ADD 1 ATT A Special Provisions and Specifications R1.pdf

PDF 630 KB Posted

Attached to
ER OR42 MP18. 9 Culvert Repair Project
Solicitation number
S-73000-00014939
Issued by
Coos County, Oregon

About this file

This document is a special provisions and specifications document from the Oregon Department of Transportation (ODOT) for the ER OR42: MP18.9 Culvert Repair Project located along the Coos Bay - Roseburg Highway (OR42) in Coos County, Oregon. The project scope involves supplying materials, equipment, labor, and incidentals to complete ten primary tasks, including temporary traffic protection, water management facilities, erosion control, subgrade stabilization, culvert pipe installation, slope end sections, trench resurfacing, pavement removal, and asphalt concrete mixture placement. The project will involve installing an 18-inch subgrade stabilization, a 30-inch culvert pipe over 20 feet deep, and 600 tons of Level 3, ½ Inch ACP Mixture (64-22 oil).

The document provides detailed technical specifications for various construction activities, including requirements for traffic control, environmental protection, pipe installation, pavement work, and erosion control. The project includes provisions for utility coordination, with contact information provided for Pacific Power, Ziply Fiber, Douglas Fast Net, and AT&T. Contractors are required to notify utilities at least 14 calendar days before beginning work. The specifications also outline precise requirements for materials, testing, installation methods, and quality control, with detailed guidance on everything from asphalt concrete placement temperatures to pipe deflection testing and seeding requirements. The project appears to be funded through standard ODOT infrastructure maintenance and improvement channels, with a focus on culvert repair and highway preservation.

View the file

Other files

File Type Posted
ADD 1 ATT C Bid Pricing Form R1.xlsx XLSX spreadsheet
00014939 Invitation to Bid.docx DOCX document
COBID Notice_NVC~1.pdf PDF
Attachment H Apprenticeship Requirements~1.docx DOCX document
ATT A Special Provisions and Specifications~37.pdf PDF
ATT B Plans~30.pdf PDF
Copy of ATT C Bid Pricing Form 00014939.xlsx XLSX spreadsheet
00014939 Bid Results.xlsx XLSX spreadsheet
ATT G Project Wage Rates~3.pdf PDF
ATT I FHWA Form 1273~4.pdf PDF
00014939 Addendum 1.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT A - REV. 1

SPECIAL PROVISONS & SPECIFICATIONS FOR

ER OR42: MP18.9 CULVERT REPAIR PROJECT

SCOPE

The work to be completed under this Contract is located along the Coos Bay – Roseburg Highway (OR42) in Coos County, OR, which consists of supplying the materials, equipment, labor and incidentals required to perform the following tasks as described in the Contract plans and specifications:

1. Provide Temporary Protection and Direction of Traffic.

2. Install and Maintain Temporary Water Management Facilities.

3. Install and Maintain Erosion Control.

4. Install 18 Inch Subgrade Stabilization, Riprap Geotextile, Type 2, Subgrade Geotextile.

5. Install 30 Inch Culvert Pipe, over 20 ft deep.

6. Install Slope End Sections, 30 Inch

7. Construct Trench Resurfacing.

8. Perform Cold Plan Pavement Removal, 3 Inches deep.

9. Install 600 tons of Level 3, ½ Inch ACP Mixture (64-22 oil)

10. Perform additional and incidental work as detailed in the Contract plans and specifications and as directed.

PROJECT INFORMATION

General information pertaining to this project may be obtained from the following:

Jessica Spann, Project Manager 307 Highway 42 Coquille, OR Phone: (541) 396-1143 Email: Jessica.SPANN@odot.state.or.us

APPLICABLE STANDARD SPECIFICATIONS AND SPECIAL PROVISIONS

Silence of Specifications: The apparent silence of the specifications as to any detail, or the apparent omission of a detailed description concerning any point, shall be regarded as meaning that the highest value commercial practices are to prevail and that only materials and workmanship of first quality are to be used.

Utility Contact Information Pacific Power Kristopher Freeman

135 West Lockhart Coos Bay, OR 97420 Kristopher.freeman@pacificorp.com 541-267-1830

Ziply Fiber Monte Rutherford 276 LaClair St.

Coos Bay, OR 97420 Monte.rutherford@ziply.com 541-269-3396

Douglas Fast Net Rich Brammer 2350 NW Aviation Dr.

Roseburg, OR 97470 rbrammer@dfn.net 541-673-4242 e. 1037

AT&T Alex Thompson 700 S Main, Ste. 3 Yreka, CA 96097 athompson@shastagroup.net 530-841-0621 e. 120

The Contractor shall notify, in writing, the Utilities listed above, with a copy to the Engineer, at least 14 Calendar Days before beginning Work on the Project. Utilities may require an on-site observer, at no cost to the Contractor.

��)��������
�����
���������
�����*����������������+,-�)�./01��2�*�������

������3����� ��������� ��� -��� 4����� �����#&��� 5����#��"�#���4�������6���������4��#���7�8����#���!����������������!���#��#��������������#����&!9��#����9��#�����:�����"%�;��������4�������6������������������������!"�'�����&�����'"��&���������%���4��#������<<=><?�<<=@<?�<<=A<?�<<B<C?�<<B><?�<<B=<?�<<BB>?�<<D>C?�<<DDC?�<<DAC?�<<E=<?�<<ED<?�<<FB<?�<<FDD?�<<@D=?�<><B<?�<><D<?�<=D>C�����������������G5HIJ�$J$K�:LH5K�MLKN;$H��IOI5JIPJ$�N6LH�:$QN$4������������������

RSTUV�WXWYZX[Z\]�\YVYXVW\̂X_̀XX̀

��)��������
�����
���������
�����*����������������+,-�)�./01��2�*�������

������3����� ��������� ��� -��� 4����� �����#&��� 5����#��"�#���4�������6���������4��#���7�8����#���!����������������!���#��#��������������#����&!9��#����9��#�����:�����"%�;��������4�������6������������������������!"�'�����&�����'"��&���������%���4��#������<<==<>�<<=?<�������������������@5ABC�$C$D�:EA5D�FEDG;$A��BHB5CBIC$�G6EA�:$JG$4������������������

KLMLNOPPQ�RLMSTUVWVXYWZYVW�WZ[V\[XW�]Ŵ_WW_

��)��������
�����
���������
�����*����������������+,-�)�./01��2�*�������

������3����� ��������� ��� -��� 4����� �����#&��� 5����#��"�#���4�������6���������4��#���7�8����#���!����������������!���#��#��������������#����&!9��#����9��#�����:�����"%�;��������4�������6������������������������!"�'�����&�����'"��&���������%���4��#������<<==<>�<<==?>�<<===>�<<==@>�<<==A���������������������B5CDE�$E$F�:GC5F�HGFI;$C��DJD5EDKE$�I6GC�:$LI$4������������ MNONPQRRS�TNOUVWXYXZ[Y\[X]�Y\̂_̀ X̂\�aYbcYYc

����������������������������������������������������������������� ������������!"�#���$����������������������������������������!����%����������������#�����������#�������&������#������������#����������������������!�����������������#�!��'����������#��&#�#���������������#���$�������%��������(���
����)�������������������������

����*������������ �����+,-�)�./01��2 *������� ������3����� ���������� ��������� ����-��� 4����� �����#&��� 5����#��"�#���4�������6���������4��#���7�8����#���!����������������!���#��#��������������#����&!9��#����9��#�����:�����"%�;��������4�������6������������������������!"�'�����&�����'"��&���������%���4��#������<<=>?�������������������@5ABC�$C$D�:EA5D�FEDG;$A��BHB5CBIC$�G6EA�:$JG$4����������������

KLMLNOPPQ�RLMSTUVWVXYWZYV[�WZ\[]\̂V�_ẀaWWa

��)��������
�����
���������
�����*����������� �����+,-�)�./01��2�*�������

������3����� ��������� ��� -��� 4����� �����#&�������� 5����#��"�#���4�������6���������4��#���7�8����#���!����������������!���#��#��������������#����&!9��#����9��#�����:�����"%�;��������4�������6������������������������!"�'�����&�����'"��&���������%���4��#������<<=><?�<<=@@?�<<=A@�������������������B5CDE�$E$F�:GC5F�HGFI;$C��DJD5EDKE$�I6GC�:$LI$4��������������������

MNONPQRRS�TNOUVW XYXZ[Y\[XY�Y]̂Y_̂X̀�aY]bYYb

SECTION 00210 – MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

00220.02(a) General Requirements - Add the following bullet(s) to the end of the bullet list:

When performing trench excavation or other excavation across or adjacent to a Traffic Lane on a Roadway having a pre-construction posted speed greater than 35 mph.

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Traffic Lanes may be closed on the Coos Bay-Roseburg Highway (OR 42) when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

Single Lane Closures – One Traffic Lane in each direction on the Coos Bay-Roseburg (OR 42) may be closed during the following times:

• At all times.

