Specifications Bryce Canyon Rehabilitate Main Water Systems at East Creek and Yovimpa Point National Park Service

Contract Number: 140P2021D0001 PMIS Number: BRCA 318695

Final Construction Documents July 13, 2026

BRCA 318695 01 07 00 - 1

112723 SEALS PAGE

Bryce Canyon National Park, BRCA 318695

SECTION 01 07 00 – SEALS PAGE

Prepared by Eric R. Schallert (Civil) (Div’s/Sec’s:

Div 01, Div 02, 31 23 00, 32 92 19, 33 05 07, 33 11 00, 33 11 00-13, 33 30 00

Prepared by Michael D. Clark (Civil) (Div’s/Sec’s: Div 03, Div 05, 31 23 16-16, 33 05 16-13)

Prepared by Nicholas J. Bath (Mechanical) (Div’s/Sec’s: Division 26 and Division 40)

29964.13.00 TABLE OF CONTENTS

ms2352 SECTION 00 01 10 - Page 1

BRYCE CANYON REHABILITATE MAIN WATER

SYSTEMS AT EAST CREEK AND YOVIMPA POINT

NATIONAL PARK SERVICE

DENVER, COLORADO

CONTRACT NO: 140P2019F0280

PMIS NO: BRCA 318695

SPECIFICATIONS GROUP

GENERAL REQUIREMENTS SUBGROUP

Resp.

Charge Section Title Page

DIVISION 01 GENERAL REQUIREMENTS

ERS 01 11 00 Summary of Work 1 to 6 ERS 01 26 01 Contract Modification Procedures 1 to 6 ERS 01 27 00 Definition of Contract Line Items 1 to 4 ERS 01 31 00 Project Management and Coordination 1 to 10 ERS 01 32 16 Construction Schedule 1 to 10 ERS 01 32 33 Photographic Documentation 1 to 2 ERS 01 33 23 Submittal Procedures 1 to 7 ERS 01 35 13.22 Archeological Protection - RC 1 to 4 ERS 01 35 23 Safety Requirements 1 to 5 ERS 01 40 00 Quality Requirements 1 to 8 ERS 01 42 00 Reference Standards 1 to 19 ERS 01 50 00 Temporary Facilities and Controls 1 to 9 ERS 01 55 00 Vehicular Access and Parking 1 to 6 ERS 01 57 19.12 Noise and Acoustics Management 1 to 3 ERS 01 57 23 Temporary Storm Water Pollution Prevention (SWPP), Under-an-Acre Pollution Prevention (UPP) 1 to 7 ERS 01 67 00 Product Requirements 1 to 9 ERS 01 73 29 Cutting and Patching 1 to 4 ERS 01 73 40 Execution 1 to 7 ERS 01 74 19 Construction Waste Management and Disposal 1 to 8 ERS 01 77 00 Closeout Procedures 1 to 5 ERS 01 78 23 Operation and Maintenance (O&M) Data 1 to 10 ERS 01 78 23A Closeout and Operation & Maintenance (O&M) Requirements 1 to 2 ERS 01 79 00 Demonstration & Training 1 to 3

FACILITY CONSTRUCTION SUBGROUP

DIVISION 02 EXISTING CONDITIONS

ERS 02 41 00 Demolition 1 to 14

DIVISION 03 CONCRETE

MDC 03 00 10 Concrete Work 1 to 11

DIVISION 05 METALS

MDC 05 50 00 Metal Fabrications 1 to 8

SITE AND INFRASTRUCTURE SUBGROUP

DIVISION 26 ELECTRICAL

NJB 26 05 00 Common Work Results for Electrical 1 to 21 NJB 26 05 33 Above-Grade Raceway 1 to 6 NJB 26 05 43 Below-Grade Raceway 1 to 6

TABLE OF CONTENTS 29964.13.00

Page 2 - SECTION 00 01 10 ms2352

Resp.

