610535 WORCESTER FAP No. STP/HPP-0033(047)X Pedestrian and Bicycle Improvements on Pleasant Street
Solicitation number
BD-27-1030-0H100-0H002-130915
Issued by
Worcester County, Massachusetts

About this file

This is a Project Utility Coordination (PUC) Form prepared by the Massachusetts Department of Transportation Highway Division for Proposal No. 610535-134928, which concerns pedestrian and bicycle improvements on Pleasant Street in Worcester, Massachusetts. The project involves coordination with multiple utilities including Eversource Gas, National Grid, and Worcester Department of Public Works Water Division to manage the relocation of underground and aerial utility infrastructure. The primary scope includes installation of 2-inch, 4-inch, and 8-inch HDPE gas mains totaling approximately 6,560 linear feet across multiple stations on Pleasant Street, along with service relays, tie-overs, pressure testing, nitrogen purging, and abandonment of existing cast iron, carbon steel, and brass gas mains. The form identifies four utility poles requiring relocation and notes a project revision date of April 2, 2026, with a scheduled advertisement date of June 27, 2026.

The utility coordination plan establishes a phased approach requiring the contractor to provide seven calendar days advance notification to the District Construction Office and ensure 30 days advance notice-to-proceed for utility relocations. Estimated work duration for utility operations is 190 work days, with no early benefit planning permitted for district-initiated early relocations. Critical constraints include seasonal restrictions prohibiting gas line installation from November 15 through March 15, and requirements for the contractor to provide unimpeded access including snow removal, clearing, grubbing, guard rail removal, and tree removal at costs deemed incidental to the project. Key utility contacts include Jeffrey Evans-Mongeon from Eversource Gas and Mike Daigneault from Worcester DPW Water, with design coordination through Toole Design represented by Coleen Lautrup. The form requires incorporation of utility coordination timelines into all contractor schedules including pre-construction, baseline, subnet, and monthly submissions.

View the file

Other files

File Type Posted
610535 - Notice to Contractors.pdf PDF
A00820-610535.pdf PDF
WORCESTER-610535-134928-A-1.pdf PDF
A00809-610535.pdf PDF
A00861-610535.pdf PDF
610535 - Plan Holders List 7-27-2026.pdf PDF
Link to Bid Opening 7-28-2026~1.pdf PDF
A00801-610535.pdf PDF
BIDS OPENED - Tuesday - July 28-2026.pdf PDF
610535 Bid Items List.txt TXT text file
A00860-610535.pdf PDF
A00816-610535.pdf PDF
A00811-610535.pdf PDF
610535 - Plan Holders List 7-15-2026.pdf PDF
WORCESTER-610535-134928-A-2.pdf PDF
610535 - Bid Tabulations.pdf PDF
A00802-610535~1.pdf PDF
A00862-610535.pdf PDF
A00870-610535.pdf PDF
A00875-610535.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Massachusetts Department Of Transportation Highway Division Proposal No. 610535-134928

A00808 - 1

DOCUMENT A00808

Project Utiltity Cordination Form

Massachusetts Department Of Transportation Highway Division

A00808 - 2

THIS PAGE INTENTIONALLY LEFT BLANK

Revision

Date:

M ass DO

T PM

Total Poles Relocated:

4/2/2026

PRIN

TED

Yes N o Agreem ent

YES

N O

YES

N

O

UG

O H

Eversource G as

Jeffrey Evans-M ongeon

508-305-6970 Jeffrey.Evans-M ongeon@ eversource.com

X X

X X

W orcester DPW

W ater M ike Daigneault 508-929-1300 ext.

Daigneaultm ci.w orcester.m a.us

N /A

N /A

X X

X

Suggested Sequence of Relocation (Based on Consultant proposed construction staging) The sequence as detailed on the follow ing pages is based on the consultants proposed staging plan. This inform ation w as com piled through m eetings that included all of the utilities listed below along w ith the designer and the City of W orcester. The inform ation provided is the best available inform ation prior to project advertisem ent.

U tility Relocation N otes for M assDO

T Contractor Unless otherw ise noted by Contract, the M assDO

T Contractor is to provide the District Construction O ffice w ith 7 Calendar Days advance notification in order to validate the current progress and provide the required 30 Days advance notice-to-proceed for the first Utility - and each subsequent Utility. These advance notifications are to be identified in the Contractor's Schedules (Pre-Con preparation, Baseline, Subnets, and Updated/M onthly Schedules) as specified in Subsection 8.02 (for DBB Contracts) and/or Section 9 (of DB Contracts). N ote: The durations included below do not include these lead-tim

es. See Additional 'Im portant Basis notes for Contractor' - on last PUC Form page.

Additional notes:

U tilities

U nderground (U

G

/Aerial (O H)

Route/Street:

Toole Design Coleen Lautrup

857-398-6511

Scope, Budget, Duration Subm itted Reim bursem ent

U tility Com pany Contact

O ffice #

Cell # Em ail

N on-Reim b'le N otes

Potential for District Initiated Early Relocation *

U tilities O n Bridge/Structure

Pleasant Street

TBD

Adetoyin O laoye

Consultant:

Contact:

O ffice #

Cell # Em ail clautrup@ tooledesign.com

W orcester

610535 R. Goodale

N ational Grid

City/Tow n:

PU

C Com pleted by:

Project File #:

U tility Pole Set:

CO

N

TACTS AN

D GEN

ERAL UTILITY IN

FO

RM

ATIO

N

Project U tilities Coordination (PU

C) Form

Resident Engineer:

Scheduled Ad Date:

Betterm ent W ork X

6/27/2026

Proposal No. 610535-134928

A00808 - 3 mailto:clautrup@tooledesign.com mailto:clautrup@tooledesign.com mailto:clautrup@tooledesign.com mailto:clautrup@tooledesign.com

Yes N o 4/2/2026

X

PRIN

TED

Yes N o

X

Exclusive U tility on site

Concurrent U tilities

Contractor O ff-Site Contractor Concurrent

C = Contractor U = Utility Co.

Utility working with no other

Utilities in vicinity

Utility working with other Utilities on site

No Contractor physical construction operations on-site

(while Utility is Contractor and

Utility are working on-site - but NOT in the same vicinity

C

Task: 4 U

X X

N o

U X

X N o U

X X

N o

U X

X N o U

X X

N o

U X

X N o U

X X

N o

U X

X N o U

X X

N o

U

X X

N o

123456789

M obilize &

M aterials Delivery and Project Planning

1020342015

Sub-Total

U nless otherw ise specified in the M assDO

T Construction Contract, or unless specifically noted w ithin this PU

C Form , these durations (herein) are based upon the Contractor providing unim peded access to the U tility com pany to perform

U tility relocations (see N ote 5 - Access).

Access - U nless otherw ise noted in the Contract, and in addition to the 'enabling' notes above, the Contractor m ust provide safe and unim peded access (for trucks, lifts, cranes, etc.) to the U tilities, to allow for the proposed relocation(s) -including but not lim ited to snow rem oval, clearing and grubbing, guard rail rem oval, barrier rem oval, tree rem oval, and grading. Any costs associated w ith these tasks are deem ed to be incidental to the project.

For all M assDO

T construction contracts issued after January 2014, the new U tility Coordination/docum entation specification is required. This is Section 8.14 in Design-Bid-Build Contracts (see Design-Build index reference for applicable section #).

Prior to starting any and all enabling w ork for U tilities, the Contractor is to plan in advance w ith subm ittals and approved durations.

* Potential District Initiated Early U tility Relocation - if noted herein, the District reserves the right to initiate early utility relocation in advance of the Contract N

TP. In subm itting a bid price and in the developm ent/basis of the Baseline Schedule, the Contractor shall not plan the W ork w ith the potential benefit of any form of 'early utility relocation.' As a requirem ent of the Baseline subm ission, unless otherw ise noted in this Specification, the earliest that the first U tility com pany is to receive the 30 days advance notification to m obilize to the site, w ill be 7 calendar days after the pre-construction m eeting and never sooner than 7 days after the Contract N

TP.

"Concurrent U tilities" operations noted herein, are to signify those U tility Com pany operations that can be w orked concurrently (e.g. U tility A and U tility B w ork on-site together) - M assDO T and the Contractor are to prepare N

TPs to U tilities accordingly.

RESPONSIBLE PARTY

Concurrent / Exclusive U tility W ork Contractor note: In planning and executing the w ork, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 colum ns.

DESCRIPTIO

N

- U tility Relocation Phases, Tasks and Activities

Potential Access Restraint (Yes/No)

Eversource G as

U

TILITY O

PERATIO

N

S - U nderground

Enabling' w ork by the Contractor - Coordinate w ith Eversource during betterm ent w ork installation.

Is 'enabling' (prep) w ork, by the Contractor, necessary prior to the start of the first series of utility relocations:

Has any of the U tility w ork been identified to w ork concurrently

PU

C FO

RM

- CO

N

TIN

U

ED

Reason/Note (optional)

Access Restraint & Lim itations of O perations N otes

Should an AR be considered for the Contractor ?

Estimated Duration (Work Days) by Utilities (Lead time not included)

"Potential Access Restraints" noted w ithin this PU

C Form are for planning purposes. See M assDO T Contract for Contractual Access Restraints (refer to Subsections 8.02, 8.03, and/or 8.06 for Design Bid Build Contracts and Volum e II Section 9 for Design Build Contracts).

U tility non-w ork periods - For planning purposes, the durations above contain som e non w ork days (contingency) for N ew

England conditions (precipitation, high tem peratures, low tem peratures, snow

, ice). Gas line w ork how ever, typically has a seasonal restriction and can N

O T be installed from

15-N ovem ber to 15-M arch. M unicipally O w ned Electric and Gas U tilities are also restricted from proceeding from 15-N ovem ber to 15-M arch. The Contractor shall (and the CTD plan) reflect this calendar restriction w ithin the schedule (unless otherw ise note).

IM

PO

RTAN

T BASIS N

O

TES - FO

R CO

N

TRACTO

R

Install 2" IP HDPE Gas M ain in project scope bounds on Pleasant St (Side Street Stubs)

Install 4" IP HDPE Gas M ain in project scope bounds on Pleasant St (2,735') STA. 16+69.82 to STA 43+75

Install 8" IP HDPE Gas M ain in project scope bounds on Pleasant St (1,080') STA 44+10 to STA 53+ 20.5

Install 4" IP HDPE Gas M ain in project scope bounds on Pleasant St (2,745') STA 53+25 to STA 80+70

Service relays & tie-overs (13 Relays, 36 Tie overs)

Backfill & Site restoration and dem obilize

Pressure Test and nitrogen purge m ain into service

Abandon / Retire old 4", 6", 8" CI, CS, BS Gas M ain

Pig new m ain

A00808 - 4

A00808 PUC Form
A00808 PUC Form
Page 1Contacts & General Info
Page 2&3 - PUC detail