A10. J14_ProgressSched (FS 6300-7).rtf
RTF text file 196 KB Posted
- Attached to
- San Francisquito Fire Station & Barracks Construction Federal contract opportunity
- Solicitation number
- 12970224R0036
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a proposed progress schedule for the San Francisquito Fire Station & Barracks Construction project, a federal contract opportunity issued by the USDA Forest Service Region 5 Angeles National Forest.
The project involves the construction of a new single-story fire station building of approximately 7,000 square feet with bay space for up to four fire engines and 15 full-time employees, as well as a new single-story barracks building of approximately 3,500 square feet that will provide housing for 2 engine crews. The contract also includes optional bid items such as a new vertical well, landscaping using drought-tolerant plants, and a new waterline. The anticipated performance period is approximately 540 calendar days from the Notice to Proceed (NTP) effective date. The solicitation period is proposed to be from July 16, 2024 to August 23, 2024, with a pre-proposal conference/site visit on July 23-24, 2024. The anticipated contract award date is on or about September 13, 2024, with a contract value expected to be more than $10 million. The contract will be a single award Firm Fixed Price (FFP) and is set aside for small businesses.
Text of this file
USDA Forest Service R2-FS-6300-7 (Rev 2/81)) MS Word 2000
PROPOSED PROGRESS SCHEDULE
PROJECT
San Francisquito Fire Station & Barracks Construction
UNIT
Angeles National Forest
CONTRACT NO.
CONTRACT TIME
Compute Time Per Square as follows:
Total Time ( ) days = ( ) days per square Item of Work
% Completion Days Contract Time
INSTRUCTIONS
SUBMITTED BY:
REVIEWED AND APPROVED:
CONTRACTOR
1 Complete CONTRACT TIM block above to determine days per square
2 Insert contract days in brackets at 20%, 40%, etc.
3 Show line through each square for work planned. Please do not block in solid.
4. Submit ONE copy to C.O.R.
Contractor Contracting Officer’s Representative
Date C.O.R.
REVIEWED
1 Approve schedule or submit to C.O. with comments
2 Chart actual progress against proposed progress
3 Advise C.O. when progress falls behind By
4 Distribute as follows: Original to C.O. copies to Contractor, C.O.R. Forest
Date Contracting Officer
Date
GPO 830-257
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .