This is Amendment 4 to Solicitation 140P2026B0003 for the Curecanti National Recreation Area Water & Wastewater System Rehabilitation project, issued by the National Park Service (NPS) Denver Service Center on September 28, 2026. The amendment provides Question & Answer responses through September 28, 2026, and an updated Schedule B (Price Schedule) with the correct Solicitation number. The bid opening date remains October 7, 2026 at 2:00 PM Mountain Time, with all other terms and conditions of the solicitation remaining unchanged.
The solicitation requires rehabilitation of water and wastewater infrastructure at Elk Creek, Lake Fork, and Iola areas within Curecanti National Recreation Area. Work includes nine contract line items (CLINs) structured as five base CLINs and four option CLINs, all priced on a lump-sum basis: (1) Elk Creek Sanitary System Repair, (2) Elk Creek Water Supply Repair, (3) Complete SCADA System Replacement, (4) Replace Elk Creek Marina Lift Station in kind, (5) Archaeological Monitoring, with options for (6) Elk Creek Gravity Sewer, (7) Elk Creek Lagoon Work, (8) Elk Creek Lift Station Replacement, and (9) Lake Fork Complete Scope. The estimated contract value exceeds $10 million. The performance period is 550 calendar days. Key requirements include HDPE water lines per Section 33 11 00-13, replacement of three lagoon liners with 60 mil HDPE per geomembrane manufacturer specifications, SCADA system compliance with performance-based specifications accommodating multiple manufacturers (Allen-Bradley, Siemens, GE, Schneider Electric), phased construction to maintain park operations, archaeological monitoring at sensitive areas, third-party testing/quality control by separate qualified individuals, and comprehensive utility work including HDD installations. The contractor is responsible for all permitting, site preparation, ARPA permit acquisition, and standard Division 01 requirements. Bidders must acknowledge receipt of the amendment prior to the October 7, 2026 submission deadline and comply with Section 01 requirements before Notice to Proceed issuance.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Vicki Freese-supler
See continuation page
NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
DOI, NPS, DSC Contracting Services 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
PDS
PDS
140P2026B0003
09/28/2026
08/26/2026
1 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P2026B0003/0004
CURE 318472 - Rehabilitation of Water &
Wastewater System - Curecanti National
Recreation Area
The purpose of this amendment is to provide for the following information:
1. To provide for the Question & Answer
Responses thru 09/28/2026.
2. To provide an updated Schedule B - Price
Schedule - with correct Solicitation
#140P2026B0003.
The date/time for the Bid Opening has been scheduled for October 7, 2026 at 2:00 Mountain
Time. Call in details and meeting details remain unchanged from the information provided through Amendment #1.
All other terms and conditions of the
Solicitation remain unchanged and in full force and effect.
Solicitation 140P2026B0003
Question No. Sheet or Reference Question Response Amendment
1 Can the use of Siemens hardware and WinCC be utilized in lieu of the use of Allen Bradley as specified in the construction specifications?
The construction specification does not require Allen- Bradley exclusively. Division 40 accommodates multiple SCADA hardware and software manufacturers, including, but not limited to Allen-Bradley, Siemens, GE and Schneider Electric, provided the proposed system meets the specified performance and compatibility requirements. The Division 40 specifications are performance based and accommodate alternate SCADA hardware and software platforms provided the proposed equipment meets the specified functional, performance, compatibility, communication and integration requirements. Bidders are not precluded from proposing an equivalent solution under the current specification. Any equivalent solution would need to demonstrate compliance with the specified salient characteristics and be evaluated through the submittal process.
2 Can key personnel serve in dual positions? I.e. Superintendent - also service as Quality Control? Yes 4
3 What is the gallon limitation for use of water - especially when utilizing water for flushing and chlorination purposes?
Park Water use: flushing, disinfection and other potable uses only.
Non-potable water availability contingent on drought conditions and availability; potential to utilize surface water of the lake if coordinated with CODEQ and BOR;
contractor to coordinate.
