This Construction Bid Addendum No. 1 is issued by the Michigan Department of Technology, Management and Budget (DTMB) State Facilities Administration Design and Construction Division for the Barry State Game Area – New Pole Barn project (File No. 751/22020.JLM), with NFE Engineers serving as the professional and Josiah Meyers as project director. The addendum reschedules the mandatory pre-bid meeting to Friday, January 26th, 2024 at 2:00pm and establishes Friday, February 2nd, 2024 at 2:00pm as the deadline for submitting questions and bid RFIs. The revised bid opening date is Wednesday, February 7th, 2024 at 2:00pm, with a post-bid interview scheduled for Friday, February 9th, 2024 at 2:00pm. A significant scope modification eliminates the requirement for the contractor to remove an existing garage structure and concrete, as this work has already been completed by DNR staff.
The addendum includes comprehensive modifications to the project drawings across multiple plan sheets (A101, A102, A201, A301, A302, A401, and A501), which introduce a new shallow trench footing design, add #5 reinforcing bars, revise post footing depth dimensions, incorporate two different insulation rigid board options for foundation protection, add "approved equal" material provisions, specify unfaced stud cavity batt insulation, and include kraft-faced attic insulation. Additionally, a geo-technical report is being provided to all contractors for their reference and use in bid preparation. Acknowledgement of this addendum is mandatory in the bid summary and bid form; failure to acknowledge may result in bid rejection. This addendum becomes part of the contract documents upon distribution through www.michigan.gov/SIGMAVSS.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 2.pdf | ||
| Specifications 22020.pdf | ||
| Drawings 22020_Part1.pdf | ||
| Drawings 22020_Part2.pdf | ||
| Addendum 1 Drawings.pdf | ||
| Addendum 3.pdf | ||
| Addendum 4.pdf | ||
| 751-22020.JLM_Pre-Bid Sign-in Sheet.pdf | ||
| Addendum 2 Bid Summary.pdf | ||
| 751-22020.JLM_Barry SGA_Geotech Report.pdf | ||
| Advertisement 22020.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 12/17)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 1
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
1/11/2024
PROJECT NAME
Barry State Game Area – New Pole Barn
FILE NUMBER
751/22020.JLM
PROFESSIONAL
NFE Engineers
PROJECT DIRECTOR
Josiah Meyers
BID OPENING DATE:
2/7/2024
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
1. MANDATORY PRE-BID MEETING HAS BEEN RESCHEDULED FOR:
Friday, January 26TH at 2:00pm
2. ACCEPTING QUESTIONS/BID RFI’s UNTIL:
Friday, February 2nd, 2024 at 2:00pm.
3. NEW BID DUE DATE:
Wednesday, February 7th, 2024 at 2:00pm.
4. NEW POST BID INTERVIEW DATE:
Friday, February 9th, 2024 at 2:00pm.
5. Modifications to Scope:
The existing garage structure and concrete has been removed by DNR staff and will no longer be required by the
Contractor as part of the contract.
6. Modifications to Drawings (See attached drawings) A101:
Added a new shallow trench footing design to plan.
Added #5 bars to plan.
Changed depth dimension of post footing.
Added (2) different insulation rigid boards for foundation insulation protection.
A102:
Added “approved equal” to notes.
A201:
Added “approved equal” to notes.
Changed footing graphics.
A301:
Added “approved equal” to notes.
Added new shallow trench footing design to section.
Added #5 bars to section.
Changed depth dimension of post footing.
Added (2) different insulation rigid boards for foundation insulation protection.
Added “unfaced” in stud cavity Batt. Insulation note.
A302:
Added “approved equal” to notes.
Added new shallow trench footing design to section.
Added #5 bars to section.
Changed depth dimension of post footing.
Added (2) different insulation rigid boards for foundation insulation protection.
Added “unfaced” in stud cavity Batt. Insulation note.
Added ‘kraft’ to attic insulation note A401:
Added “approved equal” to notes.
Added new shallow trench footing design to section.
Added #5 bars to section.
Changed depth dimension of post footing.
Added (2) different insulation rigid boards for foundation insulation protection.
Added “unfaced” in stud cavity Batt. Insulation note A501:
Added (2) different insulation rigid boards for foundation insulation protection.
Added new shallow trench footing design to section.
7. See attached Geo-Technical Report Providing Geo-Technical Report to Contractors for their use and information.
ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: Karl Ruiter DATE: 1/11/2024
APPROVED BY:
PROJECT DIRECTOR: Josiah Myers DATE: 1/11/2024