, and testing to secure disposal facility approvals.

16. Exterior drainage and environmental pathways. The RFP requires assessment of exterior drainage components, while Appendix C requires roof cleaning and closure of HVAC roof penetrations. Please identify the exterior drainage components and discharge pathways included in the project, provide available roof-drain, stormwater, and civil drawings, and provide any prior sediment, soil, roof-drain, or stormwater sampling results.

No prior soil, sediment, or storm runoff sampling has been performed. Available roof layouts are included in Appendix C. The Design-Build entity must inspect exterior drainage and roof-drain pathways connected to the work area to prevent off-site environmental migration during remediation.

17. Wet-cleaning wastewater. Appendix C requires wet cleaning but does not state how cleaning water is to be collected or disposed. Please identify wastewater collection, filtration, characterization, discharge, and disposal requirements, including whether a zero-discharge approach is required and whether use of sanitary sewer connections is prohibited.

A zero-discharge approach is required for all wet-cleaning wastewater. No untreated wastewater may be discharged to the sanitary sewer or storm drain systems. All generated wastewater must be collected, containerized, characterized, and disposed of off-site in accordance with local, state, and federal environmental regulations.

18. Facility operations, access, and security. Appendix C states that Work Areas will be unoccupied while other portions of the facility may remain occupied.

Please provide work-hour restrictions, security and escort requirements, background checks, access limitations, outage restrictions, blackout periods, emergency egress requirements, and advance-notice requirements for disruptive work.

Normal work hours are 0700–1700, Monday through Friday. Any disruptive work or utility outages require a minimum of 14 calendar days advance notice and written approval from the DMVA PM.

19. Applicable code editions and completed code policy. SC-8.0 Exhibit H directs the parties to the State Building Code Compliance Policy but leaves the policy revision and adopted-code dates blank. Please provide the completed, project-specific Exhibit H and identify the building, mechanical, electrical, plumbing, fire, energy, accessibility, and other code editions governing the design and code review.

Current Colorado Building Code Compliance Policy applies. Rev. 8/2026

20. Completed contract elections, exhibits, and forms. Please issue the completed project-specific SC-8.0 agreement and associated exhibits and forms, including the Article 6 optional elections, applicable prevailing-wage determinations, apprenticeship contribution rates, SBP-6.17 apprenticeship utilization certifications, performance and payment bond forms, any project-specific insurance modifications, and any Supplementary General Conditions.

Please confirm whether State prevailing wages, Davis-Bacon requirements, registered-apprenticeship participation, and apprenticeship contribution requirements apply to this project.

The completed project-specific SC-8.0 agreement will be available to the selected bidder after award and during contracting phase. SBP-6.17 Apprenticeship State prevailing wages, Davis-Bacon requirements, registered-apprenticeship participation, and apprenticeship contribution requirements do not apply to this project.

21. Step I page and attachment limitations. Please confirm the Step I page limit, whether the two-sided cover letter is counted, and whether resumes, project sheets, credentials, safety data, sample work products, organizational charts, the surety letter, and the Acknowledgement and Attestation Form are excluded from the limit.

Please refer to Sections VIII. Submittals of Qualifications and X. Evaluation of Qualifications for submittal requirements and evaluation criteria. Other than the required cover letter, which is limited to one page (two-sided), there is no page limitation. However, respondents are encouraged to provide clear, concise, and well-organized submissions that effectively address the solicitation requirements without unnecessary detail.

22. Step I electronic submission requirements. For the Step I electronic qualifications submission, please confirm the permitted file format, maximum file size, naming convention, electronic-signature requirements, upload procedure, and whether the Box.com portal provides a time-stamped receipt documenting timely submission.

File format: .pdf or .docx Max file: not specified https://osa.colorado.gov/sites/osa/files/documents/SBP-BldgCodePolicy%202026.pdf

Naming convention: Company_name 082411 (zip file folder)

Box.com shows date/time folder is added. No receipt is provided.

23. Interview and Step II sealed proposal requirements. For shortlisted firms, please confirm the interview duration, presentation format, number of permitted attendees, audiovisual equipment, and handout restrictions. Please also confirm the method, location, packaging, labeling, and deadline for delivery of the Step II sealed Cost Proposal and required proposal guaranty.

Shortlisted firms will receive a formal Request for Proposals (Step II) containing comprehensive instructions regarding interview duration, presentation formats, permitted attendees, and the exact submission location and deadline for the sealed Cost Proposal. The sealed Cost Proposal will be due at scheduled date and time of firms in-person interview.

24. Are existing asbestos inspection reports available for the facility, specifically addressing suspended ceiling tiles, drywall ceiling systems, carpet and associated adhesives, vinyl cove base and mastic, pipe insulation, roofing materials, and HVAC components that may be disturbed during remediation? If reports are available, please provide them.

No asbestos inspection reports are available for this facility. Testing for asbestos-containing materials (ACM) that may be impacted by the work must be performed by the Design-Build entity during the investigation phase.

