About this file
This is a Project Manual and Request for Proposals (RFP) issued by Granite School District (GSD) for the construction of a Taylorsville High School Addition located at 5225 South Redwood Road, Taylorsville, Utah. The project encompasses construction of a new office wing, new classroom wing, new athletics wing, remodeling of existing classroom and office spaces, and miscellaneous site improvements. Work includes selective demolition, site improvements, fire protection and alarm system modifications, mechanical and electrical systems, communication and audio/visual systems, and installation of new Culinary Arts lab equipment. Only pre-qualified General Contractors from the prior prequalification solicitation (DB27-009-RFSQ) may respond. A mandatory pre-bid meeting and site tour is scheduled for October 27, 2026, at 1:00 PM Mountain Time at the GSD offices in Salt Lake City; attendance is required for contractor eligibility. Questions must be submitted by November 9, 2026, at 2:00 PM Mountain Time through the Utah Public Procurement Place/Bonfire (U3P) portal. Responses are due on or before November 19, 2026, at 2:00 PM Mountain Time via U3P. Construction is expected to commence in mid-December 2026, with Substantial Completion not later than July 9, 2029. Award recommendation will be presented at the November 24, 2026, board meeting, with final award issued after board approval.
Evaluation is scored on a 100-point basis comprising Project Cost (80 points maximum), Project Team (2 points), and Proposed Construction Schedule (18 points maximum). The lowest cost response receives 80 points, with each successively higher response receiving three points less. Respondents must submit a Bid Bond for total response amounts of $50,000 or greater and provide a list of all subcontractors with contract values of $50,000 or greater. Responses must include completed GSD Project RFP Forms, proposed project team information, and a detailed construction schedule in Gantt chart format identifying work sequences, summer break activities, long lead items, and milestone dates. The project schedule must prioritize completion of the office wing and identify work occurring during non-school periods to minimize disruption. A full-time Site Superintendent must be on-site whenever work is performed, and both the Site Superintendent and Project Manager must pass background checks for security badge issuance. The contractor is responsible for all labor, materials, equipment, waste disposal, hazardous materials compliance, and permits unless otherwise specified in supplementary conditions. GSD will abate any identified asbestos-containing materials prior to contractor work commencement.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2500 South State Street Salt Lake City, Utah 84115
October 20, 2026
Project Manual for Taylorsville High School
Addition
5225 South Redwood Road
Taylorsville, Utah 84123
Project Manual Contents Granite School District
October 20, 2026
Addition
Drawings
Asbestos Survey and Assessment (NESHAP) for Taylorsville High School
Asbestos Survey and Assessment (NESHAP) for Relocatable Units #1-16
Asbestos Report Review by Air Quality Consulting, LLC
2027/2027 and 2027/2028 GSD Calendars
Technical Specfications
Project Manual Contents
Project Manual Cover
GSD Schedule of Values - Page 2 of 2
GSD Payment Application - Page 1 of 2
GSD Change Order Form
Description
Dates of Construction and Damages
Project Directory - Contact Information
Security Access Card Application
Supplemental General Conditions
General Conditions of the Contract for Construction
Instructions to Bidders
Construction Materials Asbestos Statement
Tax Exempt Form
Contractor's Project Bid Form
Contractor's Agreement (Sample)
2.0 - PM Contents - Table of Contents 10/20/2026
P R O J E C T D I R E C T O R Y
Project: TAYLORSVILLE HIGH SCHOOL
ADDITION
Taylorsville High School 5225 South Redwood Road Taylorsville, Utah 84123
Owner: GRANITE SCHOOL DISTRICT
Architecture, Engineering & Construction 2500 South State Street Salt Lake City, Utah 84115
(385) 646-4142
Designer:
MHTN Architects, Inc.
280 South 400 West, Suite 250 Salt Lake City, Utah 84101
Joel Burkhart, AIA
(801) 326-3278 ajoel.burkhart@mhtn.com mailto:ajoel.burkhart@mhtn.com
I N S T R U C T I O N S T O RESPONDENTS
4.0 - Instructions to Bidders Taylorsville High School October 20, 2026 Addition
Instructions to Respondents Contracted Services for:
Taylorsville High School
Addition
1) Project Description. Granite School District (GSD) is soliciting responses from pre-qualified
General Contractors for the construction of a new office wing, new classroom wing, new athletics wing, remodeling of existing classroom and office spaces, and miscellaneous site improvements at Taylorsville High School, 5225 South Redwood Road, Taylorsville, Utah.
Work shall include, but is not limited to:
• Selective demolition of existing building, including but not limited to interior walls/partitions, ceilings, finishes, portions of mechanical systems, portions of electrical systems, and modifications to fire protection and fire alarm systems;
• Site Improvements;
• Construction of new office, classroom, and athletic wings with associated entries;
• Remodeling existing commons, office, and classroom spaces;
• Fire sprinkler system;
• Extension and modification of fire alarm system;
• Building mechanical systems;
• Building electrical systems;
• Communication, network, and audio/visual systems;
• Furnish and install new Culinary Arts lab equipment;
• Close out documents, warranties, and manuals.
2) General Contractor/Prime Contractor. Respondent has been prequalified as a potential
Prime Contractor on the Project and shall provide coordination and supervision for, and direction to, Subcontractors at any tier hired by and under the Prime Contractor.
3) Site Superintendent. Successful Respondent shall have a full-time Site Superintendent on-site any time work is being performed by Contractor’s own employees and/or by Subcontractors, for the duration of the Project. The Site Superintendent must coordinate all construction activities and Subcontractor access. It will be the Site Superintendent’s responsibility to follow GSD security procedures and to provide access for the Contractor’s employees and Subcontractors for all construction activities. Failure to provide a full-time Site Superintendent on-site shall result in issuance of an immediate “stop work” order from GSD until such time as the Superintendent returns to the site. Issuance of a “stop work” order by GSD shall not result in claim for delay or additional cost to GSD, nor shall it be grounds for extension of Contract days.
4) Background Check: The successful Contractor’s Site Superintendent and Project Manager will be required to pass a background check which will allow for issuance of a security badge and additional access.
5) Project Management Plan. GSD has several projects bidding or awarded for construction that will be under construction concurrently with this Project. A Project Management Plan must be submitted by the Contractor within 24 hours of receiving a request from the GSD Purchasing Agent if any of the following conditions apply to the Respondent:
a) The Contractor has been awarded a Contract for a District Project that will be under construction concurrently with this Project;
b) The Contractor has submitted a response for a District Project that will be under construction concurrently with this Project; and/or
c) The Contractor desires to submit responses on multiple projects currently bidding that will be under construction concurrently with this Project.
The Project Management Plan shall demonstrate how the Contractor intends to independently carry out this Project along with the other projects that have been, or could be, awarded to Contractor, and meet GSD’s published completion date(s). The Project Management Plan shall include the following information for each Project under consideration:
a) Proposed Full-Time Site Superintendent for the Project;
b) Other key project personnel and their role;
c) Preliminary schedule;
d) Other information to illustrate how the Contractor will manage the Work separately from the other Project(s).
6) Scope of Work. Contractor shall furnish all labor, material, and equipment to perform the work as indicated on the Drawings and Specifications, and in accordance with RFP Documents, including General and Supplemental Conditions of the Construction Contract, Addenda, and other documents as provided, for the performance of this Work.
7) Hazardous Materials. Asbestos-containing materials (ACM) or lead are present in the Facility and may be within the Project Work Area. ACM has been identified by GSD Environmental Safety Personnel or Consultants and documented in a Hazardous Materials Inspection Report or NESHAP. The NESHAP is provided with the RFP documents for reference. GSD will abate any hazardous materials in the Project Work Area prior to Contractor starting work. Contractor shall stop work immediately and notify GSD if any suspected hazardous materials are encountered in the Project Work Area during demolition or construction activities.
ACM is assumed to be present in roof flashings, mastics, or other materials in the roof assembly. Roofing contractor shall be certified to remove and properly dispose of ACM encountered in this Work. Roofing contractor shall make any required notifications as required by the Utah Department of Air Quality prior to commencing work.
