This is Amendment 0005 to Solicitation 140P2026B0004, issued by the National Park Service (NPS) on October 2, 2026, for the rehabilitation of the main water system at East Creek and Yovimpa in Bryce Canyon National Park. The bid opening date remains October 8, 2026 at 2:00 PM Mountain Time. The amendment corrects information from the previously issued Amendment 4 by providing accurate responses to contractor questions and including Construction Specification 22 11 19 for Domestic Water Piping Specialties, which was provided for the incorrect project initially.

The specification establishes requirements for backflow preventers (reduced-pressure-principle type) in 2-inch and 6-inch sizes with design flow rates of 150 gpm and 600 gpm respectively. Acceptable manufacturers include Ames Fire & Waterworks, Apollo Valves, Caleffi North America, FEBCO, WATTS, and Wilkins. The specification requires compliance with SDWA standards, NSF/ANSI/CAN 61 and 372 certification with weighted average lead content ≤0.25 percent, ASSE 1013 standard, continuous-pressure operation, maximum 5 psig pressure loss, bronze bodies for 2-inch sizes, and ductile or cast iron with interior lining for larger sizes. Installation requirements mandate backflow preventers in each water supply to mechanical equipment, atmospheric-vent drain connections with air-gap fittings, and prohibition of bypass piping. The document also contains 100 questions and answers addressing technical clarifications on pipe sizes, valve specifications, personnel requirements, testing procedures, construction staging, archaeological monitoring, and equipment coordination. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Vicki Freese-supler

See continuation page

NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287

DOI, NPS, DSC Contracting Services 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287

PDS

PDS

140P2026B0004

10/02/2026

08/24/2026

1 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P2026B0004/0005

BRCA 318695 - Rehabilitate Main Water System at

East Creek and Yovimpa, Bryce Canyon National

Park

The purpose of this amendment is to correct the previous issued Amendment 4 which provided responses to questions and additional information for the incorrect project. All

Offerors are instructed to disregard the information contained within Amendment #4 and replace with the information issued as part of this Amendment which provides for the following:

1. To provide for the responses to Questions received.

2. To provide Construction Specification 22 11

19 - Domestic Water Supply Piping Specialties

The date/time for the Bid Opening remains unchanged and is currently scheduled for

October 8, 2026 at 2:00 Mountain Time. Call in details and meeting details remained unchanged from the information provided through Amendment

#1.

All other terms and conditions of the solicitation remain unchanged and in full force and effect.

29964.13.00 DOMESTIC WATER PIPING SPECIALTIES

ms2352 SECTION 22 11 19 - Page 1

PART 1 GENERAL

1.01 SUMMARY

A. Section includes: Backflow preventers.

1.02 ACTION SUBMITTALS

A. Product Data: For each type of specified product.

B. Shop Drawings: For domestic water piping specialties.

1.03 INFORMATIONAL SUBMITTALS

A. Test and Inspection Reports: For backflow preventer, reduced-pressure-principle type.

B. Field Quality Control Reports: For specified tests and inspections.

1.04 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For domestic water piping specialties to include in emergency, operation, and maintenance manuals.

PART 2 PRODUCTS

2.01 GENERAL REQUIREMENTS FOR PIPING SPECIALTIES

A. Domestic water piping specialties intended to convey or dispense water for human consumption are to comply with the SDWA, requirements of authorities having jurisdiction, and NSF/ANSI/CAN 61 and NSF/ANSI/CAN 372, or to be certified in compliance with NSF/ANSI/CAN 61 and NSF/ANSI/CAN 372 by an American National Standards Institute (ANSI)-accredited third-party certification body that the weighted average lead content at wetted surfaces is less than or equal to 0.25 percent.

2.02 PERFORMANCE REQUIREMENTS

A. Minimum Working Pressure for Domestic Water Piping Specialties: 50 psig.

B. Backflow Preventers, Reduced-Pressure-Principle Type :

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Ames Fire & Waterworks; A Watts Water Technologies Company

b. Apollo Valves; a brand of Aalberts Integrated Piping Systems (Aalberts Industries)

c. Caleffi North America

d. FEBCO; A WATTS Brand

e. WATTS; A Watts Water Technologies Company

f. Wilkins; Zurn Elkay

2. Description: Reduced-pressure backflow preventers are intended for high-hazard applications.

They contain two independently acting, spring-loaded check valves separated by a reduced-pressure zone that includes a relief valve force-loaded to the open position, allowing discharge to atmosphere if either check fails.

3. Standard: ASSE 1013.

4. Operation: Continuous-pressure applications.

5. Pressure Loss: Maximum of 5 psig measured across the middle third of the flow range.

6. Size: 2” and 6”

7. Design Flow Rate for 2”: 150 gpm

8. Design Flow Rate for 6”: 600 gpm

DOMESTIC WATER PIPING SPECIALTIES 29964.13.00

Page 2 - SECTION 22 11 19 ms2352

9. Pressure Loss at Design Flow Rate: 70 psig for sizes NPS 2 (DN 50) and smaller; 70 psig for NPS 2-1/2 (DN 65) and larger.

10. Body: Bronze for NPS 2 (DN 50) and smaller; ductile or cast iron with interior lining that complies with AWWA C550 or that is FDA approved or stainless steel for NPS 2-1/2 (DN 65) and larger.

11. End Connections: Threaded for NPS 2 (DN 50) and smaller; flanged for NPS 2-1/2 (DN 65) and larger.

12. Configuration: Designed for horizontal, straight-through flow.

13. Valves NPS 2 (DN 50) and Smaller: Ball type with threaded ends on inlet and outlet.

14. Valves NPS 2-1/2 (DN 65) and Larger: Outside-screw and yoke-gate type with flanged ends on inlet and outlet.

15. Air-Gap Fitting: ASME A112.1.2, matching backflow-preventer connection.

PART 3 EXECUTION

3.01 INSTALLATION OF PIPING SPECALTIES

A. Backflow Preventers: Install in each water supply to mechanical equipment and systems and to other equipment and water systems that may be sources of contamination. Comply with authorities having jurisdiction.

1. Locate backflow preventers in same room as connected equipment or system.

2. Install drain for backflow preventers with atmospheric-vent drain connection with air-gap fitting, fixed air-gap fitting, or equivalent positive pipe separation of at least two pipe diameters in drain piping and pipe-to-floor drain.

3. Do not install bypass piping around backflow preventers.

3.02 ADJUSTING

A. Adjust each reduced-pressure-principle backflow preventer in accordance with manufacturer's written instructions, authorities having jurisdiction and the device's reference standard.

END OF SECTION

1) Eric R. Schallert

2) Angela M. Y. Romero

Solicitation 140P2026B0004 BRCA 318695 - Rehabilitate Main Water System

Question No. Sheet or Reference Question Response

Can the use of Siemens hardware and WinCC be utilized in lieu of the use of Allen Bradley as specified in the construction specifications?

The construction specification does not require Allen- Bradley exclusively. Division 40 accommodates multiple SCADA hardware and software manufacturers, including, but not limited to Allen-Bradley, Siemens, GE and Schneider Electric, provided the proposed system meets the specified performance and compatibility requirements.

The Division 40 specifications are performance based and accommodate alternate SCADA hardware and software platforms provided the proposed equipment meets the specified functional, performance, compatibility, communication and integration requirements. Bidders are not precluded from proposing an equivalent solution under the current specification. Any equivalent solution would need to demonstrate compliance with the specified salient characteristics and be evaluated through the submittal process.

Since submission of subject solicittion is electronic email, are scanned copies of the original bid guarantee acceptable? Section L, Page 71, Paragraph D specifies a bid guarantee should be submitted with emailed copy of Bid Package; however, Page 72, Bid Guarantee section indicates photocopied and faxed copies of bonds will be rejected.

Yes; however, the seal must be evident on the emailed version.

Can we use compression fittings instead of flared for the corps/curb stops? No.

The specs on the Mueller brass don't seem to match. The corp mentions 1/4 turn ball valve but the part #H-15000 corp signifies inverted key valve which only has a 125 psi rating is not a 1/4 turn valve. The curb stop same thing mentions 1/4 turn ball valve but the part # signifies it as an oriseal valve with only a 175 psi rating. Would a 1/4 turn ball style valve at 300 psi be better suited for this application? Also can we bid FORD brass instead of Mueller?

Provide 1/4 turn ball style brass valves for this application.

Minimum pressure rating of 200 psi. Product references are provided as a basis of design. Alternate brands that meet specified salient features are acceptable.

Can we bid Kennedy gate valves to match the hydrants instead of Clow? Both companies are owned by McWane and both valves are the same pattern/specs just the name is different?

Product references are provided as a basis of design.

Alternate brands that meet specified salient features are acceptable.

Would you to open to utilizing HDPE instead of k-soft copper for the 2" and smaller services? They are using HDPE for the main line as well as the 2" line to the flushing hydrants.

HDPE is acceptable for 2" and smaller services..

We were not seeing a specification for the backflow preventers, do they want double check or RPZs?

Reduced Pressure Zone (RPZ's).

For the flushing hydrants, do we need 6x2 tee like the detail shows? Or a 6x2 saddle and corp like it mentions in certain spots.

Tee's.

For all the flushing hydrants, fire hydrants, valves, etc. that are in the 15' deep HDD areas should those all be installed at 15' depth as well?

Yes, all appurtenances need to be 15' deep where specified.

The section for waterline from the well house to the tank transitions between 6" and 8" (sheet C1.15) that appears to be in error. Can you confirm the pipe size through those sections.

The pipe from the valve vault east of the wells to Science Hill tanksarea will all be 6" HDPE.

The section of pipe from the Visitor Center is indicated as 8" pipe but on Sheet C1.20 and C1.21 it shows that valves on that line are to be 6". Can you confirm the pipe size through those sections.

Pipe and valve sizes from Science Hill to the Visitor's Center are to be 8".

HDD will require clean mixing water for construction. Is there a limit on what water will be available for construction?

Potable water will be available @ 10kgal/day for disinfection and flushing of water line. The park does not have capacity to support non-potable uses. Contractor may coordinate with Tropic Ditch Company for non-potable source.

Is it allowable to dump drill mud in the maintenance laydown area for drying prior to hauling outside the park? Similar to a concrete washout.

A non-permeable containment area and plan that meets specifications and enviornmental requirements is required for approval. Reference 33 05 07 2.8 for final clean up requirement

Option B in the dorm (concessionaire housing area) will require the parking area asphalt to be removed. What level of closure will be allowed for that parking area?

To be coordinated. NPS will permit partial closures to complete construction. This area may require construction outside of peak park times to limit disturbance (such as winter months). Emergency response vehicle access needs to be maintained as coordinated with park.

Estimated dewatering flow rates (GPM) anticipated for trench excavations and HDD pits. Contractor responsibility - means and methods - consult geotech report and contract documents.

Expected excavation depths where dewatering may be required. Contractor responsibility - means and methods - consult geotech report and contract documents.

Estimated static lift from water surface to discharge location. Contractor responsibility - means and methods - consult geotech report and contract documents.

Approximate discharge distances from excavation areas to approved discharge points. Contractor responsibility - means and methods - consult geotech report and contract documents.

Planned discharge locations and any treatment or permitting requirements. Contractor responsibility - means and methods - consult geotech report and contract documents.

Available electrical power on site, including voltage and phase, if electric pumps are preferred. Sunset campground can be used for contractor construction trailer, 50 amp service is available. Identify need after award. Construction power is not available for dewatering pumps. Reference 01 47 19.12 for noise and acoustic management requirements.

Anticipated duration of dewatering operations. Contractor responsibility - means and methods - consult geotech report and contract documents.

Expected number and size of simultaneous excavation areas requiring dewatering. Contractor responsibility - means and methods - consult geotech report and contract documents.

HDD launch and receiving pit dimensions and depths. Contractor responsibility - means and methods - consult geotech report and contract documents.

Any contractor assumptions, engineering estimates, or previous project data regarding groundwater inflows.

Contractor responsibility - means and methods - consult geotech report and contract documents - Utah DEQ permits.

Water quality requirements, filtration requirements, sediment control requirements, or environmental restrictions related to pumping and discharge.

Contractor responsibility - means and methods - consult geotech report and contract documents - Utah DEQ permits.

Any known areas of concern beyond borings B-1, B-2, and B-3 where groundwater is anticipated. Contractor responsibility - means and methods - consult geotech report and contract documents - Utah DEQ permits.

Section 33 11 00, 2.07.A, PDF page 277, requires Type K copper services between the main and curb-stop box

Please identify the material and replacement limits for each service, including where copper transitions to HDPE or ties into the existing service.

The service pipe connecting to the distribution pipe to existing service connection. Connect to existing service downstream of the meter.

Section 31 23 00, 3.15.E, PDF page 240, says initial backfill extends 1 inch above the pipe. Section 33 11 00-13, 2.01.B, PDF page 284, says 1 foot

Please confirm that the 1-inch requirement is a typo and that 12 inches governs. Yes, 12 inches governs. Section 31 23 00, 3.15.E: Replace "1" (inch)" with "1' (feet)"

Section 31 23 00, 2.01.C and 2.02, PDF pages 232–233, limits initial backfill to ¾-inch maximum material and remaining excavated backfill to stones no larger than 1½ inches. Section 3.15.F, PDF page 240, separately permits well-broken rock within a specified portion of the trench.

What gradation and maximum rock size apply in each trench zone, and under what conditions can native material be reused?

Well-graded mineral particles with 100% passing 1-1/2" sieve and not over 12% passing No. 200 sieve. Job-excavated material, use at all location except where select backfill is required.

Section 33 11 00, 2.11, PDF page 279, and Section 33 11 00-13, 2.07, PDF page 285, require No. 10 solid copper wire with blue THHN insulation.

Which wire governs open-trench installation, and how should it connect to the separately specified HDD tracer-wire system?

Detail 5: Utility Trench Detail calls out 14/1 UF tracer wire connected to fire hydrants. Service lines 12 gauge tracer wire.

Section 33 11 00, 2.08, PDF page 278, specifies a Val-Matic Model 25 with a 1-inch inlet. Section 33 11 00-13, 2.08, PDF page 286, specifies a Model 48BW with a 2-inch inlet. Both specify globe isolation valves.

Please confirm the required valve function, model, size, pressure rating, isolation valve and vent arrangement for each location.

Specifications confirmed. Detail 4: AIR RELEASE ASSEMBLY, provided on sheet C1.51.

Section 33 05 16-13, 2.02.G.1, PDF page 253, specifies round, solid ductile-iron covers.

Please confirm the required access opening, cover material and load rating for each structure. Specifications confirmed. Follow details for access opening.

33 C1.82, PDF page 55, lists WATR7 as 6-inch

HDPE.

Is W7 intended to be 6-inch or 8-inch, and which bid item includes it? 8-inch

C1.20, PDF page 29, calls for a 6-inch valve at W2-V2, Station 213+27.91, on an 8-inch main.

Should these valves be 8-inch, or are reduced-size valves intentional? If intentional, please provide reducer and restraint requirements.

8-inch

Section 33 11 00, 3.05.A.4, PDF page 280, states: “Set buried valves on concrete thrust block extending to undisturbed earth and having bearing area equal to ‘dead end’ for pipe of same size as valve.”

Are concrete thrust blocks required at valves smaller than 12 inches, and where is an approved restrained-joint system acceptable instead?

No. Restrain joints using pipe manufacturer's standard restrained joints rated at specified test pressure for buried piping lengths show on drawings.

Section 31 23 00, 3.11.D, PDF page 238, specifies 4 inches of hot-mix asphalt with base requirements tied to existing conditions.

Which pavement section applies at each road crossing and restoration area? Pavement replacement sections are to match existing.

What is removed is to be replaced in kind.

Section 33 11 00, 3.08.C–D, PDF page 281, specifies 150 psi for two hours. Section 33 11 00-13, 3.02.D, PDF pages 287–288, specifies 46 psi ±2 psi with an HDPE-specific expansion and testing procedure.

Please confirm that 46 psi is intentional for the HDPE system and identify the testing procedure for sections containing multiple pipe materials.

150 psi is the intended test pressure for the water system.

Allowing time for expansion of the HDPE is necessary. 46 psi is insufficient to test the system, so use 150 psi and allow time for expansion per the lower presure specification.

Detail 3/C1.52, Note 3, PDF page 47, calls for 4 cubic yards of drain aggregate at the flushing hydrant.

Please confirm that 4 cubic yards at each flushing hydrant is intentional. These are different assemblies, but the quantity difference warrants confirmation.

Confirmed.

Details 4 and 5/C1.55, PDF page 50, show 2-inch and 6-inch backflow assemblies.

Please provide the required assembly type, approved products, pressure rating, connections, testing and vault drainage requirements.

Provide, install, test and certify code compliant assemblies. Please refer to Specification 22 11 19 - Domestic Water Piping Specialties included with this Amendment.

Detail 5/C1.51, PDF page 46, shows 1 foot of clearance on each side of the pipe.

Which trench detail and width govern each installation area, including the width to use for excavation and restoration pricing?

Detail 5: Utility Trench Detail, sheet C1.51

The solicitation requires the following onsite Personnel. Superintendent QC Manager / QC Superintendent Site Safety Officer Environmental/SWPPP Manager HDD Superintendent HDD Drill Operator Tracking Technician Mud Engineer Certified HDPE Fusion Technician Archaeological Monitor

Can any of these positions be dual hatted? QC Manager can also be Site Safety Officer (SSO).

Independent from Superintendent, reporting directly to PM. All other positions per contract.

Should the Base Bid CLIN for Archaeology Observations include that scope that will be required for the Option CLINs or should the Archaeology Observations required for the Option CLINs be included in the respective line items for each Option CLIN?

Archaeology Monitoring support shall be incorporated in each construction Option CLIN as needed to complete the specific Option work; Archaeological Monitoring CLIN 11, Option H, shall be for supporting the BASE Construction line items only.

Can the NPS specify and details or a basis for design for the water meters of various sizes for the project.

McCrometer Field Mag 5000, found in specification 40 70 00, Part 2, Section2.03.A.3.d

Please clarify the required onsite staffing for the Superintendent, Quality Control Manager, and Safety Manager. Are these required to be three separate individuals? May the Superintendent also serve as the Safety Manager if qualified? Section 01 40 00 states both that the Quality Control Supervisor “may also perform other duties” and that the Quality Control Supervisor “shall be assigned no other duties.” Please clarify the intended requirement.

QC Manager can also be Site Safety Officer (SSO).

Independent from Superintendent, reporting directly to PM. All other positions per contract.

Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

No - the POP is as stated in the contract documents.

There is a discrepancy in the SOW about nonpotable water availability; please confirm if it will be available for use on-site?

Potable water will be available @ 10k gal/day for disinfection and flushing of water line. The park does not have capacity to support non-potable uses. Contractor may coordinate with Tropic Ditch Company for non-potable source.

Are there any prior surveys / results for existing hazardous materials that might be encountered? No.

When do you anticipate on site work starting? Contractor will be given a full clearance once acceptable Division 01 submittals have been completed.

Please confirm which testing / special inspections are contractor-paid vs Government-provided. Government will not provide any special inspections.

Follow contract docs.

Please confirm whether red tops, yellow tops, blue tops, or any other specific staking conventions are required.

Yes, contractor is fully responsible for validating and verifying location of all existing utilities.

Please identify the anticipated endangered / protected species and all required mitigation / monitoring / seasonal restrictions.

Reference plans and specifications.

The geotechnical report identifies weathered mudstone and limestone and notes the possibility of difficult excavation; please confirm that subsurface rock or obstructions materially differing from the conditions indicated in the geotechnical report and contract documents will be evaluated under the Differing Site Conditions clause.

Reference geotechnical report.

Section 33 11 00 requires third-party testing of water mains in accordance with AWWA C600 at 150 psi for two hours, while Section 33 11 00-13 specifies a separate HDPE hydrostatic test at 46 psi ±2 psi. Please clarify the required hydrostatic test procedure and pressure for each pipe material and confirm whether third-party testing / witnessing is required for HDPE piping.

Section 33 11 00 - Cement-lined ductile iron Section 33 11 00-13 - HDPE Confirmed third-party testing is required for HDPE piping.

Section 31 23 00 requires 3/4-inch minus granular backfill to 1 inch above flexible piping, while Section 33 11 00-13 defines the HDPE pipe zone through 1 foot above the pipe and requires 90% ASTM D698 compaction. Please identify the controlling requirement, including required material and limits of granular embedment.

Section 31 23 00, 3.15.E: Replace "1" (inch)" with "1' (feet)"

The solicitation project description includes enlargement of one raw-water storage tank; however, Option E and the construction documents appear to address only removal / replacement of asbestos-cement piping at the storage tank area. Please confirm whether enlargement or modification of an existing storage tank is included in this contract. If included, provide the applicable drawings, specifications, and CLIN assignment.

Reference drawings and contract price schedule.

Section 40 61 96 requires the System Integrator to test existing well automation logic that is noted as not fully specified. Please provide current information necessary to perform the specified modifications and testing.

The intent of the design is not to modify the existing well automation; the test is to ensure that automatic well operation remains unaffected by the installation of the local control station at each well. System Integrator is expected to review existing well automation logic in the existing controllers and prepare a Sequence of Operations describing the well operation, as required by action submittal 1.05B. Thie existing sequence is further to be integrated into the Field Test plan, as specified by 1.05C.

HDD will require clean mixing water for construction. Is there a limit on what water will be available for construction?

Potable water will be available @ 10kgal/day for disinfection and flushing of water line. The park does not have capacity to support non-potable uses. Contractor may coordinate with Tropic Ditch Company for non-potable source.

Is it allowable to dump drill mud in the maintenance laydown area for drying prior to hauling outside the park? Similar to a concrete washout.

Specify need. Follow specifications and enviornmental plans.

Option B in the corm (concessionaire housing area) will require the parking area asphalt to be removed. What level of closure will be allowed for that parking area?

Specify need. NPS will permit partial closures to complete construction. This area may require construciton outside of peak park times to limit disturbance (such as winter months).

Please confirm whether NPS potable or non-potable water will be available to the Contractor for HDD drilling fluid, hydrostatic testing, dust control, and other construction activities. Please identify the available source(s), any anticipated quantity or drought restrictions, and any fees or metering requirements. Please also advise whether the Government has an anticipated daily or total quantity that may be made available to the Contractor.

Potable water will be available @ 10kgal/day for disinfection and flushing of water line. The park does not have capacity to support non-potable uses. Contractor may coordinate with Tropic Ditch Company for non-potable source.

Please identify any NPS-approved location(s) within the project area where HDD drilling fluid, bore mud, and associated drilling spoils may be contained, dried, processed, or disposed. If no on-site location will be authorized, please confirm that bidders should include removal and lawful off-site disposal of all HDD drilling fluids and spoils in their bids.

Specify need. Follow specifications and enviornmental plans.

The raw-water alignment extends beyond the existing access road into a substantial segment without an established road. Please clarify what temporary access improvements, if any, will be permitted, including grading, matting, aggregate placement, temporary crossings, or other measures necessary to mobilize excavation, fusion, HDD, and support equipment. Please identify any portions where equipment travel is permitted but ground disturbance or access-road construction is prohibited.

Reference plans and specifications.

Please confirm the temporary office requirements under the Contract Documents. Is the Contractor required to furnish a separate field office or trailer for the COR, NPS inspectors, construction management personnel, or other Government representatives? If so, please provide the required size, furnishings, utilities, internet/communications, sanitary facilities, parking, and required duration. If no separate Government office is required, please confirm that temporary office facilities are required only for the Contractor's operations.

Yes. Confirmed. Reference plans and specifications.

Please identify allowable water-system shutdown durations, advance-notice requirements, restricted work hours, and any temporary water or bypass requirements associated with connections to the existing potable-water system. Please also clarify whether any facilities must maintain uninterrupted potable-water and/or fire-protection service throughout construction.

Reference plans and specifications.

Please identify allowable lane closures, one-lane operations, work hours, nighttime-work restrictions, weekend/holiday restrictions, peak-visitation blackout periods, and maximum work-zone lengths for work along Main Road, the Visitor Center, Lodge, General Store, and other public-use areas. Please also clarify whether NPS anticipates additional traffic or access restrictions during periods of unusually high visitation.

Reference plans and specifications.

Please confirm that CLIN 0011, Option H, is intended to compensate the Contractor for all required archaeological monitoring associated with ground-disturbing activities throughout the Base Bid and all awarded Options. Please clarify the anticipated payment basis and whether monitoring required as a result of Government-directed delays, discoveries, additional investigation, or work extending beyond the Contractor's planned duration will be compensated separately.

Archaeology Monitoring support shall be incorporated in each construction Option CLIN as needed to complete the specific Option work; Archaeological Monitoring CLIN 11, Option H, shall be for supporting the BASE construction line items only.

Please identify any NPS or third-party construction anticipated to occur concurrently with this project within or adjacent to the Contractor's limits of disturbance, particularly the planned Visitor Center shuttle-stop work. Please provide any known schedules, access restrictions, shared staging requirements, sequencing constraints, or other interfaces bidders should incorporate into their bids.

Coordination will occur after projects are awarded.

The solicitation materials appear to contain differing information regarding the estimated magnitude of construction. Gideon USA has identified project information indicating a magnitude of $5,000,000 to $10,000,000, while the Government stated during the September 16, 2026 pre-bid meeting that the contract value is more than $10,000,000. Please clarify the Government's official estimated magnitude of construction for Solicitation 140P2026B0004 and identify the magnitude range bidders should rely upon for bidding purposes so that all bidders are working from consistent solicitation information.

Please see FAR 36.204. IGE will not be released until bid opening

69 Does Bryce Canyon National Park have a Resource Manager and a Park Archaeologist? Yes.

70 Does the archaeologist have to be on site everyday of construction? Reference plans and specifications.

The plans show several areas where additional cultural and biological resource surveys are required. Are these areas prairie dog habitats? Is the Park Resource Manager/Archaeologist going to be performing these surveys? Will they be handling the archaeological monitoring during the project as well?

Surveys have been completed. Information not for public distributuon. Area information will be provided after award.

Can the Superintendent, QC Manager, Site Safety Officer, and Environmental Manager be the same individual or 4 separate positions? Can they be combined between 2-3 different people?

QC Manager can also be Site Safety Officer (SSO).

Independent from Superintendent, reporting directly to PM. All other positions per contract.

73 What type of bridge goes over the intermittent wetlands? Sheet C1.07 shows the bridge/wetlands/biological/cultural surveys in the same area.

Reference plans and specifications.

74 Can we move the temp fencing down the line as we move? Reference plans and specifications.

Are we able to use power from park? Do we need a meter? Yes, power may may be used if available. Power must be metered. Refernece plans and specifications 76 Are the pumps in the well houses being reused? Reference plans and specifications.

77 Will seeding be required? Reference plans and specifications.

The open cut HDPE specification lists PE3408/PE345444C and a 200 psi working pressure but does not state the DR. Please confirm the resin, DR, pressure class, IPS or DIPS sizing and stripe/color required for each open cut pipe size. Is PE4710 DR11, 200 psi acceptable?

HDPE DR11 DIPS. Provide material per specifications.

79 HDPE to ductile iron transition detail, including adpater, backing ring, stiffener, restraint and encasement.

Per pipe manufacturer recommendations.

Reference: 33 11 00-13, 2.02; water schedules

The open-cut HDPE specification lists PE3408/PE345444C and a 200 psi working pressure but does not state the DR. Please confirm the resin, DR, pressure class, IPS or DIPS sizing, and stripe/color required for each open-cut pipe size. Is PE4710 DR11, 200 psi acceptable?

HDPE DR11 DIPS. Provide material per specifications.

