A10. J2_SOI - 12970224R0036.xlsx
XLSX spreadsheet 18 KB Posted
- Attached to
- San Francisquito Fire Station & Barracks Construction Federal contract opportunity
- Solicitation number
- 12970224R0036
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a Schedule of Items (SOI) for the San Francisquito Fire Station & Barracks Construction solicitation (Solicitation #12970224R0036) issued by the USDA Forest Service.
The project includes construction of a new 6,467 SF fire station building, a 390 SF fire pump house, a 2,700 LF new waterline, and related civil/site work. The solicitation also includes optional bid items for a 3,695 SF barracks building, landscaping/irrigation, and a new well with waterline extension. The anticipated contract is a single-award, firm-fixed-price contract with a 540-calendar day period of performance starting in September 2024. A pre-proposal conference is scheduled for July 23-24, 2024, and proposals are due by August 23, 2024. The contract is set aside for small businesses, with a bid bond requirement of 20% of the total contract value and 100% performance/payment bonds. The estimated contract value is over $10 million.
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule of Items
| CONTINUATION OF SF 1442 - SECTION B |
| SCHEDULE OF ITEMS |
| PROJECT TITLE | San Francisquito Fire Station & Barracks Construction | ||||
| UNIT | Angeles National Forest | ||||
| SOL # | 12970224R0036 | ||||
| Issuing Office | Specialized Project Operations Center (SPOC) Southwest Branch | ||||
| BASE ITEMS | |||||
| ITEM NO. | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 0001 | MOBILIZATION - All Base Items | 1 | LS | $0.00 | $0.00 |
| 0002 | BONDING - Base Only | 1 | LS | $0.00 | $0.00 |
| 0003 | FIRE STATION BUILDING | 6,467 | SF | $0.00 | |
| Substructuer Foundations | 1 | LS | $0.00 | $0.00 | |
| Shell - Superstructure | 1 | LS | $0.00 | $0.00 | |
| Interiors | 1 | LS | $0.00 | $0.00 | |
| 0004 | FIRE PUMP HOUSE | 390 | SF | $0.00 | |
| Substructuer Foundations | 1 | LS | $0.00 | $0.00 | |
| Shell - Superstructure | 1 | LS | $0.00 | $0.00 | |
| Interiors | 1 | LS | $0.00 | $0.00 | |
| 0005 | NEW WATERLINE | 2,700 | SF | $0.00 | |
| Sitework: Site Prep, excavation/Trench water supply | 1 | LS | $0.00 | $0.00 | |
| Civil/Mechanical Utilities | 1 | LS | $0.00 | $0.00 | |
| Water Supply | 1 | LS | $0.00 | $0.00 | |
| 0006 | CIVIL WORK & SUPPORTING FACILITIES | 1 | LS | $0.00 | |
| Building Site Work | 1 | LS | $0.00 | $0.00 | |
| Site Improvements - Roadways, parking lots, retaining walls, sidewalks | 1 | LS | $0.00 | $0.00 | |
| Utilities (Includes electrical, gas, telecomm, lighting, sewer, water, fire water, water storage tank | 1 | LS | $0.00 | $0.00 | |
| SUBTOTAL - Base Only | $0.00 | ||||
| SUBTOTAL - Base with Base Bonding | $0.00 | ||||
| OPTIONAL ITEMS | |||||
| ITEM NO. | SUPPLIES/SERVICES | QUANTITY | UNIT | UNIT PRICE | AMOUNT |
| 1001 | BARRACKS BUILDING | 3,695 | SF | $0.00 | |
| Mobilization -Barracks Building | 1 | LS | $0.00 | $0.00 | |
| Substructuer Foundations | 1 | LS | $0.00 | $0.00 | |
| Shell - Superstructure | 1 | LS | $0.00 | $0.00 | |
| Interiors | 1 | LS | $0.00 | $0.00 | |
| 1002 | LANDSCAPING & IRRIGATION | LS | $0.00 | ||
| Mobilization - Landscaping & Irrigation | 1 | LS | $0.00 | $0.00 | |
| Site Improvments - Planting per plans | 1 | LS | $0.00 | $0.00 | |
| Site Improvements - Irrigation per plans | 1 | LS | $0.00 | $0.00 | |
| 1003 | NEW WELL & WATERLINE EXTENSION | $0.00 | |||
| Test drilling Primary Site | 1 | LS | $0.00 | $0.00 | |
| Test drilling Secondary Site | 1 | LS | $0.00 | $0.00 | |
| Additional Drilling Primary or Secondary Site | 200 | LF | $0.00 | $0.00 | |
| Drill Cuttings Pit BMPs Primary or Secondary Site | 1 | LS | $0.00 | $0.00 | |
| Well Development Primary or Secondary Site | 1 | LS | $0.00 | $0.00 | |
| Extend water distribution line | 1,500 | LF | $0.00 | $0.00 | |
| Development of Well Building | 1 | LS | $0.00 | $0.00 | |
| Mobilization - Well & Waterline Extension | 1 | LS | $0.00 | $0.00 | |
| SUBTOTAL - ALL Options | $0.00 | ||||
| SUBTOTAL (Base + Option 1) | $0.00 | ||||
| SUBTOTAL (Base + Option 2) | $0.00 | ||||
| SUBTOTAL (Base + Option 3) | $0.00 | ||||
| 1004 | BONDING - Base + ALL Options | 1 | LS | $0.00 | $0.00 |
| TOTAL CONTRACT VALUE (Base + ALL Options) | $0.00 | ||||
