This is a Statement of Work (SOW) for the replacement of roofs and gutters on two housing units (B034 and B035) located at 49794 and 49796 Blue Ridge Parkway, Laurel Springs, North Carolina 28644, near the Blue Ridge Parkway in Alleghany County.
The contractor shall remove and replace approximately 3,600 square feet of asphalt shingles with 30-year architectural dark gray shingles, including installation of #30 (or synthetic) underlayment, drip edges, ridge vent systems, and waterproof roof boots. Additionally, the contractor must remove and replace approximately 420 linear feet of gutters with downspouts and install approximately 270 linear feet of gutter guards on both buildings. Work includes inspecting and repairing damaged roof supports, fascia boards, and roof decking as necessary, and replacing all existing flashing. The contractor shall furnish all supervision, personnel, equipment, transportation, materials, and incidentals; provide proof of liability insurance; and supply an onsite portable toilet per OSHA requirements. Materials must be stored on pavement at the work location, and all work must comply with current local, state, and federal codes and OSHA guidelines for work on elevated surfaces, including personal fall arrest systems. Work is permitted Monday through Friday from 7:30 a.m. to 4:30 p.m. only, with no weekend or Federal holiday work allowed. Required submittals include contractor liability insurance, warranty information, a site-specific safety plan, and personal fall arrest system inspection sheets and training records. The contractor must provide a minimum one-year warranty against defects and a minimum five-year workmanship warranty. Upon project completion, the contractor shall remove all tools, equipment, debris, and trash, then contact the Contracting Officer's Representative to arrange final inspection. The Contracting Officer will issue a letter of final acceptance upon correction of any deficiencies and receipt of all closeout submittals.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Attachment_0008_Updated_Eval_Criteria_140P5126Q0036_0001.pdf | ||
| Sol_140P5126Q0036_Amd_0001.pdf | ||
| B09_Attachment_0007_Questions_and_Answers_140P5126Q0036_0001.pdf | ||
| Sol_140P5126Q0036.pdf | ||
| B08_Attachment_0002_WDOL_WD_140P5126Q0036_BLRI_R-G.pdf | ||
| B08_Attachment_0006_PPQ_140P5126Q0036.pdf | ||
| B08_Attachment_0003_Bidsheet_140P5126Q0036_BLRI_R-G.pdf | ||
| B08_Attachment_0005_Site_Visit_Information_140P5126Q0036.pdf | ||
| B08_Attachment_0004_Site_Specific_Safety_Plan_140P5126Q0036.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPLACE ROOFS AND GUTTERS ON 2 BLUFFS HOUSING UNITS
(B034 & B035)
49794 & 49796 BLUE RIDGE PARKWAY
Laurel Springs NC, 28644
PART 1 - GENERAL
DESCRIPTION OF WORK
A. This contract provides for the removal and replacement of roof and gutter systems for two houses, buildings B034 & B035 at Bluffs Housing: removal of approximately 36-Sq /3,600 -SF of asphalt shingles and replace with architectural 30 year shingles and #30 underlayment (note: underlayment can be replaced with synthetic underlayment), repair/replace damaged plywood sheeting/facia boards, replace drip edge, roof boots, install roof underlayment, installation of a ridge vent(s) along the length of the buildings, the removal and replacement of approximately 420-LF of gutter with downspouts and installation of approximately 270-LF of gutter guards on buildings. The buildings are a two-story residence with an asphalt shingle roofs.
B. Site visits are highly recommended.
C. The buildings may be occupied during this contract period.
D. The contract work for B034 and B035 includes:
1. Remove and dispose of the existing asphalt shingle roof(s) and roofing underlayment off site. The combined roof size of B034 & B035 is approximately 36-Sq /3,600 -SF.
2. Protect the building structures and contents from weather and other potentially damaging elements.
3. Inspect the existing roof supports (rafters) and fascia boards, replace damaged facia boards.
4. Repair or replace in kind as necessary damaged roof decking/sheathing revealed by inspection.
5. Replace in kind all existing flashing.
6. Install new 30-pound asphalt saturated roofing underlayment or synthetic underlayment.
7. Install new dark gray 30-year architectural shingles. (Color must be approved by COR.)
8. Install new drip edges around the entire perimeter of the roof.
9. Install full length ridge cap(s) roof vent system.
10. Install new waterproof vent collars/roof boots.
11. Remove and replace approximately 420 linear feet of gutter and associated downspouts on buildings B034 &
B035. (color must be approved by COR)
12. Install gutter guards on all gutters.
E. All work will be performed under a single contract.
F. Work and materials shall adhere to the following mitigations:
1. Replacement architectural asphalt shingles should match existing shingles in size, color, and texture. New shingles/gutters and downspouts color must be approved by COR before installation.
2. Materials shall be stored on pavement at work location.
3. MUST follow ALL OSHA guidelines for work performed on an roofs/elevated surfaces and personal fall protection system.
1.01 LOCATION AND ACCESS
A. The project site is located near the Blue Ridge Parkway in Alleghany County NC, The addresses are 49794
& 49796 Blue Ridge Parkway Laurel Springs NC, 28644. Housing is located right before the maintenance shop.
1.02 CONTRACTOR-FURNISHED ITEMS
A. The Contractor shall furnish all necessary supervision, personnel, equipment, transportation, materials, and incidentals required to complete the contract requirements.
