900455-20251218 Bid Tabulation.pdf
PDF 127 KB Posted
- Solicitation number
- S-KE0010-00015122
- Issued by
- Lane County, Oregon
About this file
This is a Bid Tabulation Summary Report for the City of Eugene, Oregon in collaboration with the Oregon Department of Transportation (ODOT) for the Regional Bicycle Enhancements Eugene 2024 project. The project involves the installation of 96 bicycle racks across 26 locations in Springfield and includes mobilization, temporary work zone traffic control, and pollution control plan implementation. The bid tabulation documents submissions from 13 bidders, with bids received by the October 30, 2025 deadline at 2:00 p.m., followed by a virtual bid opening at 2:05 p.m. The contract is scheduled for completion by April 6, 2026, with liquidated damages of $800 per work day for delays. The project scope encompasses standard steel pipe bike racks, powder-coated black, with specific mounting and installation requirements per technical specifications.
The bid tabulation reflects significant variation in pricing among responsive bidders, with total project bids ranging from approximately $23,915 to $94,900. Key line items include Mobilization (ranging from $1,138 to $20,000), Temporary Work Zone Traffic Control (ranging from $166.67 to $3,500), Pollution Control Plan (ranging from $166.67 to $1,500), and Bicycle Racks installation (ranging from $221 to $850 per unit). The Engineer's Estimate totaled $53,815.36. Contractors were required to submit a Bid Guaranty of 10 percent of the bid amount, proof of valid Certificate of Registration with the Construction Contractor Board, and demonstrate experience with at least three similar public sector projects. The contract is funded through Federal Highway Administration (FHWA) funds, with the project budget ranging from $33,000 to $44,500. Prevailing wage requirements comply with federal Davis-Bacon and Oregon Bureau of Labor and Industries (BOLI) standards, with workers paid the higher of applicable federal or state rates. The City intends to award to the lowest Responsive Responsible Bidder, with 30 percent of contract work to be performed by the contractor's own organization.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 900455-20251124 Addendum 2.pdf | ||
| 900455 specifications.pdf | ||
| 900455 Instructions to Bidders.pdf | ||
| 900455-20260130 Intent to Award.pdf | ||
| 900455 plans.pdf | ||
| Lemon Juice.docx | DOCX document | |
| 900455 bid forms.pdf | ||
| 900455-20251210 Addendum 3.pdf | ||
| 900455 contract and bonds.pdf | ||
| 900455 tier.pdf | ||
| 900455-20251024 Addendum 1.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pay Item No. Quantity Unit Extended Value Unit Value Extended Value Unit Value Unit Value Extended Value
2100010 1.00 LS $5,000.00 $3,000.00 $3,000.00 $1,850.00 $5,200.00 $5,200.00
2250010 1.00 LS $5,000.00 $700.00 $700.00 $4,000.00 $1,800.00 $1,800.00
2900010 1.00 LS $500.00 $500.00 $500.00 $350.00 $175.00 $175.00
9999999 96.00 EA $26,400.00 $275.00 $26,400.00 $306.00 $350.00 $33,600.00
$36,900.00 $30,600.00 $40,775.00
Pay Item No. Quantity Unit Extended Value Unit Value Extended Value Unit Value Unit Value Extended Value
2100010 1.00 LS $3,700.00 $1,850.00 $1,850.00 $1,138.00 $4,200.00 $4,200.00
2250010 1.00 LS $10,000.00 $5,750.00 $5,750.00 $2,717.00 $2,000.00 $2,000.00
2900010 1.00 LS $190.00 $3,100.00 $3,100.00 $923.00 $200.00 $200.00
9999999 96.00 EA $28,800.00 $370.85 $35,601.60 $437.00 $425.00 $40,800.00
$42,690.00 $46,301.60 $47,200.00
Pay Item No. Quantity Unit Extended Value Unit Value Extended Value Unit Value
2100010 1.00 LS $5,105.03 $14,219.16 $14,219.16 $8,000.00
2250010 1.00 LS $3,000.00 $6,852.52 $6,852.52 $5,000.00
2900010 1.00 LS $1,000.00 $520.00 $520.00 $300.00
9999999 96.00 EA $41,945.28 $373.42 $35,848.32 $850.00
$51,050.31 $57,400.00
$81,600.00
GRAND TOTAL: $53,815.36 $94,900.00
4 Bicycle Racks (Purchase and Installation) $436.93 $300.16 $28,815.36
$5,000.00
3 Pollution Control Plan $1,000.00 $1,500.00 $1,500.00 $300.00
2 Temp. Work Zone Traffic Control, Complete $3,000.00 $3,500.00 $3,500.00
Extended Value
1 Mobilization $5,105.03 $20,000.00 $20,000.00 $8,000.00
Line No Description Unit Value Unit Value Extended Value
Farline Bridge Inc Joseph Muller Construction Cavallaro Earthworks Anderson's Erosion Control
Bidder 10 Bidder 11 Bidder 12 Bidder 13
GRAND TOTAL: $43,332.91 $35,576.00
4 Bicycle Racks (Purchase and Installation) $300.00 $413.19 $39,666.24
3 Pollution Control Plan $190.00 $166.67 $166.67
Bidder 5 Bidder 6
Wildish Construction Co Dallum Build Company LLC
Unit Value Unit Value Extended Value
$3,700.001 Mobilization
2 Temp. Work Zone Traffic Control, Complete
$923.00
$41,952.00
$3,333.33 $3,333.33 $1,138.00
$10,000.00 $166.67 $166.67 $2,717.00
Great Western Corporation 2G Construction Knife River Corporation -
Northwest
Extended Value
Bidder 7 Bidder 8 Bidder 9
Line No Description
$29,376.00
GRAND TOTAL: $23,915.00 $35,576.00
4 Bicycle Racks (Purchase and Installation) $275.00 $221.00 $21,216.00
$4,000.00
3 Pollution Control Plan $500.00 $258.00 $258.00 $350.00
2 Temp. Work Zone Traffic Control, Complete $5,000.00 $1,003.00 $1,003.00
Extended Value
1 Mobilization $5,000.00 $1,438.00 $1,438.00 $1,850.00
Line No Description Unit Value Unit Value Extended Value
BID TABULATION SUMMARY REPORT
Project Number 900455 Project Name Regional Bicycle Enhancements Eugene 2024
Pacific Excavation
Bidder 4Bidder 1 Bidder 2 Bidder 3
Engineer Estimate AB Utility Contractors RiverBend Construction Inc Hybrid Construction LLC
Run Date: 12/18/2025 Page 1 of 1