This file is a Proposed Progress Schedule for the Kinney Creek Trail Bridge Replacement project in Payette National Forest. The document provides a template for contractors to outline their planned work progress across different completion stages, with instructions for filling out the chart by marking progress through various percentage milestones (0% to 100%). The schedule requires the contractor to submit one copy to the Contracting Officer's Representative (C.O.R.) for review and approval, with specific guidelines for marking work progress using lines rather than solid blocks. The document is designed to track and monitor the project's timeline, allowing the C.O.R. to compare actual progress against the proposed schedule and advise the Contracting Officer of any potential delays.

Text of this file

USDA Forest Service R2-FS-6300-7 (Rev 2/81)) MS Word 2000

PROPOSED PROGRESS SCHEDULE

PROJECT

Kinney Creek Trail Bridge Replacement

UNIT

PayetteNational Forest

CONTRACT NO.

CONTRACT TIME

Compute Time Per Square as follows:

Total Time ( ) days = ( ) days per square Item of Work

% Completion Days Contract Time

INSTRUCTIONS

SUBMITTED BY:

REVIEWED AND APPROVED:

CONTRACTOR

1 Complete CONTRACT TIM block above to determine days per square

2 Insert contract days in brackets at 20%, 40%, etc.

3 Show line through each square for work planned. Please do not block in solid.

4. Submit ONE copy to C.O.R.

Contractor Contracting Officer’s Representative

Date C.O.R.

REVIEWED

1 Approve schedule or submit to C.O. with comments

2 Chart actual progress against proposed progress

3 Advise C.O. when progress falls behind By

4 Distribute as follows: Original to C.O. copies to Contractor, C.O.R. Forest

Date Contracting Officer

Date

GPO 830-257

Other files for this federal contract opportunity

Other files attached to Kinney Creek Trail Bridge Replacement, newest first.
File Type Posted
Addtl Q_A 127EAV26Q0010.pdf PDF
Q_A 127EAV26Q0010.pdf PDF
A6 J3 Drawing Final Bridge Plan.pdf PDF
SF 30 127EAV26Q0010.pdf PDF
A6 RFQ 127EAV26Q0010.pdf PDF
A6 J4 Wage Determination ID20240086.pdf PDF
A6 J2 Specifications 127EAV26Q0010.pdf PDF
A6 J8 DesignationofKTRKeyPersonnel-Reps.doc DOC document
A6 J3 Drawings 127EAV26Q0010.pdf PDF
A6 J7 BiobasedStatementLetter.docx DOCX document
A6 J1 Schedule of Items 127EAV26Q0010.xlsx XLSX spreadsheet
A6 J5 Experience Questionnaire (FS 6300-27).docx DOCX document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .