This is a Questions and Answers document for federal solicitation 127EAV26Q0010 for the Kinney Creel Trail Bridge project. The document addresses four questions from prospective bidders regarding scope clarification and site conditions.

Regarding removal work, contractors must remove charred bridge timbers (which can be disposed of on-site on forest lands under Contracting Officer's Representative direction) and small remaining steel components from the prior timber structure, which must be removed from forest lands and properly disposed of. For rip rap work, the standard STD 964-10-02a is not strictly required; contractors need only rearrange existing material currently at the site to protect the new concrete sills, with this work considered incidental to bridge installation. The document includes multiple photographs of the work site showing the creek, charred timber remains, rocks, and surrounding forest conditions to assist bidders in understanding site conditions and the extent of existing bridge debris remaining.

View the file

Other files for this federal contract opportunity

Other files attached to Kinney Creek Trail Bridge Replacement, newest first.
File Type Posted
SF 30 127EAV26Q0010.pdf PDF
A6 J3 Drawing Final Bridge Plan.pdf PDF
Q_A 127EAV26Q0010.pdf PDF
A6 J5 Experience Questionnaire (FS 6300-27).docx DOCX document
A6 J3 Drawings 127EAV26Q0010.pdf PDF
A6 J6 Progress Schedule.rtf RTF text file
A6 J7 BiobasedStatementLetter.docx DOCX document
A6 J1 Schedule of Items 127EAV26Q0010.xlsx XLSX spreadsheet
A6 J2 Specifications 127EAV26Q0010.pdf PDF
A6 J8 DesignationofKTRKeyPersonnel-Reps.doc DOC document
A6 RFQ 127EAV26Q0010.pdf PDF
A6 J4 Wage Determination ID20240086.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Additional Questions and Answers for Solicitation: 127EAV26Q0010 Kinney Creel Trail Bridge

Q1. Looks like the plans say the bridge is already removed, however, there is a bid item to remove and dispose of existing bridge. Can you clarify if there is a structure there that needs to be removed?

A1. All that needs to be removed is the charred bridge timbers which can be disposed of near the site on forest lands as directed by the COR and the small bits of steel remaining from the prior structure. Those will have to be removed from forest lands and disposed of.

Q2. The new drawings so Rip Rap, STD 964-10-02a. Is that required or is alternative allowed?

A2. All that is required for Rip Rap is to rearrange the material that is presently at the site to protect the new concrete sills this work is incidental to the bridge installation.

Q3. Do you have any pictures of the work site?

Q4. What is the material on the existing bridge?

A5. The previous bridge was a timber structure. See pictures above for current condition.

File details come from the government source that posted it. Updated .