This is Amendment 0002 to Solicitation 140P2026B0004, issued by the National Park Service (NPS), Department of Interior (DOI). The amendment, effective September 17, 2026, provides the Pre-Bid Site Showing Attendee List and PowerPoint presentation materials to offerors. All other terms and conditions of the solicitation remain unchanged and in full force and effect. Offerors must acknowledge receipt of this amendment prior to the specified hour and date by completing items 8 and 15 on the form, acknowledging receipt on each copy of the offer submitted, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers.

The underlying solicitation 140P2026B0004 is for water system rehabilitation work at Bryce Canyon National Park in Utah. This is a sealed bid, firm fixed price contract for construction services (NAICS 237110 – Water and Sewer Line and Related Structures) with a contract value exceeding $10 million. The solicitation is a total small business set aside with a $45 million size standard. Offerors must submit prices for four base line items and seven optional line items covering raw water main construction, visitor center potable water supply, lodge area water distribution, and optional work including residential water supply, campground improvements, sewer laterals, tank area pipe replacement, Yovimpa Point demolition, mixing circle standpipe, and archaeological monitoring. The pre-bid meeting was held September 16, 2026, with questions due September 22, 2026, and bids due September 30, 2026. Electronic submission is required to Vicki Freese-Supler and Brian Baugh, with bid opening via Microsoft Teams. The period of performance is 550 calendar days from Notice to Proceed. Liquidated damages are set at $1,420 daily, and performance and payment bonds are required.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Vicki Freese-supler

See continuation page

NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287

DOI, NPS, DSC Contracting Services 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287

PDS

PDS

140P2026B0004

09/17/2026

08/24/2026

1 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P2026B0004/0002

The purpose of this amendment is to provide the

Pre-Bid Site Showing Attendee List as well as the Power Point presentation provided.

All other terms and conditions of the solicitation remain unchanged and in full force and effect.

PRE-BID SITE VISIT

Rehabilitate Main Water Systems

East Creek and Yovimpa Point

Bryce Canyon National Park | BRCA 318695

Final Construction Documents July 13, 2026

Source graphics: Drawings and Specifications

BRCA 318695 | Pre-Bid Site Visit

Project Area Orientation

Contract Line Items: Base Bid and Options

CLIN Area / Option Primary Work

0001 Base – Raw Water Main Wells to new valve vault; HDD to Science Hill; open cut to tanks; ARV/isolation valves.

0002 Base – Visitor Center Potable transmission along Main Road; HDD/open cut; hydrants, services, and tie-ins.

0003 Base – Lodge Area Potable distribution system improvements; hydrants, flushing hydrants, services.

0004 Option A Old Residential Area and Residence Halls water supply.

0005 Option B North Campground Loop D water supply.

0006 Option C Maintenance Yard water supply.

0007 Option D Mission 66 sanitary sewer laterals to residences.

0008 Option E Water storage tank area AC pipe replacement.

0009 Option F Yovimpa Point water system demolition.

0010 Option G Mixing Circle truck-fill standpipe.

0011 Option H Archaeological monitoring.

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 4 Specs 01 27 00 + Drawing G1.01

Bid Options: Additive Work Packages

A Old Residential + Residence Halls Open-cut HDPE water main, services, hydrants.

B North Campground Loop D Open-cut HDPE water main, services, hydrants.

C Maintenance Yard Open-cut HDPE water main, services, hydrants.

D Mission 66 Sewer Laterals PVC sewer laterals to existing 8-inch sewer main.

E Tank Area AC Pipe Remove AC piping; replace with HDPE by open cut.

F Yovimpa Point Demo Remove galvanized service, structures, and slabs.

G Mixing Circle Standpipe Water main extension and truck-fill standpipe.

H Archaeological Monitoring Monitor ground-disturbing work in sensitive areas.

Project Area: East Creek Well Area / Raw Water Main

CLIN 0001

Raw Water Main from Well House to Water Storage Tanks

• Connect existing wells to a new valve vault using HDPE pipe via open cut.

• Construct HDD segment from the new valve vault toward Science Hill.

• Complete open-cut segment from the end of HDD to the water storage tanks.

• Install combination air/vacuum relief valves and isolation valves as shown.

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 8 Drawings C1.01–C1.02 + Spec 01 27 00

Project Area: Main Road / Visitor Center Potable Water

CLIN 0002

Potable Water Supply to Visitor Center

• Construct new potable water transmission piping along the Main Road corridor.

• Use a combination of HDD and open-cut construction as shown on the plans.

• Make connections to fire hydrants, services, and tertiary water mains.

• Coordinate traffic control and utility shutdowns with NPS before tie-ins.

Project Area: Lodge Area

CLIN 0003

Water Distribution

• CLIN 0003 upgrades potable distribution in the Lodge area.