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.06 Traffic Control Plan - Replace this subsection with the following subsection:

00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs –

(a) Traffic Control Plan - Submit one of the following, 5 Calendar Days before the preconstruction conference:

(1) Agency Traffic Control Plan - If the Contractor intends to use the Agency TCP without modification, a written notification indicating that the Agency TCP will be used without modification.

(2) Contractor-Modified Traffic Control Plan - The Contractor may request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor. Do not use a modified TCP, or a TCP developed by the Contractor, unless approved by the Engineer.

Use the Agency TCP unless a modified TCP, or a TCP developed by the Contractor is accepted.

The Engineer is not obligated to consider any modified Agency TCP or a TCP developed by the Contractor. The Agency will not be liable to the Contractor for failure to accept or act upon any request for a modified Agency TCP or a TCP developed by the Contractor.

To conserve time and funds, the Contractor may first submit a written request for a preliminary review by the Engineer. The request should contain a description of the proposal together with a rough estimate of anticipated dollar and time impacts. The Engineer will, within a reasonable time, respond to the Contractor in writing whether or not the request would be considered by the Agency.

If requesting a Contractor-modified Agency TCP, or a TCP developed by the Contractor, at a minimum the request shall meet all requirements of the Contract documents and comply with the Project transportation management plan (TMP). Provide the following information:

• Stamped Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD.

• A TPAR plan that includes:

• Details and features used to provide pedestrian accessibility.

• Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.

• Temporary alternate facilities or detour routes for pedestrian traffic.

• Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.

• Proposed order and duration of the TCM.

• A detailed temporary striping plan.

If the Contractor’s request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor is approved in whole or in part, acceptance will be made by a Change Order.

The Engineer will establish prices that represent a fair measure of the value of Work to be added, changed, or deleted as a result of any accepted modifications to the Agency TCP or an accepted TCP developed by the Contractor.

Once a TCP has been accepted by the Engineer, any additional modifications must be submitted by the Contractor for Agency review following the procedure described above.

The Engineer is not obligated to consider additional modifications to a previously approved TCP.

(b) Tourist-Oriented Directional and Business Logo Signs - Submit one of the following for approval, at least 5 Calendar Days before the preconstruction conference:

(1) No Signs - If there are no tourist-oriented directional (TOD) or business logo signs on the Project, a written notification that no TOD or business logo signs exist within the Project limits or

(2) Signs - Submit one copy of a sketch map of the Project showing all existing TOD and business logo signs and a written narrative describing how these signs will be kept in service and protected throughout all the construction stages. If modifications are necessary, submit updated information to the Engineer for approval at least 21 Calendar Days before the change is needed.

00221.60 Temporary Traffic Control Devices – Replace the paragraph that begins “TCD delivered to the Project Site found…” with the following paragraph:

Repair or replace TCD delivered to the Project Site found to be in “marginal” or “unacceptable” condition, at no additional cost to the Agency.

00221.90(b) Temporary Protection and Direction of Traffic – Replace the bullet that begins “Providing, Surfacing, maintain…” with the following bullet:

• Providing, surfacing, maintaining, removing, and restoring the TPAR.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications.

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

Comply with Section 00224 of the Standard Specifications.

SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT ATTENUATORS

Comply with Section 00226 of the Standard Specifications modified as follows:

00226.43 Truck Mounted Attenuator – Replace the title of this subsection with “Temporary Impact Attenuator, Truck Mounted”

Replace the paragraph that begins “When workers or construction Equipment…” with the following paragraphs:

Use a temporary truck mounted impact attenuator (TMA), when workers or construction Equipment are exposed to Public Traffic on a Freeway or Multi-Lane Highway and are not located behind a rigid barrier system, as follows unless otherwise shown or directed:

• Each Shoulder or each lane closure where the preconstruction posted speed is 45 mph or more.

00226.80(b)(2) Temporary Barrier - Add the following to the end this subsection:

The quantities will be limited to those shown in Table 00226-1. The estimated quantity of Temporary Barrier is:

TABLE 00226-1

Stage/Phase Location (STA to STA)

Temporary Barrier (foot)

Temporary Barrier, Minimum Deflection

(foot) Stone Buttress Construction

N/A 850

Total Quantity 850

SECTION 00245 - TEMPORARY WATER MANAGEMENT

Section 00245, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00245.00 Scope - This Work consists of furnishing, installing, operating, maintaining, and removing temporary water management facilities in regulated Work areas.

00245.01 Abbreviations:

TWM - Temporary Water Management TWMF - Temporary Water Management Facility TWMP - Temporary Water Management Plan

00245.02 Definitions:

Temporary Water Management Facility - A TWMF that conveys water around or through Work areas, removes water from Work areas, and treats and discharges water at locations outside Work areas.

Materials

Pipe ....................................................................... 00445.11 Plastic Sheeting ................................................ 00280.14(a) Sandbags ......................................................... 00280.15(a)

Furnish pumps that are:

• Self-priming.

• Equipped with a variable speed governor.

• Equipped with a power source.

• Able to pump water that contains soft and hard solid.

Finishing and Cleaning Up

00245.70 Removal - Prior to removal of the TWMF, obtain approval from the Engineer after completion of all Work within ordinary high water limits. Remove the TWMF and re-water and restore the stream flow. Maintain downstream water flow during removal of the facility. Staged or metered re-watering may be required and will be determined by the Engineer.

Measurement

00245.80 Measurement - No measurement of quantities will be made for temporary water management facilities.

The estimated quantities of Materials required for the temporary water management facility are:

Temporary Water Management Facility at Station “’L” 35+00:

Pipe ....................................................................... 200 Feet Plastic Sheeting ........................................... 3 Square Yards Sandbags ............................................................. 100 Each

Payment

00245.90 Payment - The accepted quantities of temporary water management facilities will be paid for at the Contract lump sum amount for the item "Temporary Water Management Facility at Station “L” 35+00.

SECTION 00280 - EROSION AND SEDIMENT CONTROL

Comply with Section 00280 of the Standard Specifications modified as follows:

00280.00 Scope - Replace the paragraph that begins "This Work also consists of providing temporary …" with the following paragraph:

This Work also consists of providing temporary erosion and sediment control (ESC) measures and furnishing, installing, moving, operating, maintaining, inspecting, and removing ESC throughout the Project area according to the Standard Drawings, the erosion and sediment control plan (ESCP), the Specifications, or as directed, until the site is permanently stabilized. Included also is the monitoring of weather, of stormwater and receiving waters, the reporting of monitoring observations, the reporting of corrective actions (when necessary) and the updates and revisions of the ESCP, including ESCP cover sheet, necessary to keep it representative of current site conditions and compliant with the NPDES 1200-CA, 1200-CN, OR 1200-C permit if applicable.

Delete the paragraph that begins “When contaminants, pollutants or hazardous materials…”.

Add the following paragraph to the end of this subsection:

The Agency’s NPDES 1200-CA permit is not applicable to this Project. Comply with all applicable conditions of this Section.

00280.02 Definitions - Delete the definition Wet Season Work

00280.04 Erosion and Sediment Control Plan on Agency Controlled Lands - Replace the bullet that begins “Information required under 1200-CA…” with the following bullet:

• Information required under 1200-CA permit, if applicable.

00280.06 Erosion and Sediment Control Manager - Delete this subsection.

00280.16(k) Active Treatment System – Add the following sentence to the end of this subsection:

Obtain approval of the active treatment system from DEQ prior to use.

00280.41(c) Wet Season Work and Temporary Work Suspension - Replace this subsection with the following subsection:

00280.41(c) Temporary Work Interruption - Update the ESCP and schedule for Work proposed between October 1 and May 31 to ensure that all appropriate controls, including ESC during Work interruption, are implemented and maintained. Submit the updated ESCP and schedule to the Agency and receive approval before beginning any Work between October 1 and May 31.

Between October 1 and May 31, limit excavation and bare ground activities to only those required for immediate operations. Stabilize stockpiles at the end of each workday by diverting flows, placing covers, or installing Sediment barriers.

00280.41(f) Hauling Material – Replace this subsection, except for the subsection number and title, with the following:

Cover loads carrying soil or sediment which may generate dust. Haul saturated loads in water tight beds or drain saturated loads prior to leaving the Project Site.

00280.41(g) Underground Injection Controls (UIC) – Replace this subsection, except for the subsection number and title, with the following:

Do not allow storm water from work area to enter Underground Injection Control (UIC) inlets, UIC catch basins or UIC wells.

00280.48 Emergency Materials - Add the following paragraphs after the paragraph that begins "Provide, stockpile, and protect...":

Provide and stockpile the following emergency Materials on the Project Site:

Item Quantity

Plastic Sheeting ...................................... 500 Square Yards Straw Bale ............................................................. 30 Each

When emergency materials are used, restock emergency materials within 48 hours of use.