Reference: 33 11 00, 2.01; 33 11 00-13, 2.04.C; water schedules

The drawings show several ductile-iron branch lines, while Section 33 11 00 addresses buried ductile iron from 4 inches through 12 inches. Please confirm the required material for the 2-inch and 3-inch segments. Also provide the required HDPE-to-ductile-iron transition detail, including adapter, backing ring, stiffener, restraint and encasement.

Size and material per drawing plan and profiles.

Transition requirements per pipe manufacturer recommendations.

Reference: 33 11 00 and 33 11 00-13 product requirements

Please confirm whether the manufacturers named in Sections 33 11 00 and 33 11 00-13 are mandatory or are listed as a standard of quality. If equals are allowed, please confirm the substitution process and NSF 61 requirements for pipe, fittings, adapters, valves, hydrants, air-release valves, tracer wire and valve boxes.

Product references are provided as a basis of design.

Alternate brands that meet specified salient features are acceptable. They may may be submitted as part of the submittal review/approval process

The solicitation materials appear to contain differing information regarding the estimated magnitude of construction.

Greater than $10M

Is there a detail that shows how the pipe to pipe connections should be at the HDD Bore Holes? Three options are acceptable: butt fuse the pipe ends, use electrofusion couplings, or use pipe stiffeners and ductile iron restrained mechanical joints sleeves.

On sheet C1.55, can you please clarify if detail callout 6 is in reference to callouts 4 and 5, or is this for something else?

Yes. Detail 6, Concrete Box details, does refer to Details 4 and 5, Backflow Preventers and provides construction details for the concrete box enclosing the BFP.

On Sheets C1.19 through C1.24, the HDPE waterline sizes and associated appurtenances shown in plan view do not consistently match those shown in the profiles. For example, the plan notes indicate one pipe size, while the profiles reference both 6" and 8" pipe. Additionally, at Sta.

243+52, 255+25, 248+30, and 238+23 an 8" valve is called out on a 6" waterline. Please clarify the correct HDPE waterline sizes and corresponding appurtenance sizes for these sheets and confirm whether the 8" valves at Sta. callouts are correct.

The pipes and valves from the junction structure at the wells to the tanks at Science Hill are all to be 6".

Can our onsite Superintendent also be the Safety officer. No. Reference reponses to similar question.

Can we get a list of the contractors bidding on the project? Please refer to SAM.gov as these were posted with a previous Amendment.

Are there images of the control panels - outside and inside? I would like to know if there is enough room to mount additional switches and other hardware.

For bidding purposes assume space is not available.

Who supplies and installs the well switches, lights, relays, and starter-to-RTU wiring? A complete operational system is to be provided as part of this project. GC to coordinate work responsibilities within their team. Typically, the Integrator is most familiar and best equipped to select control panel parts and complete termination, support from electrical contractor may be required.

What is the existing remote alarm-notification method? Cellular modem located at Science Hill WTP control panel.

How should alternation occur, and what happens when a well faults, leaves remote, or loses communications?

Well automation to remain as programmed. The intent of the design is not to modify the existing well automation;

the test is to ensure that automatic well operation remains unaffected by the installation of the local control station at each well. System Integrator is expected to review existing well automation logic in the existing controllers and prepare a Sequence of Operations describing the well operation, as required by action submittal 1.05B. Thie existing sequence is further to be integrated into the Field Test plan, as specified by 1.05C.

Who supplies, installs, configures, and trains on the Science Hill meter? GC to coordinate all work responsibilities within their team. Typically, the Integrator is most familiar and best equipped to configure and train on the meter, however they likely will need mechanical and electrical installation support from other contractors to run the underground conduit and cable, and mount the meter to the pipe.

Which panel receives the switches/lights? Reference Note 2 on drawing I1.02B.

Are the training prerequisites intended to require a separate return visit? Training to be scheduled and coordinated with NPS operations and the Contractor team. Wells must be operable during training (piping must be intact from wells to science hill tank), so training can occur either before or after the pipe replacement work, not during.

Can you quantify the asphalt/concrete repair. The plans don’t show enough detail to know what patching might be required.

Pavement replacement sections are to match existing.

What is removed is to be replaced in kind.

Is there any contingency if we hit refusal on the Horizontal directional drill? Variances for pipe bursting the existing waterline along east creek may be considered.

Will you cover the electrical sub and the archeological monitoring contractor? No. These are contract requirements and the responsibility of the general contractor.

On Sheets C1.15 through C1.1.16, the HDPE waterline sizes shown in plan view do not match those shown in the profiles. For example, the plan notes indicate 6” pipe size, while the profiles reference both 6" and 8" pipe. Ex. Profile view on C1.15 and 1.16 says Sta 254+93.70 to Sta 268+42.61 says 8” HDPE. Please clarify the correct HDPE waterline sizes for these sheets and confirm.

The pipes and valves from the junction structure at the wells to the tanks at Science Hill are all to be 6".

The solicitation identifies enlargement of an existing raw water storage tank as project work.

However, the Option E specification describes the removal of existing asbestos-cement piping and replacement with HDPE. The referenced drawings show existing tank connections, piping improvements, and a replacement valve vault. We have not located a proposed tank capacity or construction details for tank enlargement.

a) Is enlargement or replacement of a raw water storage tank required under this contract?

b) If required, identify the tank, its existing capacity, the required final capacity in gallons and whether the intent is to modify the existing tank, replace it, or install additional storage.

c) Provide the applicable design drawings and specifications, including tank dimensions, materials, foundation and structural requirements, piping connections, and testing requirements.

d) Identify the base bid or option contract line item under which this work must be included.

e) If tank enlargement is not reuqired, please confirm that the reference on Solicitation, Page 9 will be removed by amendment and clarify the intended tank area scope.

Tank replacement/enlargement is not part of the project scope. Option E items are those identified.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

22 11 19 - Domestic Water Piping Specialties 09-30-2026.pdf
PART 1 GENERAL
1.01 SUMMARY
A. Section includes: Backflow preventers.
1.02 ACTION SUBMITTALS
A. Product Data: For each type of specified product.
B. Shop Drawings: For domestic water piping specialties.
1.03 INFORMATIONAL SUBMITTALS
A. Test and Inspection Reports: For backflow preventer, reduced-pressure-principle type.
B. Field Quality Control Reports: For specified tests and inspections.
1.04 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: For domestic water piping specialties to include in emergency, operation, and maintenance manuals.
PART 2 PRODUCTS
2.01 GENERAL REQUIREMENTS FOR PIPING SPECIALTIES
A. Domestic water piping specialties intended to convey or dispense water for human consumption are to comply with the SDWA, requirements of authorities having jurisdiction, and NSF/ANSI/CAN 61 and NSF/ANSI/CAN 372, or to be certified in compliance wi...
2.02 PERFORMANCE REQUIREMENTS
A. Minimum Working Pressure for Domestic Water Piping Specialties: 50 psig.
B. Backflow Preventers, Reduced-Pressure-Principle Type :
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Ames Fire & Waterworks; A Watts Water Technologies Company
b. Apollo Valves; a brand of Aalberts Integrated Piping Systems (Aalberts Industries)
c. Caleffi North America
d. FEBCO; A WATTS Brand
e. WATTS; A Watts Water Technologies Company
f. Wilkins; Zurn Elkay
2. Description: Reduced-pressure backflow preventers are intended for high-hazard applications. They contain two independently acting, spring-loaded check valves separated by a reduced-pressure zone that includes a relief valve force-loaded to the o...
3. Standard: ASSE 1013.
4. Operation: Continuous-pressure applications.
5. Pressure Loss: Maximum of 5 psig measured across the middle third of the flow range.
6. Size: 2” and 6”
7. Design Flow Rate for 2”: 150 gpm
8. Design Flow Rate for 6”: 600 gpm
9. Pressure Loss at Design Flow Rate: 70 psig for sizes NPS 2 (DN 50) and smaller; 70 psig for NPS 2-1/2 (DN 65) and larger.
10. Body: Bronze for NPS 2 (DN 50) and smaller; ductile or cast iron with interior lining that complies with AWWA C550 or that is FDA approved or stainless steel for NPS 2-1/2 (DN 65) and larger.
11. End Connections: Threaded for NPS 2 (DN 50) and smaller; flanged for NPS 2-1/2 (DN 65) and larger.
12. Configuration: Designed for horizontal, straight-through flow.
13. Valves NPS 2 (DN 50) and Smaller: Ball type with threaded ends on inlet and outlet.
14. Valves NPS 2-1/2 (DN 65) and Larger: Outside-screw and yoke-gate type with flanged ends on inlet and outlet.
15. Air-Gap Fitting: ASME A112.1.2, matching backflow-preventer connection.
PART 3 EXECUTION
3.01 INSTALLATION OF PIPING SPECALTIES
A. Backflow Preventers: Install in each water supply to mechanical equipment and systems and to other equipment and water systems that may be sources of contamination. Comply with authorities having jurisdiction.
1. Locate backflow preventers in same room as connected equipment or system.
2. Install drain for backflow preventers with atmospheric-vent drain connection with air-gap fitting, fixed air-gap fitting, or equivalent positive pipe separation of at least two pipe diameters in drain piping and pipe-to-floor drain.
3. Do not install bypass piping around backflow preventers.
3.02 ADJUSTING
A. Adjust each reduced-pressure-principle backflow preventer in accordance with manufacturer's written instructions, authorities having jurisdiction and the device's reference standard.