Contractor shall not remove or disturb suspected hazardous materials unless otherwise directed by GSD Environmental Safety Personnel.
8) Waste Disposal. Contractor shall furnish all labor and equipment to remove, and properly dispose off-site, all construction waste, debris, and packing materials. Contractor shall furnish a dumpster for disposal of all materials and waste. Contractor shall not use GSD disposal container(s).
9) Bonds. The respondent is required to submit with their response a Bid Bond for a total response amount that is $50,000.00 or greater. Refer to instructions contained in the solicitation documents on the Utah Public Procurement Place/Bonfire (U3P). Failure to submit a Bid Bond will cause the response to be considered non-responsive.
10) List of Subcontractors. Respondent will submit, with their response, a list of all subcontractors who will be engaged in this Project, each with a contract value of $50,000.00 or greater.
11) Additional Information. Please see the General Conditions of the Contract for Construction and the Supplemental General Conditions for the construction dates, penalties, liquidated damages, and other information.
12) Response Submission and Evaluation. In addition to the Bid Bond and Subcontractors List, the RFP Submission shall be composed of the following elements: Project Cost, Project Team, and Proposed Construction Schedule. Each part of the submission listed below will be awarded points as indicated in their respective description, up to a total of 100 points. The Respondent receiving the highest total score will be awarded the Project. In case of a tie between the two highest scores, the response with the lowest cost solution will be used as the tie breaker.
a) Project Cost (80 points, maximum): The respondent shall fill out the GSD Project RFP
Form in its entirety. Failure to fill out the form completely will result in reduced score.
Responses submitted on other than the GSD Project RFP Form will be considered non-responsive and ineligible for consideration.
Evaluation Criteria: All responses will be evaluated on Base Response, including Allowances, and the addition of any alternates permitted to be selected by budget, at GSD’s discretion. The lowest total response will be awarded 80 points. Second lowest response will receive 77 points, third lowest will receive 74 points, with each successively higher response receiving three (3) points less than the next lower. In event of a tie at any response tier, the responses that are tied will be awarded equal points at that tier.
b) Project Team (2 points): Respondent identified their Project Teams in their Statement of
Qualifications. Respondent shall submit the proposed Project Team for the Taylorsville High School Addition with the response.
Evaluation Criteria:
1) Proposed Project Team provided with response. Two (2) points.
2) Failure to submit with response will result in a score of zero.
c) Proposed Construction Schedule (18 possible points): Project schedule/sequencing is critical to the successful completion of the Taylorsville High School Addition project. The Project is expected to start in mid-December 2026, with Substantial Completion not later than July 9, 2029. Respondent shall provide a proposed schedule, in Gantt chart format, outlining sequencing of the Work, work that will be done during the summer breaks, and work that needs to be performed in advance of other work in order to meet interim and final completion deadlines. Schedule shall also indicate specific long lead items that will affect the performance of the Work.
The Supplemental Conditions identify specific project milestones that must be met to permit relocation of staff and students, perform work without disruption of school activities, and meet schedule obligations. The schedule shall prioritize completion of the new office wing, without sacrificing progress on other areas of construction. The Substantial Completion date for the office wing in the Supplemental Conditions is to permit the relocation of all main office staff to allow the sequencing of the renovation of the existing main office space and other interior spaces. In addition to the Culinary Arts Lab, Commons Area, and Cafeteria work to be performed during summer breaks, the schedule shall identify work in other areas normally occupied by students that will need to be performed during periods when school is not in session. Refer to the attached district calendars for the 2026/2027 and 2027/2028 school years for additional information; the 2028/2029 calendar has not been approved. Schedule shall also include areas where remodels of existing vacant spaces may occur while school is in session.
Schedule shall include the work described by the alternates indicated in the Construction Documents. Respondent shall plan the work at the tennis courts to commence upon completion of the spring tennis season in 2027 or 2028 and shall execute the work continuously through completion to minimize impact on the following spring season.