00280.62 Inspecting and Monitoring – Delete the paragraph that begins “Inspect the Project Site…”.

00280.62(a) Inspection - Replace the paragraph that begins "Perform site inspection, complete…" with the following paragraph:

Inspect the Project Site and all ESC devices for Effective Function and potential erosion or sediment movement and complete all applicable parts of the ODOT Erosion Control Monitoring Form, and submit the form to the Agency as follows:

00280.64(a) Corrective Action Timelines – Delete the bullet that begins “If completion of corrective action is not feasible…”

Delete the bullet that begins “Provide a schedule for clean-up and corrective actions…”

Delete the bullet that begins “Provide all corrective action documentation and photographs…”

00280.91 Payment – Replace the paragraph that begins “Emergency Materials that are incorporated…” with the following paragraph:

Materials listed in 00280.48 that are incorporated into the Project will be paid for under the appropriate items listed in the Contract Schedule of Items.

SECTION 00290 – ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications modified as follows:

00290.20(c)(2) Clean Fill - Add the following paragraph to the end of this subsection:

Manage all excavated soil that does not meet the definition of clean fill according to Section 00294.

Add the following subsection:

00290.30(a)(7) Water Quality:

• Do not discharge water contaminated by pollutants including sediment, drilling fluids and waste, concrete, grout, or water contained within a work area isolation, into any waters of the State or U.S. or conveyances draining thereto until it has been treated using Materials such as those listed in 00280.15 or 00280.16 or by pumping to a vegetated upland location.

Do not allow Project discharges to increase the concentration of any pollutant in the receiving water to a level that exceeds the limits prescribed by OAR 340-041.

• Implement containment measures adequate to prevent pollutants from entering waters of the State or U.S. Such pollutants include but are not limited to construction and demolition materials, waste spoils, fuel or petroleum products, detergents, silt, welding slag and grindings, concrete sawcutting by-products and sandblasting abrasives.

00290.34(a) Regulated Work Areas - Add the following to the end of this subsection:

The regulated work area is defined as the area at or below the ordinary high water (OHW) elevation. The Engineer will identify and mark the regulated work area.

Perform work within the regulated work area only during the in-water work period. The in-water work period is from _July 1___ to __September 15___.

Add the following subsection:

00290.34(c) Aquatic Species Protection Measures Required by Environmental Permits:

(1) General Requirements:

Use heavy equipment as follows:

• Secure absorbent material around all stationary power equipment (for example:

generators, cranes, drilling equipment) operated within 150 feet of wetlands, waters of the State, waters of the U. S., drainage ditches, or water quality facilities to prevent leaks, unless suitable containment is provided to prevent spills from entering waters of the State or waters of the U.S.

• Store fuel and maintain all equipment in staging areas that are at least 150 feet away from any waters of the State, waters of the U.S., or storm inlet or on an impervious surface that is isolated from any waters of the State, waters of the U.S., or storm inlet.

(2) Work Area Isolation - Provide work isolation according to Section 00245. Provide safe passage around or through the isolated work area for adult and juvenile migratory fish unless passage did not previously exist.

(5) Site Restoration - Restore damaged streambanks to a natural slope, pattern, and profile suitable for establishment of permanent woody vegetation unless precluded by pre-project conditions (for example: natural rock substrate):

• Stabilize all disturbed soils, including obliteration of temporary access roads, following any break in work unless construction will resume in 4 Calendar Days.

00290.51 Protection of Sensitive Cultural Sites - Add the following to the end of this

An Inadvertent Discovery Plan (IDP) has been developed for this project. The IDP is available from the Engineer.

SECTION 00305 - CONSTRUCTION SURVEY WORK

Comply with Section 00305 of the Standard Specifications.

SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Comply with Section 00310 of the Standard Specifications modified as follows:

00310.80 Measurement - Replace the bullet “Length and Area…” with the following bullet:

• Length and Area - The length or area of the Structure or item actually removed, will be measured along the line and grade of the Structure or item for each continuous Structure or item removed. Measurement will be on the length or area basis, limited to the Neat Lines shown or directed.

(Asphalt Pavement Sawcutting) (and) (Concrete Sawcutting) will be measured by the linear foot of sawcut, limited to the Neat Lines shown or directed unless otherwise specified.

Methods other than sawcutting will not be measured. If the depth is greater than shown, the length will be adjusted by converting to an equivalent number of feet on a proportionate-length basis.

Additional concrete sawcutting beyond what is shown or directed by the Engineer will not be measured.