4 Does insulation presently covering existing piping need to be removed? Yes 4
5 Are offerors required to submit General References with their proposal? If so, is there a template? Yes - Template was uploaded to SAM.gov 4
6 Are offerors required to submit Section K with their proposal? Yes 4
7 What is the period of performance? 550 Calendar days 4
8 Could we please get a copy of the radio path survey that was completed prior to the project going out for bid?
This information will be shared with the awardee after award. 4
Question No. Sheet or Reference Question Response Amendment
9 Did the engineers confirm that the Aviat Aprisa SR+ radios will handle the required Allen Bradley data transfer rates?
Neither Allen Bradley nor Aviat Aprisa SR+ are specific requirements of the project – they were used as basis of design. The design does not seek to prescribe any particular make or model (PLC or radio) – the contractor may submit any equipment they feel best suits the needs of the system.
DOR is not aware of a published “data transfer rate” for Allen Bradey PLCs inherent to the model or ethernet IP protocol – data transfer rate is primarily dependent on the amount of data and frequency of data being sent, which more is dependent on specific configuration and timing of messaging than a protocol or brand. The minimum data update rates specified (every 15-30 sec depending on the application) are not demanding of a high speed connection; payloads are expected to be on the order of kilobytes, not megabytes for daily SCADA functions. The SR+ is the basis of design used for the radio interference analysis report requested by NPS during design; this model exemplifies a modern digital radio with advanced modulation schemes that are expected to outperform the existing analog radios.
10 The solicitation lists the offer due date/time as "09/29/2026 1400 MD." Could you please confirm the applicable time zone for the proposal submission deadline? 2:00 p.m. Mountain Time 4
11 Good Morning, may I have the sign in sheet from the prebid meeting on 9-10? See Amendment 02 4
12 Could you please confirm whether bidders are required to submit references and, if so, what specific information is required?
Please refer to General Reference Sheet uploaded to SAM.gov. 4
Section C states bids are due by the date and time identified in SF 33 Block 9. Section D states bids must be received at the government's initial point of entry by 5:00 PM one working day prior to the due date. Please confirm whether 5:00 PM the preceding workday is a recommended submission time or the actual deadline for receipt of bids.
Yes in order to get through the various Government firewalls. The Government can not confirm receipt if Bidder waits till 2:00 p.m. submission.
14 C2.13 Sheet C2.13 indicates that the Northeast Lagoon with different call outs than the other lagoons. Can you confirm that all 3 of the lagoons on the sheet with cross hatching get replacement liners?
Confirmed, all three shaded lagoons are slated to have their membranes removed and replaced 4
15 The Visitor Center area and parking lot will require saw cutting and asphalt replacement. Are there any timeline restrictions for that work to take place.
See phasing plan in contract documents. Maintain pedestrian walkways between parking areas and the VC building can be established and maintained during construction.
16 The Boat Ramp launch area parking will require saw cutting and asphalt replacement for both sewer and water. Are there any schedule restrictions for that work?
See phasing plan in contract documents. Boat ramp work will need to take place in the Spring (Feb - April) and fall (Oct-Dec) to keep the area usable for boaters in the peak summer season
17 Are there any schedule restrictions for the campground area including campground roads being cut and replaced along with road cut restriction?
See phasing plan in contract documents. Closures will need to be scheduled to have only one loop closed at a time. Main road cuts will need to leave one lane open for campground traffic and be covered at night.
18 Is there any restriction to when and how long the dump station can be out of service during upgrades?
See phasing plan in contract documents. None known at this time 4
19 The Housing and Maintenance area will require some asphalt cutting and road closures. Is there any schedule restrictions for those areas?
See phasing plan in contract documents. Access will be preserved for residents, maintenance, and law enforcement staff. Minimal occupancy is Spring (Feb- April) and Fall (Oct - Nov)
20 Will construction water be available from the existing system? Addressed in Question 3 4
21 Does the QCM and tester have to be 2 separate individuals? Yes, third party testing by definition is a third party. See specification. 4
22 Does the Government have a preferred Direct Digital Control for HVAC Company? If so, please provide the contact information.
No. The Government does not have a preferred Direct Digital Control (DDC) contractor. Selection and coordination of subcontractors is the responsibility of the Contractor. The DDC system shall comply with the requirements of the contract documents.
23 Can one person "triple hat" as superintendent, SSHO and QC Manager? No 4
24 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project? No 4
25 Please provide the site visit attendee sign in sheet. This was published as Amendment 2, please refer to SAM.gov. 4
26 Is permitting required? Required permitting is required per Specification section 01 31 00, 1.4.D.12 and 1.9 4
27 Is any landscaping restoration required for this project? For example: topsoil, seeding and fertilizer. Refer to requirements of Section 32 92 19 4
28 Please provide staking data points for the project. This information will be shared with the awardee after award. 4
29 Are red, yellow and blue tops required? Contractor is responsible for all utility locates; park may be able to assist in location of park owned utility. 4
30 Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.
No hazardous materials testing was performed as part of the project design, and the Government is not aware of any information indicating the presence of asbestos-containing materials or lead-based paint within the project scope. Accordingly, no hazardous materials reports are available for this project.
Bidders shall base their proposals on the contract documents. If suspected hazardous materials are encountered during construction, the Contractor shall notify the Contracting Officer and proceed in accordance with the applicable contract requirements.
31 Are third party inspections required? See contract documents 4
32 When do you anticipate on site work starting? NTP will issue upon the contractor's sucessful completion of all division 01 requirements 4
33 Is traffic control required or can we shut down access to the area of construction?
See phasing plan in contract documents. Traffic control is required. Access to housing, maintenance and park operations buildings shall be maintained.
34 Is a SWPPP required? Yes, please refer to the Construction Specifications. 4
35 ` Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operatings in close proximity? Addressed in Question 3 4
36 What is the existing level of each lagoon to be dewatered? Contractor to verify on site. Varies. 4
37 In an effort to keep bids level across the board, is there a volume of solids to assume for lagoon solids to be hauled off? Contractor to verify on site. Varies. 4
38 Please provide drawings referenced in Notes 8 and 9 on page C2.13 on Part 6 of the drawings. Copies of the reference drawings to be provided in next amendment 4
39 Can you verify the max amount of construction water per day we are able to access. Addressed in Question 3 4
40 The plans call for water lines 2" and smaller to be HDPE and smaller to be HDPE but specs only reference K Copper. Please verify NPS preference.
Please refer to Section 33 11 00-13 for HDPE specifications. 4
41 Please verify if full time key personnel can wear multiple hats. Addressed in Question 2 and 23 4
42 Will there be any additional information/specifications released? Grinder pump, control panel, transfer switch, PVC liner, packaged lift station, mag meter, backflows, etc.
On Sheets C2.03 and C2.06 can we get clarification on the size of pipe? Starting with MH1.5 it shows all 4 in/outs as 6". Then, on Sheet C2.06 the little bubble pointing to the trunk line shows a 2 which is 4". All profiles show 6" though. During my takeoff I followed the profile and assumed that little run to be 6".
For sanitary sewer alignment SSAN5, existing sewer records show a portion of to be 4” and transition to 6” downstream at the next manhole or manhole after (unclear in records). Contractor to verify existing sewer sizes and replace sewer size in-kind.
44 Please clarify if all organics grubbed to be hauled and disposed off site.
Remove brush, rubbish, spoil, excess excavated material, and material not suitable for backfill to offsite location of Contractor’s choice
45 Will the Contractor's dedicated supervision have access to Park Employee housing units are available. No 4
46 Please verify the existence of blue board that will require disposal. Confirmed. 4
47 Please verify if the contractor can expect to be able to have full closures in the area of work.
See phasing plan in contract documents. Traffic control is required. Access to housing, maintenance and park operations buildings shall be maintained.
48 Can you please specify the scopes expected to be procured and/or performed by others?
Unless specifically identified in the contract documents, no portions of the project scope are intended to be procured or performed by others. The Contractor is responsible for providing all labor, materials, equipment, coordination, and incidental work necessary to complete the project in accordance with the contract documents.
49 Please explain the small business threshold at site walk presentation left some confusion as to who qualifies.
To be considered a small business, businesses must have gross receipts of $45M or less over the past 3 years.