B. Contractor shall provide proof of liability insurance for all personnel working in completion of this project.
C. Contractor will provide onsite portable toilet as required by OSHA 29 CFR 1910.141.
1.03 WORK CONDITIONS AND LIMITATIONS
A. FACILITY USE
B. CONTRACTOR’S USE OF PREMISES
1. Confine on-site material storage, equipment, and vehicle parking, and staging to paved parking areas or other areas specifically designated by the Contracting Officer’s Representative (COR)
2. Keep job site clear of trash and debris. Dispose of any trash, debris, and other unusable material legally at authorized facilities on non-Federal land.
C. FIELD VERIFICATION
1. The measurements and quantities specified are estimates and provided for information only. The
Contractor must verify all locations, dimensions and conditions affecting the work.
1.04 QUALITY ASSURANCE
1. All proposed materials and methods must meet or exceed the current local, state, and federal codes, standards, and regulations applicable to the contract work
2. All personnel performing the work shall be fully qualified and experienced in the type of work they will execute.
3. MUST FOLLOW ALL OSHA requirements for working on roofs/elevated surfaces, to include Personal Fall arrest systems.
1.05 WARRANTIES
A. Building components: Minimum 1-year warranty against defects. Provide a minimum 5-year warranty for workmanship.
B. Prior to beginning work, report to the COR any conflict in warranty requirements, work scheduling or material availability before proceeding with the work.
1.06 MATERIAL HANDLING
A. Deliver materials to the job site as per COR instructions. Comply with all manufacturers’ recommendations for storage, protection and handling.
PART 2 - MATERIAL
2.01 GENERAL
A. Use new materials except as otherwise approved by the Contracting Officer (CO).
2.02 REQUIRED SUBMITTALS AND APPROVALS
A. LIST OF REQUIRED SUBMITTALS
1. Contractor Liability
Insurance
2. Warranty Information
3. Site Specific Safety Plan (see attached checklist for minimum components)
4. Inspection sheets and training records for personal fall arrest systems (PFAS) as required by OSHA.
B. CHANGES TO MATERIAL REQUIREMENTS
1. Any proposed changes by the Contractor to the construction materials shall be submitted in writing to the COR
PART 3 - EXECUTION OF WORK
3.01 GENERAL
A. SERVICE INTERRUPTION
1. Indicate by work schedule expected periods of construction to avoid conflict with operations.
2. Work will be allowed Monday thru Friday from 7:30am to 4:30pm and no work will be allowed on weekends or Federal holidays.
B. SITE INVESTIGATION
1. The Contractor is responsible for investigating site conditions in the vicinity of the required work for any hazards or obstacles which may increase time or cost of the work.
C. CHANGES TO CONSTRUCTION METHODS
1. Any proposed change by the Contractor to the specified construction methods and manufacturer’s instructions must be submitted in writing to the CO along with the justification for the proposed change. Approval from the CO is required for changes in specified construction methods.
D. PROTECTION OF WORK SITE
1. Work sites are not protected by fencing but are on a private drive.
2. Maintain the work area and approaches clean and free from trash and debris to reduce interference with ongoing maintenance operations.
3. Provide a safe bypass for tenants, NPS employees, and contractor’s personnel.
3.02 PROJECT CLOSEOUT
A. CLEANUP
1. Remove all tools, equipment, excess materials, construction debris, and trash from the project site. Leave project site clean and ready for use at the time of final inspection.
2. Legally dispose of all excess and unusable materials at authorized disposal facilities.
B. FINAL INSPECTION AND ACCEPTANCE OF WORK
1. When all work including any site restoration and cleanup has been completed, the Contractor shall contact the COR to arrange the final inspection.
2. The Contractor shall be notified of any deficiencies found during the final inspection. After all deficiencies have been corrected and all required closeout submittals have been forwarded to the COR, the CO will issue a letter of final acceptance and request the release of claims.
| PART 1 - GENERAL |
| 1.01 LOCATION AND ACCESS |
| 1.02 CONTRACTOR-FURNISHED ITEMS |
| 1.03 WORK CONDITIONS AND LIMITATIONS |
| A. FACILITY USE |
| B. CONTRACTOR’S USE OF PREMISES |
| C. FIELD VERIFICATION |
| 1.04 QUALITY ASSURANCE |
| 1. All proposed materials and methods must meet or exceed the current local, state, and federal codes, standards, and regulations applicable to the contract work |
| 2. All personnel performing the work shall be fully qualified and experienced in the type of work they will execute. |
| 3. MUST FOLLOW ALL OSHA requirements for working on roofs/elevated surfaces, to include Personal Fall arrest systems. |
| 1.05 WARRANTIES |
| 1.06 MATERIAL HANDLING |
| PART 2 - MATERIAL |
| 2.02 REQUIRED SUBMITTALS AND APPROVALS |
| A. LIST OF REQUIRED SUBMITTALS |
| B. CHANGES TO MATERIAL REQUIREMENTS |
| PART 3 - EXECUTION OF WORK |
| A. SERVICE INTERRUPTION |
| B. SITE INVESTIGATION |
| C. CHANGES TO CONSTRUCTION METHODS |
| D. PROTECTION OF WORK SITE |
| 3.02 PROJECT CLOSEOUT |
| A. CLEANUP |
| B. FINAL INSPECTION AND ACCEPTANCE OF WORK |