00310.92 Separate Item Basis -

Replace the Pay Item Asphalt Pavement Sawcutting with the following Pay Item:

Pay Item Unit of Measurement

(g) Asphalt Pavement Sawcutting, ___10__ inches Deep ............. Foot

Replace the paragraph that begins “Item (g) applies…” with the following paragraph:

In item (g), the depth of cutting will be inserted in the blank.

Add the following paragraph to the end of the subsection:

No separate or additional payment will be made when methods other than sawcutting are utilized where sawcutting is shown or directed.

SECTION 00320 - CLEARING AND GRUBBING

Comply with Section 00320 of the Standard Specifications modified as follows:

00320.40(c) Tree and Vegetation Trimming - Replace the bullet that begins “Trim branches obstructing sight…” with the following bullet:

• Trim and remove branches, vegetation, or other materials obstructing sight distance at intersections or impairing visibility of signs, signals, illumination, and other TCD.

SECTION 00330 - EARTHWORK

Comply with Section 00330 of the Standard Specifications modified as follows:

00330.03 Basis of Performance - Add the following paragraph to the end of this subsection:

Perform all earthwork under this Section except for Stone Embankment on the excavation basis.

00330.16(a) Requirements – Add the following paragraph: Limit the maximum size of the Stone Embankment Material to 4 inches where specified in the plans’ typical sections and details.

00330.41(a)(9) Excavation Below Grade - Delete subsection 00330.41(a)(9)(c).

00330.42(c)(3) Embankment Slope Protection - Add the following paragraph to the end of this subsection:

Construct the outer 6 inches of embankments with suitable materials to establish slope stabilization through permanent seeding. If suitable material is not available, provide suitable materials from a Contractor-provided source which conforms to the requirements of 00330.11 or 00330.13 and provides favorable conditions for germination of seed and growth of grass.

00330.43(d) Small, Irregular Fill Areas – Replace the paragraph that begins “The density requirements of 00330.43 do not apply…” with the following paragraph:

The density requirements of 00330.43 do not apply to irregular fill areas outside of the travel lanes that have a total volume of no more than 150 cubic yards at each location. Construct these areas according to the following:

00330.82 Embankment Basis Measurement – Replace this subsection, except for the subsection number and title, with the following:

Stone Embankment shall be measured on a weight basis per ton in accordance with Section 00190.10(d)(2).

00330.91(d) General Excavation - Delete the bullet that begins "Includes Unsuitable Material…".

Payment

00330.94 Embankment Basis Payment – Replace this subsection, except for the subsection number and title, with the following:

Payment for Stone Embankment will be made per ton in place, and it is considered full compensation for all labor, materials, equipment, and incidentals necessary to complete the work as specified.

SECTION 00331 - SUBGRADE STABILIZATION

Comply with Section 00331 of the Standard Specifications.

SECTION 00350 - GEOSYNTHETIC INSTALLATION

Comply with Section 00350 of the Standard Specifications

SECTION 00415 - VIDEO PIPE INSPECTION

Comply with Section 00415 of the Standard Specifications modified as follows:

00415.22 Mainline Inspection Equipment with Laser Profiler - Replace this subsection, except for the subsection number and title, with the following:

Provide laser profiler, software and equipment according to 00415.20 and ASTM F3080.

00415.42 Post Installation Video Inspection - Replace this subsection, except for the subsection number and title, with the following:

Perform post construction video inspection according to 00415.40 and 00415.41. Video inspect the pipe interior no sooner than 30 Days after the trench backfill and compaction have been completed, and before any paving is performed. If the Contract duration does not permit a 30 Day waiting period the Engineer may adjust the duration period.

(a) Deflection Testing for Flexible Pipe - Perform post construction deflection testing for all flexible pipe including plastic, metal, and aluminum pipe using one of the approved following methods.

(1) Remote Video Inspection with Laser Profiler - Calibrate and perform deflection inspection according to ASTM F3080. Use video inspection equipment meeting the requirements of 00415.22.

(2) Manual Deflection Test - Use Equipment meeting the requirements of 00415.23.

In addition to 00415.41(b):

Measure the deflection of the pipe using either a metal or a fabric tape and read at least to the nearest 1/2 inch. Measure the smallest inside diameter three times for each pipe section in the run. Take the first measurement vertically from the crown to invert (12 o’clock to 6 o’clock positions). Take the second measurement by rotating 60 degrees from vertical (2 o’clock to 8 o’clock positions). Take the third measurement by rotating 120 degrees from vertical (4 o’clock to 10 o’clock positions). For all measurements, stretch tape to full extent across the inside of the pipe.

