This is Addendum No. 1 to a Request for Proposal issued by the Michigan Department of Technology, Management and Budget's State Facilities Administration for the Ludington State Park Beechwood Campground project to replace two toilet shower buildings (File Number 751/21086.JAN). The proposal responses are due Thursday, April 29, 2021 at 2:00 pm. The project includes ADA campsite upgrades in both front and back portions of the Beechwood Campground. The revised schedule indicates design work from May through July 2021, construction bid advertisement on August 2, 2021, with a mandatory pre-bid meeting on August 16, 2021, bid opening on August 25, 2021, construction start on October 11, 2021, and final completion by June 25, 2022.

The addendum provides clarifications regarding ADA upgrades and notes that the Phase 100 Heating Study is in draft form and will not be provided since DNR has not selected a standard system. Additional attachments provided include Front Beechwood Toilet, Laundry and Shower Building Plans from 1956, Back Beechwood Toilet and Shower Building Plans from 1961, ADA Campsite Requirements, and Back Beechwood Survey.

View the file

Other files

File Type Posted
Front Beechwood original plans 7-17-56.pdf PDF
Pre-proposal Meeting Agenda.docx DOCX document
Ludington sign-in sheet.msg MSG file
RFP 21086.pdf PDF
Campsite 3.ADARequirements.pdf PDF
Project Statement 21086.pdf PDF
Middle Beechwood original plans (s).pdf PDF
SAMPLE Billable Rate Contract (Rev 201214).pdf PDF
Back Beechwood Survey.pdf PDF
Back Beechwood original plans 7-27-61.pdf PDF
Addendum 2 21086.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 7/16)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR PROPOSAL

ADDENDUM NO. 1

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals. Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.

TO:

ALL PROPOSERS

DATE ISSUED

April 22, 2021

PROJECT NAME

Michigan Department of Natural Resources Ludington State Park Beechwood Campground Replace Two (2) Toilet Shower Buildings

FILE NUMBER

751/21086.JAN

PROJECT DIRECTOR

Jan Miller

PROPOSAL DUE DATE:

Thursday April 29, 2021 at 2:00 pm

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

1. Does DNR anticipate ADA campsite upgrades in both the front and back portions of the Beechwood site, or would it be limited to just one area?

The ADA campsite upgrades will be in both the front and back portions of Beechwood Campground.

2. Can the Phase 100 Heating Study be made available prior to the proposal due date?

The Phase 100 Heating Study is in draft form and will not be provided at this time since DNR has yet to select a standard system.

3. Revised Desired Schedule of Work:

Director approves the award of PSC contract: May 14, 2021 Design: End of May, June, July Advertise for Bid: Aug. 2, 2021 Mandatory Pre-Bid Meeting: Aug. 16, 2021 Bid Opening: Aug. 25, 2021 Submit recommendation to award construction contract to Ad Board: Aug. 30, 2021 Ad Board approves the award of construction contract: Sept. 14, 2021 Construction Start: Oct. 11, 2021 Substantial Completion: May 27, 2022 Final Completion: June 25, 2022

4. Additional attachments provided include:

• Front Beechwood Toilet, Laundry and Shower Building Plans, dated 7/17/56

• Back Beechwood Toilet and Shower Building Plans, dated 7/27/61

• ADA Campsite Requirements

• Back Beechwood Survey

APPROVED BY: Jan Miller PROJECT DIRECTOR DATE: April 22, 2021 http://www.buy4michigan.com/