50 Can you provide an extension to the bid date to continue to pass responses to subcontractors and allow material pricing to come in? extended to 10/7 4
51 Will you please the slide show, sign up sheet and other materials that were shown at the site walk? Please refer to Amendment posted to SAM.gov. 4
In the Drawings Part 6 document on sheet C2.13 the 3 lagoons to be relined are shown and on sheets C2.53 and C2.54 details for the liner system are shown. ON Sheet C2.13 General Note 5 it states provide new 60 mil HDPE liner in lagoons in accordance with CDPHE Colorado Design Criteria for Domestic Wastewater Treatment Works - WPC DR-1. In that referenced document it lists liner materials that may be considered; however, there is no mention of geotextile anywhere in the document. Therefore, we need clarification as to what type and thickness of geotextile the engineer is requesting as underlayment for the project.
Provide Geotextile per Geomembrane manufacturer recommendation. 4
Please clarify whether a single qualified individual may perform multiple project management roles required by Division 01. Specifically, may the project superintendent also serve as the Quality Contol Manager and/or Site Safety Supervisor, provided that individual meets all qualification requirements and can adequately perform the responsibilities of each position?
Please identify any Division 01 positions that are required to be staffed by separate, dedicated individuals.
Addressed in Question 2 and 23 4
Specification Section 01 50 00 states the Contracting Officer's Field Office shall be a separate structure from the contractor's office, while also stating that NPS may be able to provide space. Please confirm whether the contractor shall include furnishing the specified minimum 500 SF Contracting Officer/Government field office in its bid. If NPS will provide suitable existing space, plese confirm that the contractor will not be required to furnish the field office.
If the contractor is required to furnish it, please confirm the required duration, location, utilities, furnishings, internet/communications, cleaning and other services to be included.
Follow specification. NPS will not provide office space. 4
Section 01 35 13.22 - Archaeological Protection - please clarify the required extent of archaeological monitoring under CLIN 5 and Section 01 35 13.22. Is an SOI qualified archaeological monitor required during all ground disturbing activities throughout the project, or only during ground disturbance within designated archaeologically sensitive areas?
Additionally, if ground disturbing work occurs simultaneously at multiple locations, is a separate archaeological monitor required for each active work area, or may one monitor cover multiple concurrent operations where practicable?
Per specification 01 35 13 – Archaeological Protection, section 3.3, paragraph A. “Archeological Monitor will observe ground-disturbing site work, including construction of temporary facilities, at archeologically sensitive areas”. Additionally, Per specification 01 35 13 – Archaeological Protection, section 1.3, paragraph B “Where ground disturbance is planned, a SOI qualified archaeologist will monitor the activity to ensure the documentation of previously unidentified subsurface deposits or artifacts.” If excavation occurs simultaneously at more than one location, a monitor will be required at each location.
Please confirm that the Contractor's archaeological consultant is responsible for preparing and obtaining the required ARPA permit. Please also clarify how the Government intends to address the project schedule if ARPA permit approval is delayed beyond the Contractor's control after timely submission of a complete permit application. Will Notice to Proceed for ground disturbing activities be withheld until the permit is approved or will Government/agency review delay be treated as an execusable delay to the contract schedule?
Yes, contractor is responsible for preparing and obtaining the permit. NTP will not be issued until permit is approved.
The contract document establishes Phase 1 and Phase 2 sequencing requirements. During the pre-bid site visit, NPS indicated that actual reservoir levels, boat ramp availability, and park operations may permit modification of the planned sequence. Please confirm whether the Contractor may propose revisions to the Phase 1/Phase 2 sequence. Including concurrent work in multiple areas when such revisions improve construction efficiency while maintaing required park operations, subject to NPS/Contracting Officer approval.
Variances are subject to contracting officer approval. 4
Please clarify responsibility for final seeding and revegetation. Section 32 92 19 states in multiple locations that seeding, mulching, post seeding erosion control and maintenance are to be performed by others under the NPS revegetation plan, while also identifying certain primary construction contractor responsibilities. Please identify precisely which restoration, seedbed preparation, erosion control, seeding, watering, maintenance, reseeding and establishment activities are the responsbility of the contractor and which activities will be performed by others so all bidders price the same scope.
Work identified in specification 32 92 19 as "To be performed by others per NPS Revegetation Plan." will be addressed under a separate contract. Remaining work is included in this contract.
Please identify the areas available for Contractor staging and stockpiling at Elk Creek and Lake Fork. Please confirm whether equipment, pipe, bedding material, excavated material, and other construction materials may be staged longitudinally within the approved Limits of Disturbance where adequate space exists. Also confirm whether excess excavated material not required for backfill may be removed and legally disposed of offsite in a disposal area obtained by the Contractor without further NPS approval, except for materials specifically required to remain onsite or be reused.