Calculate percent deflection using the following formula:

Percent Deflection = [(D1 - D2) ÷ D1] × 100 where:

D1 = Initial measurement according to AASHTO Nominal Diameter D2 = Most deflected measurement in each pipe run after construction

00415.70 Video Inspection Recording and Written Inspection Report - Replace the title of this subsection with “Video Inspection Recording and Inspection Report”.

00415.70(a) Inspection Report - Replace this subsection, except for the subsection number and title, with the following:

Provide a written inspection report that includes each defect, deformity, and joint along with the distance from the inspection starting point. Provide still digital images in the report along with a reference and description of each defect, deformity and joint.

00415.70(b) Deflection Report - Replace this subsection, except for the subsection number and title, with the following:

For laser profiler provide an inspection report according to ASTM F3080.

If a manual deflection test was performed provide a written deflection inspection report that includes each deformity with the distance from the inspection starting point. Include in the report all measurements, calculations and still digital images and descriptions of each deformity.

00415.71 Corrections to Deficiencies in Work - Replace the paragraph that begins "Submit a repair plan to the Engineer for approval …" with the following paragraph:

Submit a repair plan to the Engineer for approval of all detrimental pipe deficiencies that are revealed in the video recording and written report. Repair all deficiencies within 48 hours after receiving notification from the Engineer. Re-perform the video inspection, submit the new video, and update the written report at no additional cost to the Agency.

SECTION 00445 - SANITARY, STORM, CULVERT, SIPHON, AND IRRIGATION PIPE

Comply with Section 00445 of the Standard Specifications.

SECTION 00495 - TRENCH RESURFACING

Comply with Section 00495 of the Standard Specifications.

SECTION 00620 - COLD PLANE PAVEMENT REMOVAL

Comply with Section 00620 of the Standard Specifications modified as follows:

Traffic is not allowed on the cold planed surface. Before opening the area to traffic, pave the surface according to 00744.51 and 00745.51.

00620.90 Payment - Replace this subsection, except for the subsection number and title, with the following:

The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a) Cold Plane Pavement Removal, ___3 inches__ Deep ...... Square Yard

In item (a), the depth of Pavement removal will be inserted in the blank. If the depth is variable, the depth range will be inserted in the blank.

Payment will be payment in full for furnishing all Equipment, labor, and Incidentals necessary to complete the Work as specified.

No separate or additional payment will be made for temporary wedges constructed, maintained, and removed under 00620.40(d), or for replacement of cutting teeth.

SECTION 00640 - AGGREGATE BASE AND SHOULDERS

Comply with Section 00640 of the Standard Specifications.

SECTION 00730 - EMULSIFIED ASPHALT TACK COAT

Comply with Section 00730 of the Standard Specifications modified as follows:

00730.11 Emulsified Asphalt – Replace the sentence that begins “Furnish CSS-1, CSS-1h…” with the following sentence:

Furnish CSS-1, CSS-1h, CMS-2, CMS-2S, CMS-2h, CRS-1, CRS-2, HFRS-2, HFMS-2 or HPTC as selected by the Contractor.

00730.90 Payment - Replace this subsection, except for the subsection number and title, with the following:

No separate or additional payment will be made for Emulsified Asphalt tack coat. Approximately

0.65 Tons of Emulsified Asphalt in tack coat will be required on this Project.

SECTION 00744 - ASPHALT CONCRETE PAVEMENT

Comply with Section 00744 of the Standard Specifications modified as follows:

00744.11(a) Asphalt Cement - Add the following to the end of this subsection:

Provide PG 64-22 grade asphalt cement for this Project.

00744.16 Sampling and Testing - Replace this subsection, except for the subsection number and title, with the following:

For each 1,000 Tons of placement, have a CAT I perform a minimum of one of each of the following test methods as modified in the MFTP:

• Asphalt Content - AASHTO T 308 with ODOT TM 323 determined Calibration Factor

• Gradation - AASHTO T 30

• Mix Moisture - AASHTO T 329

• Maximum Specific Gravity - AASHTO T 209

• Field Compacted Gyratory Specimens - ODOT TM 326

When less than 1,000 Tons of mix is placed in a Day, perform a minimum of one series of tests per Day. Provide test results to the Engineer by the middle of the following work shift. The Engineer may waive the requirement for any of AASHTO T 308, AASHTO T 30, AASHTO T 329, and ODOT TM 326 on a daily basis. The Engineer may waive the requirement for AASHTO T 209 when less than 500 Tons of ACP is placed in a single work shift.

Provide samples or split samples to the Engineer when requested.

