00014939 Bid Results.xlsx
XLSX spreadsheet 32 KB Posted
- Attached to
- ER OR42 MP18. 9 Culvert Repair Project
- Solicitation number
- S-73000-00014939
- Issued by
- Coos County, Oregon
About this file
The document is a bid tabulation sheet for the ER OR42 MP18.9 Culvert Repair Project issued by the Oregon Department of Transportation (ODOT), detailing bids from eight construction companies for a culvert repair project along the Coos Bay - Roseburg Highway. The project involves removing an existing 18" culvert pipe and installing a new 30" culvert pipe through the eastbound travel lanes, with bid closing on October 7, 2025, at 2:00 PM. The scope includes temporary traffic protection, water management, erosion control, subgrade stabilization, culvert pipe installation, slope end sections, resurfacing, pavement removal, and asphalt concrete placement, with substantial completion required by November 20, 2025, and final completion by November 27, 2025.
The bid tabulation reveals total bid prices ranging from $1,570,568.00 to $3,413,356.90, with bids submitted by JRT Construction, Johnson Rock Products, Moore Excavation, Rogue Line, LaDuke Construction, LTM/Knife River Materials, Granite Construction, and Farline Bridge. The project will be funded through state funds and reimbursed by the Federal Highway Administration Emergency Relief Program. Contractors must comply with specific requirements, including employing apprentices for 12% of work hours, being BOLI Registered Training Agents for contracts over $750,000, and meeting diversity and equity workforce composition goals. The project involves complex technical specifications, utility coordination, and adherence to federal and state regulations, including prevailing wage rates and Buy America provisions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ADD 1 ATT A Special Provisions and Specifications R1.pdf | ||
| ADD 1 ATT C Bid Pricing Form R1.xlsx | XLSX spreadsheet | |
| 00014939 Invitation to Bid.docx | DOCX document | |
| COBID Notice_NVC~1.pdf | ||
| Attachment H Apprenticeship Requirements~1.docx | DOCX document | |
| ATT A Special Provisions and Specifications~37.pdf | ||
| ATT B Plans~30.pdf | ||
| Copy of ATT C Bid Pricing Form 00014939.xlsx | XLSX spreadsheet | |
| ATT G Project Wage Rates~3.pdf | ||
| ATT I FHWA Form 1273~4.pdf | ||
| 00014939 Addendum 1.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 10/7/25 | |||||||||||
| ITB No. | S-73000-00014939 | BIDDER | ||||||||||
| NAME: | JRT Construction, LLC | Johnson Rock Products, Inc. | Moore Excavation Inc. | Rogue Line LLC | LaDuke Construction, LLC | LTM, Incorporated dba Knife River Materials | Granite Construciton Co. | Farline Bridge, Inc | ||||