Charge Section Title Page

DIVISION 31 EARTHWORK

ERS 31 23 00 Excavation and Fill 1 to 12 MDC 31 23 16-16 Structural Excavation and Backfill 1 to 6

DIVISION 32 EXTERIOR IMPROVEMENTS

ERS 32 92 19 Seeding 1 to 3

DIVISION 33 UTILITIES

ERS 33 05 07 Horizontal Directional Drilling 1 to 18 MDC 33 05 16-13 Precast Concrete Utility Structures 1 to 4 ERS 33 11 00 Water Utility Distribution Piping 1 to 9 ERS 33 11 00-13 HDPE Water Utility Distribution Piping 1 to 7 ERS 33 30 00 Sanitary Sewerage Utilities 1 to 7

PROCESS EQUIPMENT SUBGROUP

DIVISION 40 PROCESS INTEGRATION

NJB 40 61 96 Process Control Descriptions 1 to 4 NJB 40 70 00 Instrumentation for Process Systems 1 to 5 NJB 40 70 00-19 Sample Calibration Report 1 to 3 Transmitter Calibration 1 General Analog Device, Type 1

BRCA 318695 01 11 00 - 1

112723 SUMMARY OF WORK

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 11-27-23

By using NPS DSC Division 1 Specifications, you acknowledge you read, understand, and will format edits according to NPS DSC Division 1 Specifications Instructions.

Bryce Canyon National Park, BRCA 318695

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Construction Contractor Use of Site

5. Public Use of Site

6. Occupancy Requirements for Buildings

7. Conduct of Operations

8. Work Restrictions

9. Special Construction Requirements

10. Soils Investigation Report

11. Additional Reports

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Bryce Canyon National Park is a national park located in Utah. It is part of the

Colorado Plateau geographic province and straddles the southeastern edge of the Paunsaugunt

Plateau. The park is about 270 miles south of Salt Lake City and 260 miles northeast of Las

Vegas, on the western edge of the Colorado Plateau. The closest major airports are in Las Vegas

(LAS), Nevada and Salt Lake City (SLC), Utah, each approximately 270 miles from the park.

There are smaller airports in Cedar City (CDC), Utah (80 miles) and St. George (SGU), Utah

(125 miles). There are multiple ways to access the park, and all will require taking State Highway

UT-12 to connect with UT-63 south to Bryce Canyon National Park. The visitor center sits 1 mile inside the park boundary. The park is open year-round. Roads are plowed and sanded after heavy snowstorms. Some roads may be temporarily closed during and immediately following winter storms, but the park is always open.

B. The Work consists of:

1. Rehabilitate and/or replace obsolete, critical system components of the East Creek water system.

2. Water distribution system improvements include replacing services and upsizing water mains for structural fire protection in several visitor use areas.

BRCA 318695 01 11 00 - 2

3. Replacement of Mission 66 Housing area sewer laterals behind the lodge – only 4” and

6” sewer laterals were identified for replacement up to the 8” sewer main.

4. Decommission and demolish obsolete assets including the Yovimpa Point Water System.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work shall be conducted in phases directly coordinated with NPS Facility Management to not impact park operations. Water mains cannot be shut down during the entire duration of the project, and any temporary shutdowns needed must be coordinated 5 days in advance.

1.4 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate Construction Contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate

Work of this Contract with work performed under separate contracts.

B. Preceding Work: Coordinate with Government on any preceding work performed under separate contract.

1. To be determined with NPS.

C. Concurrent Work: Coordinate with Government on any concurrent work performed under separate contract.

1. To be determined with NPS.

D. Future Work: Coordinate with Government on any future work performed under separate contract.

1. To be determined with NPS.

1.5 CONSTRUCTION CONTRACTOR USE OF SITE

A. General: Construction Contractor shall have full use of the site for construction operations during the construction period. Construction Contractor's use of the site is limited only by the

Government's right to perform work or to retain other construction Contractors on portions of

Project.

B. General: Construction Contractor shall have limited use of site for construction operations. Limit use of premises to areas within Construction limits indicated on drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to areas within Construction limits indicated on drawings for East Creek, Main Visitor’s Center Area, the Lodge Area and Yovimpa Point.

2. Limit site disturbance, including earthwork and clearing of vegetation, to the limits of disturbance boundaries shown on the plans.

