Addendum 1 Cover Sheet Lhtg Crtl.pdf

PDF 183 KB Posted

Attached to
FRCC OSA-AFB-2024-091M23 Upgrade/Replce Lighting Ctrl Sys WC
Solicitation number
IFB1 : 2024000153
Issued by
Adams County, Westminster City, Colorado

About this file

This document is Addendum No. 1 related to the FRCC-AFB-24-02-W Front Range Community College project to upgrade and replace the lighting control system at the Westminster Campus. The addendum modifies the original contract documents by removing an existing lighting control panel from the East side of Level B, as it was found that the lighting in this area is controlled by the panel on Level C. Additionally, the acceptable lighting control manufacturers have been expanded to include ETC along with the previously approved Acuity and Wattstopper. No changes have been made to the project schedule.

The related state and local contract opportunity is for the Front Range Community College to replace the existing obsolete lighting control system at the Westminster Campus. The project scope includes the replacement of all existing relay-based lighting control panels with new relay panels, adding a new lighting control panel on Level A, replacing existing override switches and photocells for daylight zones, and adding new control locations. The project is funded by the State of Colorado and is located in Adams County and the City of Westminster.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No.: 1 March 20, 2024

2024-091M23 Upgrade/Replace Lighting Control System WC

FRCC-AFB-24-02-W

PROJECT: Front Range Community College PROJECT ID:

2024-091M23 Upgrade/Replace Lighting Contro System WC

Westminster Campus 3645 W 112th Avenue Westminster, CO 80031

CONTENTS Written Direction and Response to Questions This Addendum forms a part of the Contract Documents, clarifies and/or modifies the original Documents for the above referenced project and subsequent Addenda, and shall take precedence over the original Contract Document drawings, specifications, schedules and other documents. All bidders need to acknowledge this addendum on their cost proposal.

Changes to Drawings:

1. Sheet E001 is re-issued to remove East side Lighting control Panel from riser diagram.

2. Sheet ED214B is reissued to remove existing Lighting control panel from IT closet.

3. Sheet E214B is reissued to remove New Lighting control panel from IT closet Changes to Specifications:

1. Acceptable lighting control manufacturers have been modified to include ETC along with previously approved Acuity and Wattstopper.

Changes to Schedule:

1. None

Clarifications/Response to Questions:

1. After further site investigation, it has found that the lighting control panel on the East side of level

“B” does not exist. The lighting control for this area is controlled by the lighting control panel on level “C” directly above this space. Drawings re-issued to show this.

2. Acceptable lighting control manufacturers have been modified to include ETC along with previously approved Acuity and Wattstopper.

ISSUED BY:

Stephen Graziano Managing Architect Facilities Planning and Management Front Range Community College Phone: 303-404-5161 Email: stephen.graziano@frontrange.edu

END OF ADDENDUM ONE