Yes, material may be staged within the approved limits of distrubance. Spoil may be legally disposed of offiste without NPS approval.
The HDD alignments and designated HDD locations are mandatory, while Section 33 05 07 requires the Contractor to develop work, storage, staging, carrier-pipe assembly, access, and mud-circulation areas. Please confirm that sufficient workspace and construction access will be available at each indicated HDD entry and exit location for the drill rig, mud system, support equipment, pipe fabrication/stringing, and pullback operations. Where the existing Limits of Disturbance or access shown is insufficient for an approved HDD means and methods plan, will NPS consider temporary access or workspace adjustments that do not affect protected cultural or natural resources?
Contractor to confine work activities within the approved limits of distrubance. Adjustments to the LOD will be reviewed on a case by case basis.
Please clarify the correct solicitation and PMIS numbers to be used on all bid documents. The Curecanti solicitation package identifies Solicitation No. 140P2026B0003, while the Section B Contract Bid Schedule identifies Solicitation No. 140P2026B0004. Certain solicitation headers also reference CURE 318742, while the bid schedule and project documents reference CURE 318472. Please confirm the correct identifiers and issue a corrected bid schedule and/or solicitation pages if required.
CURE is Solicitation number 140P2026B0003 and BRCA is Solicitation Number 140P2026B0004 4
The solicitation materials contain differing information regarding the estimated magnitude of construction. Gideon USA has identified solicitation information indicating an estimated price range between $5,000,000 and $10,000,000, while other solicitation information and the Government's September 10, 2026 pre-bid meeting state that the contract value is more than $10,000,000. Please clarify the Government's official estimated magnitude of construction for Solicitation 140P2026B0003 and identify the FAR 36.204 magnitude range bidders should rely upon for bidding purposes so that all bidders are working from consistent solicitation information.
Greater than $10M 4
Lake Fork Lift Station – Drawing I04.231 – Lake Fork List Station RTU (LFLS) Panel Layout & BOM lists a 24VDC Solar Charger and 12VDC Batteries, 105 AH on the Bill of Material however, there is not any solar panels listed on the BOM nor does drawing I04.230 show the existing lift station as a solar site. Is the Lake Fork Lift Station to be a solar site with the installation of the new packaged lift station? If so, a Rohn antenna tower would be more stable than a typical antenna mast. Please advise.
Lake Fork Lift Station does not need any solar, charger or batteries, utility power will be available. The only solar site in this project is Iola tank.
Specification section 40 67 00.2.02.A. states “Enclosure Manufacturer: Hoffman Engineering Company” however, all of the drawings for the Panel Layout and BOM list Saginaw. Should enclosures be Saginaw or Hoffman? Also, Saginaw part numbers are for Stainless Steel enclosures however, no NEMA rating is listed in the specification. Should all enclosures be stainless steel with a NEMA rating of NEMA 4X?
Neither Hoffman Engineering Company nor Saginaw are specific requirements of the project – they were used as basis of design. The design does not seek to prescribe any particular make or model – the contractor is responsible to submit a product that meets the requirements
Regarding the Aviat Aprisa SR+ VHF radios – we had a Teams conference call with Aviat, the Aprisa radio manufacturer, and they were not confident that their VHF radios would be able to handle the terrain at the park or the bandwidth required for Allen Bradley PLC’s, including the Micro870 PLC’s specified for this project. Would you like us to propose an alternative communication media that will handle the bandwidth and topography requirements?
See response provided in question 9 4
Sheet C1.10A indicates that these sections are to be HDD. Please confirm as it appears this may be in error.
Sheet C1.10B indicates that these sections are to be HDD. Please confirm as it appears this may be in error.
The specification indicates the project will proceed in phases to maintain park operations.
During the transition period, is a parallel operation of the old and new SCADA systems required and if so, for how long?
DA requirement. However, Pigler Automation has recommended transitioning to Ignition, FactoryTalk View or Optix as modern alternatives. Will the customer: (a) accept an engineered proposal using one of these alternative platforms (with technical justifications)?
(b) require strict adherence to GE iFIX as specified? (c) request a comparison/trade study between iFIX and alternatives?