| Bid Closing: | 10/7/2025 @ 2:00 PM | CITY/STATE: | Oakland, OR | Coos Bay, OR | Fairview, OR | Myrtle Point, OR | Central Point, OR | Coos Bay, OR | Hermiston, OR | Stayton, OR | ||
| Description: | ER OR42 MP18.9 Culvert Repair Project | CCB# | 205161 | 34185 | 28397 | 171399 | 97502 | 56603 | 101195 | 194787 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $156,000.00 | $156,000.00 | $95,300.00 | $95,300.00 | $170,000.00 | $170,000.00 | $60,000.00 | $60,000.00 | $188,000.00 | $188,000.00 | $168,085.00 | $168,085.00 | $180,000.00 | $180,000.00 | $341,000.00 | $341,000.00 |
| 2 | Temporary Protection and Direction of Traffic | 1 | LS | $26,000.00 | $26,000.00 | $53,100.00 | $53,100.00 | $30,000.00 | $30,000.00 | $57,000.00 | $57,000.00 | $28,000.00 | $28,000.00 | $66,420.00 | $66,420.00 | $50,000.00 | $50,000.00 | $100,000.00 | $100,000.00 |
| 3 | Temporary Signs | 180 | SQFT | $40.00 | $7,200.00 | $41.60 | $7,488.00 | $32.00 | $5,760.00 | $40.00 | $7,200.00 | $36.00 | $6,480.00 | $30.00 | $5,400.00 | $25.00 | $4,500.00 | $30.00 | $5,400.00 |
| 4 | Sequential Arrow Signs | 3 | EA | $2,500.00 | $7,500.00 | $1,900.00 | $5,700.00 | $1,800.00 | $5,400.00 | $1,550.00 | $4,650.00 | $2,000.00 | $6,000.00 | $1,135.00 | $3,405.00 | $2,000.00 | $6,000.00 | $1,350.00 | $4,050.00 |
| 5 | Portable Changeable Message Signs | 2 | EA | $5,000.00 | $10,000.00 | $3,425.00 | $6,850.00 | $6,000.00 | $12,000.00 | $4,500.00 | $9,000.00 | $4,500.00 | $9,000.00 | $1,135.00 | $2,270.00 | $4,000.00 | $8,000.00 | $1,350.00 | $2,700.00 |
| 6 | Temporary Barricades, Type III | 5 | EA | $175.00 | $875.00 | $345.00 | $1,725.00 | $275.00 | $1,375.00 | $195.00 | $975.00 | $180.00 | $900.00 | $200.00 | $1,000.00 | $200.00 | $1,000.00 | $175.00 | $875.00 |
| 7 | Temporary Plastic Drums | 88 | EA | $50.00 | $4,400.00 | $49.50 | $4,356.00 | $75.00 | $6,600.00 | $52.00 | $4,576.00 | $80.00 | $7,040.00 | $57.00 | $5,016.00 | $70.00 | $6,160.00 | $50.00 | $4,400.00 |
| 8 | Temporary Non-Reflective Tape | 4950 | FT | $5.00 | $24,750.00 | $10.50 | $51,975.00 | $4.25 | $21,037.50 | $3.00 | $14,850.00 | $10.25 | $50,737.50 | $4.00 | $19,800.00 | $8.25 | $40,837.50 | $4.00 | $19,800.00 |
| 9 | Temporary Barrier | 850 | FT | $27.50 | $23,375.00 | $34.90 | $29,665.00 | $30.00 | $25,500.00 | $42.00 | $35,700.00 | $40.00 | $34,000.00 | $27.65 | $23,502.50 | $35.00 | $29,750.00 | $18.00 | $15,300.00 |
| 10 | Temporary Impact Attenuator, Narrow Site System | 2 | EA | $4,500.00 | $9,000.00 | $5,710.00 | $11,420.00 | $5,000.00 | $10,000.00 | $5,000.00 | $10,000.00 | $4,000.00 | $8,000.00 | $4,525.00 | $9,050.00 | $5,000.00 | $10,000.00 | $3,500.00 | $7,000.00 |
| 11 | Temporary Impact Attenuator, Truck Mounted | 1 | EA | $10,000.00 | $10,000.00 | $6,600.00 | $6,600.00 | $12,000.00 | $12,000.00 | $16,000.00 | $16,000.00 | $14,000.00 | $14,000.00 | $4,260.00 | $4,260.00 | $15,000.00 | $15,000.00 | $10,000.00 | $10,000.00 |
| 12 | Repair Temporary Impact Attenuator, Narrow Site System | 4 | EA | $500.00 | $2,000.00 | $630.00 | $2,520.00 | $1,000.00 | $4,000.00 | $1,200.00 | $4,800.00 | $300.00 | $1,200.00 | $500.00 | $2,000.00 | $2,500.00 | $10,000.00 | $10.00 | $40.00 |
| 13 | Repair Temporary Impact Attenuator, Truck Mounted | 2 | EA | $150.00 | $300.00 | $1,900.00 | $3,800.00 | $1,000.00 | $2,000.00 | $26,000.00 | $52,000.00 | $1,100.00 | $2,200.00 | $850.00 | $1,700.00 | $5,000.00 | $10,000.00 | $10.00 | $20.00 |
| 14 | Temporary Water Management Facility | 1 | LS | $5,500.00 | $5,500.00 | $4,300.00 | $4,300.00 | $9,000.00 | $9,000.00 | $4,500.00 | $4,500.00 | $32,000.00 | $32,000.00 | $8,250.00 | $8,250.00 | $50,000.00 | $50,000.00 | $35,000.00 | $35,000.00 |
| 15 | Erosion Control | 1 | LS | $3,000.00 | $3,000.00 | $3,150.00 | $3,150.00 | $4,000.00 | $4,000.00 | $3,000.00 | $3,000.00 | $9,400.00 | $9,400.00 | $1,135.00 | $1,135.00 | $30,000.00 | $30,000.00 | $15,000.00 | $15,000.00 |
| 16 | Plastic Sheeting | 500 | SQYD | $5.00 | $2,500.00 | $0.70 | $350.00 | $2.75 | $1,375.00 | $0.60 | $300.00 | $5.00 | $2,500.00 | $1.50 | $750.00 | $4.00 | $2,000.00 | $9.00 | $4,500.00 |
| 17 | Construction Entrance, Type 1 | 1 | EA | $2,500.00 | $2,500.00 | $2,550.00 | $2,550.00 | $4,500.00 | $4,500.00 | $2,500.00 | $2,500.00 | $3,400.00 | $3,400.00 | $3,900.00 | $3,900.00 | $15,000.00 | $15,000.00 | $3,500.00 | $3,500.00 |
| 18 | Sediment Fence | 500 | FT | $3.00 | $1,500.00 | $0.60 | $300.00 | $5.00 | $2,500.00 | $5.00 | $2,500.00 | $6.00 | $3,000.00 | $4.00 | $2,000.00 | $10.00 | $5,000.00 | $6.00 | $3,000.00 |
| 19 | Straw Bale | 30 | EA | $60.00 | $1,800.00 | $13.00 | $390.00 | $45.00 | $1,350.00 | $20.00 | $600.00 | $23.00 | $690.00 | $77.00 | $2,310.00 | $100.00 | $3,000.00 | $50.00 | $1,500.00 |
| 20 | Pollution Control Plan | 1 | LS | $500.00 | $500.00 | $400.00 | $400.00 | $1,500.00 | $1,500.00 | $600.00 | $600.00 | $1,200.00 | $1,200.00 | $115.00 | $115.00 | $2,500.00 | $2,500.00 | $3,500.00 | $3,500.00 |
| 21 | Construction Survey Work | 1 | LS | $12,500.00 | $12,500.00 | $2,550.00 | $2,550.00 | $24,000.00 | $24,000.00 | $11,000.00 | $11,000.00 | $26,500.00 | $26,500.00 | $8,850.00 | $8,850.00 | $15,000.00 | $15,000.00 | $16,800.00 | $16,800.00 |
| 22 | Removal of Pipes | 172 | FT | $7.00 | $1,204.00 | $135.00 | $23,220.00 | $10.00 | $1,720.00 | $50.00 | $8,600.00 | $20.00 | $3,440.00 | $6.00 | $1,032.00 | $150.00 | $25,800.00 | $87.20 | $14,998.40 |