Respondent may identify in the schedule any scope that may be accelerated to permit early turnover of new or renovated space.
Evaluation Criteria:
1) Schedule demonstrates minimum requirements for construction, meeting defined project milestones, and final completion date as described by Contract Documents and Supplemental Conditions. Eight (8) points.
2) Schedule documents path for early turnover of the office wing by seven (7) calendar days or more prior to milestone date in Supplemental Conditions. Contractor’s scheduled completion date will become the Substantial Completion date for this work on award. Add four (4) points.
3) Schedule documents path for early turnover of the classroom wing and counseling offices by seven (7) calendar days or more prior to milestone date in Supplemental Conditions. Contractor’s scheduled completion date will become the Substantial Completion date for this work on award. Add two (2) points.
4) Schedule demonstrates renovations that could occur in limited timeframes when students are not in attendance. Add two (2) points.
5) Schedule documents path to turnover completed project by seven (7) calendar days or more prior to Final Completion date in Supplemental Conditions. Contractor’s scheduled completion date will become the Substantial Completion date for this work on award. Add two (2) points.
6) Failure to submit schedule with response will result in a score of zero.
13) Solicitation Milestones.
a) Pre-bid Meeting: There will be a MANDATORY pre-bid meeting held on Tuesday, October 27, 2026, at 1:00 PM Mountain Time at the Granite School District Offices, 2500 South State Street, Salt Lake City, Utah. Respondents shall meet in the Architecture, Engineering, and Construction Conference Room, C-202, on the second floor of the two-story building. A tour of the Project Site will follow the pre-bid meeting. Contractors will be considered late and will not be allowed to attend the meeting if they arrive after the attendance roll has been signed by all in attendance and the doors to the room are closed.
Attendance is required for Contractor’s response to be accepted. Any prime Contractor that does not have an authorized representative attend the entire duration of the mandatory pre-bid meeting and site visit will be disqualified and ineligible to respond.
Subcontractors and suppliers are invited to attend this meeting but are not mandatory attendees.
b) Questions: Questions must be submitted by Monday, November 9, 2026, at 2:00 PM
Mountain Time. All questions must be submitted via the Utah Public Procurement Place/Bonfire (U3P). Questions submitted directly to Owner or Architect will not be answered until re-submitted through U3P. Contractor is responsible for reviewing the responses to any questions posted to U3P and acknowledges that all responses become an integral part of the response package and project requirements.
c) Response Due Date: Responses are due on or before Thursday, November 19, 2026, at 2:00 PM Mountain Time. All responses must be submitted via the Utah Public Procurement Place/Bonfire (U3P). All items indicated in the RFP Submission and Evaluation section of this document must be submitted through U3P for the response to be considered responsive.
Allow adequate time to upload all information to U3P. Incomplete responses will be considered non-responsive. Responses with conditions and/or exclusions submitted by the respondent, not addressed during the question-and-answer period or not otherwise requested on the GSD RFP Form, will be considered non-responsive.