BRCA 318695 01 11 00 - 3

C. Storage of Materials: Confine storage of materials to areas as approved and coordinated with

Park Maintenance staff and be approved by COR.

D. Parking: Confine parking to areas as approved and coordinated with Park Maintenance staff and be approved by COR.

E. Stockpiling: Confine stockpiling to staging areas as approved and coordinated with Park

Maintenance staff and be approved by COR.

F. Preservation of Natural Features:

1. Prevent damage to natural surroundings.

2. Within construction limits, erect fenced enclosures around trees to be preserved to protect crowns from contact by equipment, to preserve roots and soil conditions, and to identify tree protection zones (TPZ) in which soil disturbance is not permitted and activities are restricted unless otherwise approved by CO. Remove all tree protection prior to final acceptance.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction. Restitution plan for any trees damaged without approval is linked here:

https://doimspp.sharepoint.com/:w:/r/sites/nps-dsc-DC-

BRCA318695_LRF/Shared%20Documents/General/Compliance/Vegetation/Tree%20P rotection/BRCA%20318695%20General%20Vegetation%20Protection%20Requiremen ts.docx?d=wc19867dce2e84d34b2bee3d0ab7939ba&csf=1&web=1&e=aVg0PK

4. Protect roots over 1 inch in diameter which are severed during construction operations.

Do not allow the tree roots to dry out while exposed. Immediately cover exposed roots with wet burlap or plastic bags to keep roots moist until roots can be covered with dirt.

Rebury the roots as soon as possible.

5. Do not fasten ropes, cables, or guys to existing trees.

6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

G. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to

Government employees, park visitors, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

H. Construction Camp: Establishment of a construction camp within the park will not be permitted.

I. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.

J. Ensure all construction vehicles and equipment (prime, sub, deliveries, etc.) are cleaned of soil, plant material, and other debris prior to entering park. Since construction will span the USFS

BRCA 318695 01 11 00 - 4

and NPS boundary, equipment must be cleaned prior to crossing into NPS lands. PM or delegated

Park Representative must inspect equipment at an agreed location outside of the park. This applies to any vehicles or equipment that will travel off designated roadways or partake in excavation activities. If equipment is stored or travels outside of the park for any period of time, it will be up to the discretion of the CO, PM, or Park Representative to require inspection upon reentry to the park. Typically, if vehicles or equipment are kept on roadways and not used on other external projects while outside the park, reentry inspections are not necessary.

K. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.

1.6 PUBLIC USE OF SITE

A. The construction area defined for that phase or portion of work coordinated with Park

Maintenance staff will be closed to the public during construction and be approved by COR.

B. Construction Contractor shall conduct his operations to ensure the least inconvenience to public.

Road closures may be permitted, when required, upon specific approval of Contracting Officer.

1.7 CONDUCT OF OPERATIONS

A. Construction Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 07:00 a.m. to 05:00 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: Obtain approval in advance from Park Facility Maintenance and coordinate accordingly to not impact park operations.

2. Early Morning Hours: Obtain approval in advance from Park Facility Maintenance and coordinate accordingly to not impact park operations. Consideration of noisy work should be taken into consideration and reserved for normal working hours.

3. Hours for Horizontal Directional Drilling:

4. All drilling activities should be reserved for normal working hours coordinated in advance with Park Facility Maintenance to not impact park operations or the visitor experience

(noisy activities in housing areas and campgrounds are limited to occur approximately

8:00 AM – 5:00 PM).

BRCA 318695 01 11 00 - 5

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Construction Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the

Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than three (3) business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours and length of Utility Shutdowns: Reserve planned utility shutdowns during periods of anticipated low visitors for durations and outage extents as determined as approved by the CO based on conditions.

D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within

25 feet of entrances, operable windows, or outdoor air intakes. Tobacco use and vaping are restricted to only those designated areas approved in advance by Park Facility Management.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Management and Communication Software: Software administered by NPS shall be used to manage communication and document sharing during construction.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using

NPS project management and communication software.

B. Coordinate with Park Facility Management on special requirements such as limited access due to seasonal shutdown, park activities and limited access periods.

