This file is a Proposed Progress Schedule for the Kinney Creek Trail Bridge Replacement project in Payette National Forest. The document provides a template for contractors to outline their planned work progress across different completion stages, with instructions for filling out the chart by marking progress through various percentage milestones (0% to 100%). The schedule requires the contractor to submit one copy to the Contracting Officer's Representative (C.O.R.) for review and approval, with specific guidelines for marking work progress using lines rather than solid blocks. The document is designed to track and monitor the project's timeline, allowing the C.O.R. to compare actual progress against the proposed schedule and advise the Contracting Officer of any potential delays.
Text of this file
USDA Forest Service R2-FS-6300-7 (Rev 2/81)) MS Word 2000
PROPOSED PROGRESS SCHEDULE
PROJECT
Kinney Creek Trail Bridge Replacement
UNIT
PayetteNational Forest
CONTRACT NO.
CONTRACT TIME
Compute Time Per Square as follows:
Total Time ( ) days = ( ) days per square Item of Work
% Completion Days Contract Time
INSTRUCTIONS
SUBMITTED BY:
REVIEWED AND APPROVED:
CONTRACTOR
1 Complete CONTRACT TIM block above to determine days per square
2 Insert contract days in brackets at 20%, 40%, etc.
3 Show line through each square for work planned. Please do not block in solid.
4. Submit ONE copy to C.O.R.
Contractor Contracting Officer’s Representative
Date C.O.R.
REVIEWED
1 Approve schedule or submit to C.O. with comments
2 Chart actual progress against proposed progress
3 Advise C.O. when progress falls behind By
4 Distribute as follows: Original to C.O. copies to Contractor, C.O.R. Forest
Date Contracting Officer
Date
GPO 830-257
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Addtl Q_A 127EAV26Q0010.pdf | ||
| Q_A 127EAV26Q0010.pdf | ||
| A6 J3 Drawing Final Bridge Plan.pdf | ||
| SF 30 127EAV26Q0010.pdf | ||
| A6 RFQ 127EAV26Q0010.pdf | ||
| A6 J4 Wage Determination ID20240086.pdf | ||
| A6 J2 Specifications 127EAV26Q0010.pdf | ||
| A6 J8 DesignationofKTRKeyPersonnel-Reps.doc | DOC document | |
| A6 J3 Drawings 127EAV26Q0010.pdf | ||
| A6 J7 BiobasedStatementLetter.docx | DOCX document | |
| A6 J1 Schedule of Items 127EAV26Q0010.xlsx | XLSX spreadsheet | |
| A6 J5 Experience Questionnaire (FS 6300-27).docx | DOCX document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .