Addendum 02.pdf

PDF 99 KB Posted

Attached to
Scouters Mountain Elementary School Modular Classroom Installation Project, ITB-002-2023
Solicitation number
S-P03012-00006604
Issued by
Clackamas County, Hebo CDP, Oregon

About this file

This document is Addendum Two (2) for the Scouters Mountain Elementary School Modular Classroom Installation Project (ITB-002-2023) issued by the North Clackamas School District in Clackamas County, Oregon. The addendum provides clarification on the scope of work to be performed by the bidding general contractor, who is responsible for making plumbing connections to the site utilities, while the modular installer will provide all other lines under the building. A preliminary set of modular drawings has been attached for reference.

The overall contract opportunity involves a general contractor performing site preparation and modification work, including utilities, grading, irrigation, and fencing, while a separate contractor, Modern Building Systems, will deliver and install the pre-engineered modular building and associated decking. This contract opportunity is for the Clackamas County jurisdiction in Oregon.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NORTH CLACKAMAS SCHOOL DISTRICT

SCOUTER MOUNTAIN ELEMENTARY SCHOOL MODULAR CLASSROOM INSTALLATION

PROJECT

(ITB-002-2023)

ADDENDUM TWO (2) 1 MAY 2023

PAGE 1 of 1 (Plus Listed Attachments)

THE FOLLOWING CHANGES, ADDITIONS, AND DELETIONS TO THE CONTRACT

DOCUMENTS POSTED 18 MARCH 2023 HEREBY BECOME A PART OF THE CONTRACT

DOCUMENTS.

NOTIFY ALL SUBCONTRACTORS AFFECTED BY THIS ADDENDUM. _____

QUESTIONS AND ANSWERS:

Question 1: Can the modular drawing be provided (submittals/shop drawings) as referenced on p1.0?

Answer: Yes, see attached. This is a preliminary set; we do not have final stamped set from Modern Building Systems at this time.

Question 2: Please clarify the scope being provided by the District’s modular supplier/installer.

Is the bidding contractor to just make the connection to the site utilities. Is all other water and drain lines under the building provided by District modular installer?

Answer: The bidding GC will make the plumbing connection (for water and sewer) as shown in drawings. All other lines under the building are existing and by the modular installer.

ATTACHMENTS TO THIS ADDENDUM

1. Preliminary Modular Drawings

END OF ADDENDUM TWO (2)

File details come from the government source that posted it. Updated .