1.10 SOILS INVESTIGATION REPORT

A. The report Geotechnical Investigation Survey Report (dated July 2024), prepared by Stanley-

DOWL Joint-Venture is available, an appendix with this package.

B. In case of conflict between report and drawings or specifications, the drawings and specifications govern.

BRCA 318695 01 11 00 - 6

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

BRCA 318695 01 26 01 - 1

012721 CONTRACT MODIFICATION PROCEDURES

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

Bryce Canyon National Park, BRCA 318695

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager (PM), Assistant Project Manager

BRCA 318695 01 26 01 - 2

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.

The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

BRCA 318695 01 26 01 - 3

1) Social Security

2) Medicare

3) Workers Compensation – Policy and company calculation to be made available.

4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.

5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.

Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank

BRCA 318695 01 26 01 - 4

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. Labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for work being performed.

2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.

3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|

BRCA 318695 01 26 01 - 5

a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.

6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.

8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.

Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit…………………….7%

2. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.

BRCA 318695 01 26 01 - 6

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 012601

BRCA 318695 01 27 00 - 1

012721 DEFINITION OF CONTRACT LINE ITEMS

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21

Bryce Canyon National Park, BRCA 318695

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 0001 Raw Water Main from Well House to Water Storage Tanks

1. This item consists of the following major tasks:

a. Install new raw water main as delineated in construction documents with the following clarifications on performance of work:

1) Connect existing wells to new valve vault with HDPE pipes via open cut construction.

2) Construct HDPE raw water main via Horizontal Directional Drilling (HDD) from new valve vault to Science Hill, and via open cut construction from the end of the HDD to the Water Storage tanks.

3) Construct combination air/vacuum relief valves and isolation valves per the plans.

2. Measurement for payment will be progress based on schedule of values reflecting features of work included for specific contract line item number.

3. Payment will be made at the contract lump sum price.

BRCA 318695 01 27 00 - 2

B. Contract Line Item Number 0002 Potable Water Supply to Visitor’s Center (Main Road).

1. This item consists of the following major tasks:

a. Install new potable water transmission system piping as delineated in construction documents with the following clarifications on performance of work:

1) Construct HDPE raw water main via Horizontal Directional Drilling (HDD).

2) Construct HDPE raw water main via open cut methods.

3) Construct combination air/vacuum relief valves and isolation valves per the plans.

4) Make connections to fire hydrants and tertiary water mains and services.

2. Measurement for payment will be progress based on schedule of values reflecting features of work included for specific contract line item number.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item Number 0003 Potable Water Supply to Lodge Area

1. This item consists of the following major tasks:

a. Install new potable water distribution system piping as delineated in construction documents with the following clarifications on performance of work:

1) Construct HDPE raw water main via Horizontal Directional Drilling (HDD).

2) Construct HDPE raw water main via open cut methods.

3) Construct combination air/vacuum relief valves and isolation valves per the plans.

4) Make connections to fire hydrants, flushing hydrants, and tertiary water mains and services.

2. Measurement for payment will be progress based on schedule of values reflecting features of work included for specific contract line item number.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item Number 0004 OPTION A

1. Water Supply to Old Residential Area and Residence Halls

a. Install new potable water distribution system piping as delineated in construction documents with the following clarifications on performance of work:

1) Construct HDPE water main via open cut methods.

2) Make connections to fire hydrants, flushing hydrants, and tertiary water mains and services.

E. Contract Line Item Number 0005 OPTION B

1. Water Supply to North Campground Area Loop D

a. Install new potable water distribution system piping as delineated in construction documents with the following clarifications on performance of work:

BRCA 318695 01 27 00 - 3

1) Construct HDPE water main via open cut methods.

2) Make connections to fire hydrants, flushing hydrants, and tertiary water mains and services

F. Contract Line Item Number 0006 OPTION C

1. Water Supply to Maintenance Yard

a. Install new potable water distribution system piping as delineated in construction documents with the following clarifications on performance of work:

1) Construct HDPE water main via open cut methods.

2) Make connections to fire hydrants, flushing hydrants, and tertiary water mains and services

G. Contract Line Item Number 0007 OPTION D

1. Sanitary Sewer laterals to Residences

a. Install new potable water distribution system piping as delineated in construction documents with the following clarifications on performance of work:

1) Construct PVC sanitary sewer lateral from residences to existing sanitary sewer via open cut methods.

H. Contract Line Item Number 0008 OPTION E

1. Water Supply at Water Storage Tanks to replace AC pipe

a. Install new water system piping as delineated in construction documents with the following clarifications on performance of work:

1) Remove existing AC piping.

2) Replace with HDPE water main via open cut methods.

I. Contract Line Item Number 0009 OPTION F

1. Water System Demo at Yovimpa Point

a. Demolish existing water system piping and structures as delineated in construction documents with the following clarifications on performance of work:

1) Remove and dispose of galvanized water service.

2) Remove and dispose of structures and related concrete slabs at both ends of the water service above per the plans.

BRCA 318695 01 27 00 - 4

J. Contract Line Item Number 0010 OPTION G

1. Water Supply at Mixing Circle

a. Install new water system piping as delineated in construction documents with the following clarifications on performance of work:

1) Construct HDPE water main via open cut methods from existing water main to standpipe location.

2) Install standpipe per the plans and details.

a) Measurement for payment will be progress based on schedule of values reflecting features of work included for specific contract line item number.

b) Payment will be made at the contract lump sum price.

K. Contract Line Item Number 0011 OPTION H

1. Archeological Monitoring

2. This item consists of the following major tasks:

a. Archeological Monitor will observe ground-disturbing site work, including construction of temporary facilities, at archeologically sensitive areas, from a safe location mutually agreed by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.

b. If Archeological Monitor discovers resources, immediate relocation of work to a non-sensitive area may be required for Monitor to identify and document resources and, if necessary, develop an appropriate mitigation plan. While Archeological Monitor is documenting resources in sensitive areas, Contractor shall relocate work to non-sensitive areas where monitoring is not normally required.

c. If resources are discovered while Archeological Monitor is absent, ground disturbing activities must stop immediately and the park's Cultural Resources Specialist. If archeological resources are identified, excavation will not resume until resources are recorded.

d. Discovered cultural resources are turned over to the park immediately upon discovery.

3. Measurement for payment will be progressed based on percentage of work completed for specific contract line-item number.

4. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

BRCA 318695 01 31 00 - 1

112723 PROJECT MANAGEMENT AND COORDINATION

NPS DSC Division 1 Specifications National Park Service (NPS) - Denver Service Center (DSC) | 11-27-23

Bryce Canyon National Park, BRCA 318695

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination

3. Submittals

4. Coordination Drawings

5. Requests for Information (RFIs)

6. NPS Project Management and Communication Software

7. Project Meetings

8. Environmental Coordination

9. Permits

B. Related Requirements:

1. Section 01 32 16 "Construction Schedule" for preparing and submitting Construction Contractor’s construction schedule.

2. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.

1.2 DEFINITIONS

A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits

1.3 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm

BRCA 318695 01 31 00 - 2

1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Construction Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other Construction Contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:

1. Preparation of Construction Contractor Construction Schedule

2. Preparation of the Schedule of Values

3. Installation and removal of temporary facilities and controls

4. Delivery and processing of submittals

5. Progress meetings

6. Permit requirements

7. Pre-installation conferences

8. Project closeout activities

9. Commissioning activities

1.4 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.

BRCA 318695 01 31 00 - 3

d. Show location and size of access doors required for access to concealed dampers, valves, and controls.

e. Indicate required installation sequences.

2. Refer to individual Sections for Coordination Drawing requirements for Work in those Sections.

3. Follow NPS DSC Electronic Drawing Standards. See CAD/BIM (Computer Aided Design/Building Information Modeling) & Drafting Standards page > DSC Requirements section.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

2. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

3. Mechanical and Plumbing Work:

a. Sizes and bottom elevations of piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as valves, access doors, cleanouts and electrical distribution equipment.