00744.17 Acceptance - Replace this subsection, except for the subsection number and title, with the following:

If the test result for each mix gradation constituent, asphalt content, and density measurement is within the specification limits, the material will be accepted. If the asphalt content, one or more gradation constituents, or the density measurement are not within the specification limits, the material that is not within the specification limits will be accepted according to 00150.25.

00744.41 Mixing Temperature - Replace the table with the following:

Temperature, °F Type Maximum Minimum Behind at Mixer Paver

HMAC 350 240

WMAC 350 215

00744.49 Compaction - Replace the paragraph that begins "Determine compliance with…" with the following paragraph:

Determine compliance with density Specifications by random testing of the compacted surface with calibrated nuclear gauges. Determine the density by averaging QC tests performed by a CDT with the nuclear gauge operated in the backscatter mode according to AASHTO T 335 at one random location for each 100 Tons of asphalt concrete placed, but take no less than three tests each shift. Do not locate the center of a density test less than 1 foot from the Panel edge.

Calculate MAMD according to ODOT TM 305. The Engineer may waive compaction testing requirements when less than 500 Tons of ACP is placed in a single work shift.

Add the following subsection:

00744.51 Opening Sections to Traffic - Schedule work so that, during the same shift, the surfaces being paved are paved full width and length through the wearing Course before opening to traffic.

SECTION 00840 - DELINEATORS AND MILEPOST MARKER POSTS

Comply with Section 00840 of the Standard Specifications.

SECTION 00842 - FACILITY IDENTIFICATION MARKERS

Comply with Section 00842 of the Standard Specifications modified as follows:

00842.40(a) Stormwater Control Field Facility Markers - Add the following to the end of this

Install field markers as indicated in Table 00842-1.

Table 00842-1

Facility Location DFI Number Type S1 Marker Type S2

Marker Type S3 Marker

Station HWY/MP Green (Beginning of Facility)

Green (End of Facility)

Begin End

Sta. “L” 34+88.2

LT

USI01/18.9

X

Sta. “L” 34+19.2

RT

USI01/18.9 X

SECTION 00855 - PAVEMENT MARKERS

Comply with Section 00855 of the Standard Specifications modified as follows:

00855.90 Payment – Replace this subsection, except for the subsection number and title, with the following:

The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a) Mono-Directional _____ Type I Markers ...................................... Each

(b) Mono-Directional _____ Type IAR Markers ................................. Each

(c) Bi-Directional _____ Type I Markers ............................................ Each

(d) Bi-Directional _____ Type IAR Markers ....................................... Each

(e) _____ Type II Markers ................................................................. Each

(f) Mono-Directional _____ Type IAR Markers, Recessed ................. Each

(g) Bi-Directional _____ Type IAR Markers, Recessed ...................... Each

In items (a), (b), (c), (d), (e), (f) and (g) the color of marker will be inserted in the blank.

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment, labor, and Incidentals necessary to complete the Work.

No separate or additional payment will be made for constructing Pavement grooves, Pavement preparation, adhesive, or clean-up.

SECTION 00865 - LONGITUDINAL PAVEMENT MARKINGS - DURABLE

Comply with Section 00865 of the Standard Specifications.

SECTION 01030 - SEEDING

Comply with Section 01030 of the Standard Specifications modified as follows:

01030.13(f) Types of Seed Mixes - Add the following to the end of this subsection:

Provide the following seed mix formulas:

• Permanent Seeding:

Botanical Name PLS ÷ (% Purity x % Germination) = Amount (Common Name) (lb/acre) (minimum) (minimum) (lb/acre)

Achillea millefolium (White Yarrow) 4.0 ____ ____ ____ Bromus carinatus (California Brome) 5.0 ____ ____ ____ Danthonia californica (California Oatgrass) 4.0 ____ ____ ____ Deschampsia caespitosa (Tufted Hairgrass) 4.0 ____ ____ ____ Elymus glaucus (Blue Wildrye) 5.0 ____ ____ ____ Juncus effusus (Soft Rush) 2.0 ____ ____ ____ Juncus bufonius (Toad Rush) 1.0 ____ ____ ____ Lupinus rivularis (Riverbank Lupine) 3.0 ____ ____ ____ Alnus rubra (Red alder) 3.0 Regreen sterile wheat (Wheat x Wheatgrass hybrid) 10.0

* Oregon Certified Seed

SECTION 01040 - PLANTING

Comply with Section 01040 of the Standard Specifications.

SECTION 02415 - PLASTIC PIPE

Comply with Section 02415 of the Standard Specifications.