| 23 | Removal of Structures and Obstructions | 1 | LS | $15,000.00 | $15,000.00 | $19,850.00 | $19,850.00 | $15,000.00 | $15,000.00 | $2,200.00 | $2,200.00 | $14,000.00 | $14,000.00 | $395.00 | $395.00 | $15,000.00 | $15,000.00 | $55,000.00 | $55,000.00 |
| 24 | Asphalt Pavement Saw Cutting (10 Inch Depth) | 400 | FT | $5.00 | $2,000.00 | $9.65 | $3,860.00 | $9.00 | $3,600.00 | $24.00 | $9,600.00 | $8.00 | $3,200.00 | $11.00 | $4,400.00 | $6.00 | $2,400.00 | $4.25 | $1,700.00 |
| 25 | Clearing and Grubbing | 1 | LS | $15,000.00 | $15,000.00 | $7,350.00 | $7,350.00 | $32,000.00 | $32,000.00 | $19,000.00 | $19,000.00 | $46,000.00 | $46,000.00 | $9,700.00 | $9,700.00 | $10,000.00 | $10,000.00 | $50,000.00 | $50,000.00 |
| 26 | General Excavation | 13025 | CUYD | $16.00 | $208,400.00 | $12.10 | $157,602.50 | $27.00 | $351,675.00 | $23.00 | $299,575.00 | $18.20 | $237,055.00 | $20.20 | $263,105.00 | $50.00 | $651,250.00 | $33.90 | $441,547.50 |
| 27 | Stone Embankment | 21210 | TONS | $30.00 | $636,300.00 | $36.60 | $776,286.00 | $28.00 | $593,880.00 | $33.00 | $699,930.00 | $39.65 | $840,976.50 | $36.05 | $764,620.50 | $60.00 | $1,272,600.00 | $36.10 | $765,681.00 |
| 28 | 18 Inch Subgrade Stabilization | 25 | SQYD | $50.00 | $1,250.00 | $81.00 | $2,025.00 | $65.00 | $1,625.00 | $90.00 | $2,250.00 | $43.00 | $1,075.00 | $225.00 | $5,625.00 | $140.00 | $3,500.00 | $130.00 | $3,250.00 |
| 29 | Riprap Geotextile, Type 2 | 3500 | SQYD | $3.00 | $10,500.00 | $2.60 | $9,100.00 | $2.40 | $8,400.00 | $4.00 | $14,000.00 | $3.00 | $10,500.00 | $1.62 | $5,670.00 | $10.00 | $35,000.00 | $5.00 | $17,500.00 |
| 30 | Subgrade Geotextile | 700 | SQYD | $2.25 | $1,575.00 | $1.75 | $1,225.00 | $1.75 | $1,225.00 | $4.00 | $2,800.00 | $2.30 | $1,610.00 | $1.03 | $721.00 | $10.00 | $7,000.00 | $3.00 | $2,100.00 |
| 31 | Riprap Basins | 1 | EA | $2,250.00 | $2,250.00 | $1,600.00 | $1,600.00 | $2,000.00 | $2,000.00 | $1,675.00 | $1,675.00 | $1,600.00 | $1,600.00 | $1,500.00 | $1,500.00 | $3,000.00 | $3,000.00 | $5,000.00 | $5,000.00 |
| 32 | Mainline Video Inspection | 172 | FT | $17.00 | $2,924.00 | $35.00 | $6,020.00 | $20.00 | $3,440.00 | $25.00 | $4,300.00 | $30.00 | $5,160.00 | $17.50 | $3,010.00 | $5.00 | $860.00 | $30.00 | $5,160.00 |
| 33 | 30 Inch Culvert Pipe, Over 20 FT Depth | 172 | FT | $330.00 | $56,760.00 | $212.00 | $36,464.00 | $400.00 | $68,800.00 | $1,150.00 | $197,800.00 | $550.00 | $94,600.00 | $2,193.00 | $377,196.00 | $500.00 | $86,000.00 | $6,250.00 | $1,075,000.00 |
| 34 | Sloped End Sections, 30 Inch | 2 | EA | $500.00 | $1,000.00 | $1,950.00 | $3,900.00 | $1,200.00 | $2,400.00 | $650.00 | $1,300.00 | $450.00 | $900.00 | $2,810.00 | $5,620.00 | $2,000.00 | $4,000.00 | $5,500.00 | $11,000.00 |