• Connections include fire hydrants, flushing hydrants, tertiary mains, and services.

APE and LOD Constraints

AREA OF POTENTIAL EFFECT + LIMITS OF DISTURBANCE

• The plans show both Area of Potential Effect (APE) and Limits of Disturbance (LOD).

• Do not disturb portions of the project site beyond the work shown in the construction documents.

• Limit earthwork, clearing, staging, stockpiling, and access to approved construction limits.

• Archaeological exclusion zones and sensitive sites require fencing/avoidance before ground disturbance.

• Traffic outside the APE should be limited to the minimum necessary to avoid sensitive sites.

Archaeological Monitoring

OPTION H / CLIN 0011

• Archaeological monitor observes ground-disturbing work at sensitive areas from a safe, mutually agreed location.

• Monitor records finding locations using construction layout centerline and perimeter staking as reference.

• If resources are found, work may relocate to a non-sensitive area while resources are identified and documented.

• If resources are discovered while monitor is absent, ground-disturbing activities stop immediately and NPS is notified.

• Cultural resources discovered during work are turned over to the park immediately.

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 15 Spec 01 35 13.22 + 01 27 00

Solicitation 140P2026B0004

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 15 Spec 01 35 13.22 + 01 27 00

Summary of Solicitation and Award Information

Refer to the Solicitation for Complete Information

• Pre-Bid on Site Meeting – September 16, 2026

• Pre-Bid Questions Due – September 22, 2026

• Bids Due – September 30, 2026

• Submission – Electronic Only to: Vicki Freese-Supler and Brian Baugh

• Type of Contract – Firm Fixed Price

• NAICS Code 237110 – Water and Sewer Line and Related Structures

• Small Business Size Standard - $45M

• THIS IS A TOTAL SMALL BUSINESS SET ASIDE

• PERIOD OF PERFORMANCE: Project Completion 550 calendar days after Notice to Proceed

• CONTRACT VALUE: More than $10M

• Solicitation Process: Sealed Bid

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 15 Spec 01 35 13.22 + 01 27 00

Solicitation Clauses

FAR 52.211-12 – Liquidated Damages-Construction - $1,420.00 FAR 52.228-1 – Bid Guarantee FAR 52.228-15 – Performance and Payment Bonds FAR 52.236-2 – Differing Site Conditions FAR 52.236-3 – Site Investigations and Conditions Affecting the Work FAR 52.236-9 – Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements FAR 52.236-21 – Specifications and Drawings for Construction

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 15 Spec 01 35 13.22 + 01 27 00

Bids should be submitted electronically with the following denoted in the subject line: BRCA 318695 - 140P2026B0004 – Sealed Bid Submission, and include the Contractor’s Name. It is the responsibility of the bidders to ensure bids are received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids.

FORMAT: Submit (1) one electronic copy

ORGANIZATION:

• SF33

• Amendments

• Section B Price Schedule

• SF 24 Bid Bond (Or Other Suitable Bid Guarantee)

• Section K Representations and Certifications

• General References

LOCATION OF BID OPENING: To be held electronically via Project Teams at 2:00 p.m. MT

• Meeting ID: 269 381 509 394 268

• Passcode: 98Kd9fb9

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 15 Spec 01 35 13.22 + 01 27 00

Section M – Basis for Award

To be eligible for award of contract, the offeror shall submit prices for each line item in Bid Schedule to include all four (4) Base Line Items and all seven (7) Line Items designated as Options. Accordingly, contract award will be made to the lowest responsible bidder conforming to the solicitation, provided funds are available and the Contracting Officer determines the price to be reasonable.

Per FAR provision 52.217-5, Evaluation of Options (JULY 1990), the Government will evaluate offers for award purposes by adding the total price for all options to the total price for all base items, Line Items 5 through

11. Evaluation of options will not obligate the Government to exercise the option(s). If the determination is made to exercise any of the Options, the Contracting Officer will provide the contractor with written notice no later than 60 days after contract award, per FAR clause 52.217-7, Option for Increased Quantity Separately Priced Line Item (MAR 1989).

Issuance of this solicitation does not guarantee that an award will be made. Any resulting awards are subject to the availability of funding and the discretion of the awarding entity, including cancellation or amendment based on a determination of change in agency needs.

Pre-Bid Site Visit | Final Construction Documents dated July 13, 2026 | 15 Spec 01 35 13.22 + 01 27 00

Thank You For Your Interest in This Project

National Park Service U.S. Department of Interior

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

ADPFF7C.tmp
Slide Number 1
Slide Number 2
Slide Number 3
Slide Number 4
Slide Number 5
Slide Number 6
Slide Number 7
Slide Number 8
Slide Number 9
Slide Number 10
Slide Number 11
Slide Number 12
Slide Number 13
Slide Number 14

File details come from the government source that posted it. Updated .