4. Electrical Work:

a. Runs of vertical and horizontal conduit 1-1/4 inches in diameter and larger.

b. Light fixture, exit light, emergency battery pack, smoke detector, and other fire-alarm locations.

c. Panel board, switch board, switchgear, transformer, busway, generator, and motor control center locations.

d. Location of pull boxes and junction boxes, dimensioned from column center lines.

5. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Construction Contractor's responsibility. If Contracting Officer determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Construction Contractor, who shall make changes and resubmit.

6. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."

C. Coordination Digital Data Files: Prepare coordination digital data files according to:

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.

3. Contracting Officer will furnish Construction Contractor one set of digital data files ( AutoCAD.dwg) of Drawings for use in preparing coordination digital data files.

a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCAD.dwg.

https://www.nps.gov/dscw/ds-cad-bim-drafting.htm https://www.nps.gov/dscw/ds-cad-bim-drafting.htm

BRCA 318695 01 31 00 - 4

D. Division 1 documents:

1. Letter designating Project Superintendent

2. Construction Schedule

3. A Comprehensive Schedule of Values

4. Accident Prevention Plan

5. A List of Subcontractors for this project

6. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.

7. Certificates of Insurance and Standard Form SF1413 for Contactor and all Subcontractors

8. Waste Management Plan

9. Quality Control Plan

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP)

11. Construction Contractor Commissioning Plan

12. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit

b. Agency(ies) with Jurisdiction issuing the permit

c. Information required from Government to complete permit application

E. Provide items listed to Contracting Officer at least one week prior to Pre-Construction Conference, or as directed by Contracting Officer.

1. Failure to submit items may result in:

a. Construction conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will consider other contractual remedies.

b. Work shall not commence until written Notice to Proceed has been issued and Certificates of Insurance and SF1413 documents are received for Construction Contractor and all Subcontractors.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Construction Contractor shall prepare and submit an RFI utilizing form created on NPS project management and communication software.

1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Construction Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Date

3. RFI subject

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Construction Contractor's suggested resolution: If suggested resolution impacts Contract

Time or Contract Sum, Construction Contractor shall state impact in RFI.

8. Construction Contractor's signature

BRCA 318695 01 31 00 - 5

9. Requested date for response

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete and submit on NPS project management and communication software.

D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Construction Contractor's means and methods.

d. Requests for coordination information already indicated in Contract Documents.

e. Requests for adjustments in Contract Time or Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.

3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.

1.6 PROJECT MANAGEMENT AND COMMUNICATION SOFTWARE

A. Use to manage project communication and document sharing during contract period on:

1. Project directory

2. Project correspondence

3. Meeting agendas and minutes

4. Contract modifications forms and logs

5. RFI form and processing

6. Task and issue management

7. Photo documentation

8. Baseline schedule, schedule updates and calendar management

9. Submittal form and processing

10. Payment coordination documentation

11. Reminder and tracking functions

12. Archiving functions

13. Notification of submittal and RFI statuses and current responsible party

14. Permits and addendums

BRCA 318695 01 31 00 - 6

B. Some documents are not suitable to be shared using NPS project management and communication software. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared and shall be coordinated with project team as appropriate.

1.7 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Construction Contractor. Meeting agenda will include the following as a minimum:

1. Roles & Responsibilities / Lines of Authority

2. Park rules and regulations

3. Jobsite Safety

4. Resolution of comments on required Division 1 documents

5. Coordination of Subcontractors

6. Labor law application

7. Modifications

8. Payments to Construction Contractor

9. Payroll reports

10. Contract time

11. Liquidated damages

12. Construction Contractor Performance Evaluation

13. Display of Hotline posters

14. Notice to proceed

15. Correspondence procedures

16. NPS project management and communication software

17. Acceptance/rejection of work

18. Progress meetings

19. Submittal procedures

20. NPS Final Accessibility Inspection

21. Environmental requirements

22. Permit requirements

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials

26. Value engineering

27. Schedule of Values

B. Progress Meetings: Contracting Officer will schedule weekly meetings with Construction Contractor.

1. Attendees: In addition to Government Representatives, each Construction Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented.

Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:

BRCA 318695 01 31 00 - 7

a. Approval of minutes of previous meetings

b. Submittal status

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI)…