| B.2 SCHEDULE NOTES | |||||
| 1. Offeror must fill in the UNIT price (highlighted in yellow) and offeror info ONLY. Spreadsheet is formatted to auto populate all pricing totals. Do NOT edit any other fields. Please return the schedule of items in Microsoft Excel. | |||||
| 2. A bid bond is required for this contract. The Successful awardee that receives the contract shall provide the bid bond as part of the proposal response package. The digitally signed payment and performance bonds are due within 10 calendar days post contract award. | |||||
| 3. Responses for quantities less than those listed in the numbered items or missing (without) prices for each item and/sub-item may be rejected. | |||||
| 4. Mobilization. No additional payment will be made to the contractor for any travel incurred while being on the site for the duration of the project. This includes pre-bid and pre-construction meetings and field observations as planned throughout the timeline of the project. | |||||
| 5. Bonding. Provide the anticipated reimbursable cost for bonding. The schedule reflects bonding cost should the Government only award base items or base + option items. The base and option bonding line items represent the range the flat rate for reimbursable bonding costs is not anticipated to exceed in the performance of this work with the exception of modifications for differing site conditions. | |||||
| 6. Base Items 0002-0005. Reference items in the Drawings (Sheet G-002) specified as “BASE” and Corresponding Specifications. The work in the base bid items include all work related to the construction of the fire station building including all structural, mechanical, electrical, plumbing, and utilities as specified on the drawings. Site work will include all excavation, over-excavation, retaining walls, sidewalks, as well as utilities as stated in the “Base” items. Work will also include the waterline base items, water tank, fire pumphouse, parking lots, utilities for the fire station, and sewer pits. A critical element of this project will be the coordination of utility service from Los Angeles Department of Water and Power (DWP) for temporary water source and Southern California Edison (SCE) for temporary and permanent power. | |||||
| 7. Option 1001. Reference items in the Drawings (Sheet G-002) specified as “OPTION 1” and corresponding Specifications. The work in this option bid item includes all incidental work related to the BARRACKS building including all structural, mechanical, electrical, plumbing, and utilities as specified on the drawings. Site work including all excavation and over-excavation, retaining wall, as well as utilities as stated in the “Base” items including those in the vicinity of the barracks building are still included in the Base bid. | |||||
| 8. Option 1002. Reference items in the Drawings (Sheet G-002) specified as “OPTION 2” and corresponding Specifications. The work in this option bid item includes all work specified in the L sheets including landscaping, planting and irrigation as specified in the drawings and specifications. | |||||
| 9. Option 1003. Reference items in the Drawings (Sheet G-002) specified as “OPTION 3” and corresponding Specifications and Supplemental Specifications for the new well system. The work in this option bid item includes all incidental work related to a new vertical well and extension of the waterline construction north of the Bouquet Aqueduct and as shown on the drawings. Contractor will construct a vertical groundwater well near the new fire station and barracks administrative site. This option item will determine the availability and quality of groundwater for drinking at the new fire station and barracks location. The work will include test drilling, construction of individual drilled water wells, completion of water analysis, well logs, and test pump reports, capping successful wells and abandoning wells that do not meet production and quality requirements. A hydrogeologic assessment report will be conducted and made available to the Contractor upon its completion which will identify a primary and secondary well site. | |||||
| PRICE SUBMITTED BY | |||||
| Company Name | |||||
| POC | |||||
| POC Phone | |||||
| POC Email | |||||
| UEI SAM No. |
File details come from the government source that posted it. Updated .