A3 AF66 Schedule of Material Submittals LTUY252018 (For RFQ).xlsx
XLSX spreadsheet 29 KB Posted
- Solicitation number
- W50S8K25QA003
About this file
The file is a Schedule of Material Submittals for a federal construction contract to repair Building 53 for interim occupancy. The project, solicitation number W50S8K25QA003, is issued by the Missouri Army National Guard with a government budget of $60,000 and a contract duration of 45 calendar days after notice to proceed. Material submittals required include plumbing fixtures (due within 14 days of notice to proceed), carpet tiles (due within 10 days of contract award), wall paint (per Statement of Work), and ceiling tiles (due within 14 days of notice to proceed). The project involves repairing interior finishes including restrooms, plumbing, floors, walls, and ceilings, with a construction magnitude between $25,000 and $100,000. Site visit registrations are due by close of business on 25 April 2025, and the full solicitation and attachments will only be posted on SAM.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule SCHEDULE OF MATERIAL SUBMITTALS PROJECT NUMBER LTUY252018 PROJECT TITLE Repair B53 for Interim Occupancy SOLICITATION / CONTRACT NO.
W50S8K25QA003
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
fergusog: Enter any comments pertaining to the submittal
| 1 | Plumbing Fixtures | 1 | 1 | 1 | 1 | 1 | 1 | Within 14 days of NTP. |
| 2 | Carpet Tiles | 1 | 1 | 1 | 1 | Within 10 days of contract award. | ||
| 3 | Wall Paint | 1 | 1 | See Statement of Work. | ||||
| 4 | Ceiling Tiles | 1 | 1 | 1 | Within 14 days of NTP. | |||
| 5 | ||||||||
| 6 | ||||||||
| 7 | ||||||||
| 8 | ||||||||
| 9 | ||||||||
| 10 | ||||||||
| 11 | ||||||||
| 12 | ||||||||
| 13 | ||||||||
| 14 | ||||||||
| 15 | ||||||||
| 16 | ||||||||
| 17 | ||||||||
| 18 | ||||||||
| 19 | ||||||||
| 20 | ||||||||
| 21 | ||||||||
| 22 | ||||||||
| 23 | ||||||||
| 24 | ||||||||
| Schedule of Material Submittals Template, Feb 05 (SAF/AQCP) |