70 The specification requires 'on-premise' SCADA with no cloud-based solution. Is there any future requirement or desire to enable cloud connectivity, remote access, or integration with other NPS systems that might influence SCADA software selection?
What is the required runtime license scope for the SCADA software? (a) Single-user operator workstation at maintenance shop only? (b) Multiple seats for engineering/support staff? (c) Number of simultaneously connected OITs at remote sites? (d) Requirements for historical trending, reporting, or historian database?
The specification shows UPS units at each RTU (PULS 24VDC, 10A, with 12V 5AH battery).
Is the UPS runtime requirement only for graceful shutdown, or must it sustain operator interface and data logging for an extended period? What is the expected minimum runtime (in minutes) needed?
Specifications require verification of antenna tower requirements “as part of the radio path study report” and design per ANSI/EIA-222-F standards.
(a) Has the radio path study report (RF propagation study) already been completed by the design engineer/NPS as part of the construction documents? If yes, is a copy available in the Drawing Set or Specifications?
(b) If NOT completed, is the controls contractor responsible for commissioning and paying for a professional RF survey and path study analysis to verify antenna tower heights, orientations, and link performance?
Specifications require Owner and Engineer witness of performance tests at “Contractor’s manufacturing facility” prior to equipment shipment.
Must Factory Acceptance Testing be performed at the general contractor’s (prime’s) facility, or can FAT be conducted at the SCADA controls subcontractor’s facility or via web conference?
Will the Government provide the on-premise server hardware (OS, CPU, storage, backup infrastructure), or is the contractor responsible for selecting, procuring, and configuring the historian server? Are there minimum specifications or will NPS accept contractor-provided servers?
76 How are “availability” and “reliability” defined per Section 40.05.00?
What constitutes a reportable failure?
What happens if the system fails to meet 99% during the 30-day test—is there a re-test period?
Section 40 61 96 provides control descriptions for several processes. Are complete control narratives available for ALL 10 RTU sites?
Specifically for:
(a) Elk Creek Tank (RTU-ECT)?
(b) Elk Creek Marina Lift Station (RTU-ECMR)? (c) Elk Creek Main Lift Station (RTU- ECMN)? (d) Iola Tank (RTU-IOT)?
Will construction water be available for contractor use at the Elk Creek location? Water usage is anticipated to be approximately 20-30 gallons a day.
Can tree and scrub oak grubbing material from construction activities be left on site if chipped and stockpiled for Parks Landscaping Subcontractor?
Confirm re-lining only 2 lagoons per Sheet C2.13 and 3rd lagoon has only grinder and transfer switch work.
It is assumed pond liquid can be pumped into other ponds to complete scope. Please confirm.
Is archeological monitoring required anytime disturbance is within area of potential effect (APE)? If not, please clarify archeologically sensitive areas to be observed.
01 27 00, 3.1B;
33 11 00, 33 11
00-13; water plan/profile sheets and
Please provide or confirm a controlling open-cut water schedule by alignment showing station limits, diameter, material, installation method and bid item. Include final quantities and locations for valves, fire hydrants, air-release assemblies, meter/service reconnections, line stops, vaults and other appurtenances.
84 Please provide or confirm the controlling gravity-sewer schedule by reach, including station limits, diameter, material, invert elevations, manhole identifiers and service reconnections. Please confirm the number, size and approximate length of building laterals and whether laterals stop at the plan limits or extend to each existing structure.
Section 33 30 00 requires 6 feet minimum cover over force main, while other requirements appear to use deeper criteria.
Please confirm that plan/profile invert elevations control and state the minimum cover for each open-cut water, gravity-sewer and force-main alignment where a profile is not shown.
86 The geotechnical report anticipates shallow bedrock and possible hydraulic hammering or blasting, while the specifications prohibit explosives and the work is lump sum. Please provide the estimated rock quantity by alignment or confirm that rock beyond reasonably inferable conditions will be handled as a differing site condition. Also confirm the notification, measurement and authorization procedure for rock excavation.
Please confirm the procedure and compensation when soft, pumping, saturated or otherwise unsuitable trench bottom is encountered despite reasonable dewatering. Identify who determines the overexcavation depth and replacement material, and whether authorized removal, disposal, stabilization fabric and granular replacement beyond the normal trench section are incidental.
88 Please provide available groundwater observations by work area and identify approved dewatering discharge locations and treatment requirements. Confirm whether discharge to land, existing drainage or the sanitary system is permitted and identify any project-specific permit or sampling requirements.
Please confirm the restoration width and section at each paved road, parking area, concrete walk, gravel road and campsite disturbed by open-cut work. State whether asphalt replacement is trench width, a minimum width, half-lane or full-lane, and identify sawcut offsets, aggregate thickness, asphalt thickness and final seal or overlay limits.
90 The HDPE requirements state a 200 psi working pressure, while Section 33 11 00-13 specifies a 46 psi hydrostatic test.
Please confirm the test pressure, reference elevation, maximum test-section length and allowable make-up water for each open-cut alignment. Also confirm whether HDD and open-cut segments are tested separately before the closure joint.
Please confirm the approved source and discharge locations for hydrostatic test, flushing and disinfection water, including dechlorination and sampling requirements. Confirm who schedules and pays for bacteriological testing, the approved laboratory, sample locations and normal turnaround time.
Please confirm whether existing wet wells, dry wells, septic tanks and the dosing chamber will be pumped, cleaned and certified safe before mechanical demolition or confined-space work. Identify who is responsible for sewage/sludge characterization, removal, transport and disposal, and identify any known regulated materials within the demolition limits.
93 Please provide the complete liner-system specification for the three lagoon cells, including geomembrane resin, thickness, color, texture, underlayment, subgrade acceptance, anchor trenches, penetrations, seam testing, installer qualifications, warranty and leakage criteria. Please also identify the design liner area for each cell.
94 Please confirm how many lagoon cells must remain in operation during liner replacement, the order in which cells will be released, return-to-service criteria and maximum outage for each cell. Provide expected seasonal influent flows and identify any temporary pumping, piping, storage or treatment required.
Please confirm the existing headworks concrete to remain and provide verified dimensions, condition information and allowable repair limits. Identify responsibility for demolition, equipment setting, anchors, grout, channels, gates, piping, valves and restoration. Also confirm whether the new comminutor/grinder is Government-furnished, vendor-furnished or contractor-furnished.
Date 08/24/2026
Solicitation No.
140P2026B0003
National Park Service (NPS) – Denver Service Center (DSC) CURE 318742 – Rehabilitation of Water & Wastewater System
– Curecanti National Recreation Area
Page
SECTION B – BID SCHEDULE
CONTRACT BID SCHEDULE
SOLICITATION NUMBER: 140P2026B0003
PARK - PMIS: CURE 318472
PROJECT TITLE: Rehabilitation of Water and Wastewater System
Contract Price Schedule Template National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18
Solicitation Number:
PARK - PMIS: 318472 - CURE
(Project Management Information System)
Developed Area: Elk Creek, Lake Fork, and Iola Areas
Project Title: CURE - Replace Water and Wastewater Systems at Elk Creek and Lake Fork, Curecanti National Park
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
Contract Line Item Number
(CLIN)
Contract Line Item (CLI) Title Quantity Unit of Measure Unit Price Total Price
1 CLIN 1 - Elk Creek Sanitary System Repair 1 Lump Sum
2 CLIN 2 - Elk Creek Water Supply Repair 1 Lump Sum
3 CLIN 3 - Complete SCADA System Replacement
1 Lump Sum
4 CLIN 4 - Replace Elk Creek Marina Lift Station in kind
1 Lump Sum
5 CLIN 5 - Archeological Monitoring 1 Lump Sum
TOTAL BASE PRICE (Contract Line Item Number 1 through 5) ----------------------------------------------------------------------------
6 CLIN 6 - Elk Creek Gravity Sewer 1 Lump Sum
7 CLIN 7 - Elk Creek Lagoon Work 1 Lump Sum
8 CLIN 8 - Elk Creek, Lift Station Replacement 1 Lump Sum
9 CLIN 9 - Lake Fork Complete Scope 1 Lump Sum
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 6-9) ----------------------------------------------------------- $0.00
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 9) -------------------------- $0.00
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.
Refer to Section H of the solicitation for additional information regarding contract options.
End of Section B
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110