25. Appendix C, Section 4.8, identifies waste generated during remediation as lead-contaminated waste. Please confirm that representative Toxicity Characteristic Leaching Procedure (TCLP) testing may be performed to characterize waste streams and allow disposal as nonhazardous solid waste where analytical results and applicable disposal requirements permit.

Yes, representative TCLP testing may be performed to characterize waste streams. If analytical results demonstrate the waste is non-hazardous and the receiving disposal facility approves the profile, the waste may be disposed of as non-hazardous solid waste.

26. Please confirm whether state or federal prevailing wage requirements apply to this project. If applicable, can you please provide the governing wage determination and any applicable apprenticeship requirements.

SBP-6.17 Apprenticeship State prevailing wages, Davis-Bacon requirements, registered-apprenticeship participation, and apprenticeship contribution requirements do not apply to this project.

27. Appendix C, Sections 3.6 and 4.9, identifies the Owner’s Consultant as responsible for project surveillance, air monitoring, visual inspections, and final clearance sampling. However, RFP Section II identifies testing and final verification as responsibilities of the Design/Build Entity. Please clarify whether these services will be provided by a separate consultant retained by DMVA or by the Design/Build Entity’s industrial hygiene consultant.

The Design/Build Entity must retain an independent, certified Industrial Hygienist (IH) to perform these services and document that all Work Areas meet the mandatory ARNG clearance standard of (<10 µg/ft²) prior to handover. DMVA reserves the right to conduct independent quality assurance oversight and audit testing at its own discretion.

28. Appendix C identifies cleaning and removal of furnishings as part of the remediation scope. Please clarify whether DMVA personnel will be responsible for relocating sensitive equipment, IT equipment, military equipment, and personal belongings before remediation activities commence. Will temporary storage space be made available for cleaned furnishings and equipment?

DMVA personnel will relocate all sensitive gear and personal belongings prior to contractor mobilization. The Design-Build entity is responsible for cleaning, protecting, and moving larger items (tables, empty shelving, lockers) within the work areas. No on-site temporary storage space is available; the contractor must coordinate storage as necessary.

29. Does DMVA have a preferred sequence or phasing plan for remediation and restoration activities? Please identify any areas that must remain operational or available to facility personnel throughout construction and whether portions of the building may be temporarily vacated.

DMVA does not dictate a mandatory sequence. The building is unoccupied and no areas need to remain operational during construction. The final schedule will be coordinated and approved during the pre-construction kickoff.

30. Appendix C, Section 4.2, allows the use of existing water and electrical services, subject to availability. Please confirm whether existing water and electrical services will remain available to the remediation contractor throughout the project, including during removal and replacement of the existing building systems.

Yes, existing building electrical and water services will remain available to the contractor at the contractor’s cost. The contractor must provide all necessary connections, distribution, and backflow protection. Utility invoices will be provided to contractor for reimbursement to DMVA. The increase in usage that the contractor will be responsible for during the construction project will be determined by comparing the utility costs three months prior to construction start.

31. Would DMVA consider removal and disposal of existing window coverings, including blinds, in lieu of cleaning where replacement is determined to be more cost-effective? If approved, should replacement window coverings be included in the proposal?

DMVA will consider complete removal and disposal of existing window coverings if shown to be more cost-effective than cleaning. If proposed, equivalent, commercial-grade replacement coverings should be included in the cost proposal.

32. Are existing certified roof anchorage or tie-off points available for use during roof cleaning and remediation activities? If not, will installation of temporary or permanent anchorage points be permitted?

There are no certified roof anchorage or safety tie-off points available on the roof.

The contractor is solely responsible for establishing OSHA-compliant fall protection systems for all roofing work.

33. Appendix C requires cleaning of existing light fixtures throughout the facility.

Would DMVA consider replacement of light fixture covers or complete fixtures in lieu of cleaning where replacement provides a more cost-effective solution?

DMVA updates this requirement to replace all light fixtures or lenses.

34. Appendix C, dated May 7, 2024, identifies remediation activities throughout the approximately 25,000-square-foot facility, while the RFP Project Overview emphasizes recurring lead dust contamination associated with the former indoor firing range. Please confirm whether the entire facility-wide remediation scope identified in Appendix C is to be included in the proposal or whether the final remediation limits and component removal requirements will be established through the Design/Build Entity’s investigation and design process.

The baseline proposal must encompass the complete scope of work described in Appendix C. The final, detailed remediation limits and component removal requirements will be verified and established by the Design-Build entity’s site investigation and finalized during the 35% design phase.

35. RFP Sections II and XII identify evaluation weightings of 60% for qualifications and 40% for fees, while Section IX.C.1 identifies weightings of 70% for qualifications and 30% for fees. Additionally, Appendix A2 contains scoring examples assigning 40 points to qualifications and 60 points to fees. Please confirm the evaluation weightings and scoring methodology that will govern final selection and award.

The controlling evaluation weighting is 60% Qualifications and 40% Fee. Standard State of Colorado scoring templates utilizing this ratio will be used by the evaluation committee.

Attachments:

Addendum #1 Pre-Bid Sign in Sheet

End of Addendum