| 35 | Safety End Sectins, 30 Inch | 2 | EA | $4,250.00 | $8,500.00 | $2,125.00 | $4,250.00 | $9,000.00 | $18,000.00 | $1,600.00 | $3,200.00 | $1,000.00 | $2,000.00 | $3,077.00 | $6,154.00 | $7,500.00 | $15,000.00 | $3,500.00 | $7,000.00 |
| 36 | Trench Resurfacing | 40 | SQYD | $230.00 | $9,200.00 | $190.00 | $7,600.00 | $120.00 | $4,800.00 | $380.00 | $15,200.00 | $90.00 | $3,600.00 | $380.00 | $15,200.00 | $600.00 | $24,000.00 | $150.00 | $6,000.00 |
| 37 | Cold Plan Pavement Removal, 3 Inches Deep | 250 | SQYD | $30.00 | $7,500.00 | $44.92 | $11,230.00 | $72.00 | $18,000.00 | $34.00 | $8,500.00 | $29.00 | $7,250.00 | $42.24 | $10,560.00 | $50.00 | $12,500.00 | $18.00 | $4,500.00 |
| 38 | Aggregate Base and Shoulders | 1310 | TON | $32.00 | $41,920.00 | $56.00 | $73,360.00 | $42.00 | $55,020.00 | $65.00 | $85,150.00 | $29.00 | $37,990.00 | $50.00 | $65,500.00 | $75.00 | $98,250.00 | $130.00 | $170,300.00 |
| 39 | Level 3, 1/2 Inch ACP Mixture (64-22 oil) | 800 | TON | $245.00 | $196,000.00 | $195.00 | $156,000.00 | $185.00 | $148,000.00 | $200.00 | $160,000.00 | $165.00 | $132,000.00 | $144.00 | $115,200.00 | $200.00 | $160,000.00 | $202.60 | $162,080.00 |
| 40 | Delineators, Type 1 | 2 | EA | $125.00 | $250.00 | $160.00 | $320.00 | $150.00 | $300.00 | $240.00 | $480.00 | $120.00 | $240.00 | $126.00 | $252.00 | $250.00 | $500.00 | $500.00 | $1,000.00 |
| 41 | Culvert Drainage Markers, Type 1 | 2 | EA | $85.00 | $170.00 | $110.00 | $220.00 | $150.00 | $300.00 | $240.00 | $480.00 | $120.00 | $240.00 | $86.00 | $172.00 | $85.00 | $170.00 | $85.00 | $170.00 |
| 42 | Bi-Directional Yellow Type IAR Markers | 20 | EA | $12.00 | $240.00 | $15.00 | $300.00 | $13.00 | $260.00 | $70.00 | $1,400.00 | $45.00 | $900.00 | $12.00 | $240.00 | $12.00 | $240.00 | $12.00 | $240.00 |
| 43 | Thermoplastic, Sprayed, Surface, Non-Profiled | 900 | FT | $3.85 | $3,465.00 | $5.00 | $4,500.00 | $5.00 | $4,500.00 | $6.00 | $5,400.00 | $4.00 | $3,600.00 | $4.00 | $3,600.00 | $3.85 | $3,465.00 | $3.85 | $3,465.00 |
| 44 | Permanent Seeding | 0.5 | ACRE | $12,000.00 | $6,000.00 | $15,230.00 | $7,615.00 | $7,500.00 | $3,750.00 | $10,500.00 | $5,250.00 | $14,000.00 | $7,000.00 | $12,000.00 | $6,000.00 | $12,000.00 | $6,000.00 | $12,000.00 | $6,000.00 |
| 45 | Topsoil | 470 | CUYD | $68.00 | $31,960.00 | $86.30 | $40,561.00 | $52.00 | $24,440.00 | $102.00 | $47,940.00 | $78.00 | $36,660.00 | $69.00 | $32,430.00 | $68.00 | $31,960.00 | $24.00 | $11,280.00 |
| TOTAL | $ 1,570,568.00 | $ 1,648,947.50 | $1,717,032.50 | $ 1,897,781.00 | $ 1,925,844.00 | $2,037,121.00 | $2,962,242.50 | $3,413,356.90 |