G E N E R A L C O N D I T I O N S i
General Conditions of the Contract for Construction- Revision – March 3, 2026
GRANITE SCHOOL DISTRICT
GENERAL CONDITIONS OF THE
CONTRACT FOR CONSTRUCTION
Article Title Page
1 GENERAL PROVISIONS 1
2 GSD 7
3 CONTRACTOR 8
4 ADMINISTRATION OF THE CONTRACT 17
5 SUBCONTRACTORS 23
6 CONSTRUCTION BY GSD OR OTHER CONTRACTORS 25
7 MODIFICATIONS 26
8 TIME 29
9 PAYMENTS AND COMPLETION 32
10 PROTECTION OF PERSONS AND PROPERTY 38
11 INSURANCE AND BONDS 41
12 UNCOVERING, CORRECTION OF WORK, AND WARRANTY 44
13 MISCELLANEOUS PROVISIONS 47
14 TERMINATION OR SUSPENSION OF THE CONTRACT 51
ii iii
TABLE OF CONTENTS
ARTICLE 1. GENERAL PROVISIONS
1.1 Basic Definitions
1.2 Construction of Contract Documents, Venue
1.2.1 Applicable Laws
1.2.2 Capitalization
1.2.3 Interpretation
1.2.4 Venue
1.2.5 Intent and Hierarchy
1.2.6 Conflict Responsibility
1.2.7 Separability
1.2.8 Dividing Work and Contractor Representation
1.2.9 Construction of Words
1.3 Ownership and Use of Designer’s Drawings, Specifications and Other Documents ... 6
1.3.1 In General
ARTICLE 2: GSD
2.1 Information and Services Required of GSD
2.1.1 Project Manager
2.1.2 Specialists and Inspectors
2.1.3 Surveys and Legal Description
2.1.4 Prompt Information and Services
2.1.5 Copies of Drawings and Project Manuals for Construction
2.1.6 Other Duties
2.1.7 No Representations or Warranties
ARTICLE 3: CONTRACTOR
3.1 Review of Contract Documents and Field Conditions by Contractor
3.1.1 Reviewing Contract Documents, Information, Reporting Errors, Inconsistencies or Omissions
3.1.2 Field Conditions
3.1.3 Perform in Accordance with Documents and Submittals
3.1.4 Performance to Produce the Complete System and Intended Results
3.1.5 Prior to Construction
3.1.6 GSD’s Indemnification
3.2 Supervision and Construction Procedures
3.2.1 Supervision and Control
3.2.2 Responsibility
3.2.3 Not Relieved of Obligations
3.2.4 Inspections and Approvals
3.3 Labor and Materials
3.3.1 Payment by Contractor
3.3.2 Proposed Substitutions
3.3.3 Discipline and Competence
3.3.4 Local Preference
3.4 Warranty
3.4.1 In General
3.4.2 Exclusion
3.4.3 Furnish Evidence on Request
iv
3.4.4 Written Warranties
3.5 Allowances
3.5.1 In General
3.5.2 Usage of Allowance
3.5.3 Per GSD’s Specifications
3.6 Permits, Fees, Notices, Labor and Materials
3.6.1 Permits and Fees
3.6.2 Compliance with Public Authorities, Notices
3.6.3 Correlation of Contract Documents and Enactments
3.6.4 Failure to Give Notice
3.7 Contractor’s Superintendent
3.7.1 Project Superintendent
3.7.2 Assigned Superintendent
3.8 Contractor’s Construction Schedules
3.8.1 In General
3.8.2 Schedule of Submittals
3.8.3 Planning and Priority
3.8.4 Compliance with Schedules
3.9 Documents and Samples at the Site, Certifying “As-Built”
3.10 Submittals
3.10.1 Not Contract Documents
3.10.2 Promptness
3.10.3 Not Perform Until Designer Approves
3.10.4 Representation by Contractor
3.10.5 Contractor’s Liability
3.10.6 Direct Specific Attention to Revisions
3.10.7 Informational Submittals
3.10.8 Reliance on Professional Certification
3.11 Use of Site
3.11.1 In General
3.11.2 Access
3.12 Access to Work
3.13 Royalties and Patents
3.14 Reports
3.14.1 Progress Report
3.14.2 Equipment and Materials Report
3.14.3 Additional Reports
3.14.4 Procedures Manual
3.15 Storage and Defective Work
3.15.1 Storage and Inspection by Contractor
3.15.2 Rejection of Defective Work
3.15.3 Corrective Work
3.15.4 Owner’s Right to Cure
3.15.5 Acceptance of Defective Work
3.15.6 Storage of Materials
3.16 Turnover of Completed Work to GSD
3.16.1 Cleanliness
3.16.2 Miscellaneous
3.16.3 Final Responsibility
v
3.17 As-Builts or Record Drawings
3.18 Operation & Maintenance (O&M) Manuals
ARTICLE 4: ADMINISTRATION OF THE CONTRACT
4.1 Designer’s Administration of the Contract
4.1.1 In General
4.1.2 Site Visits
4.1.2 (1) In General
4.1.2 (2) Written Report
4.1.3 Communications Facilitating Contract Administration
4.1.4 Designer Issues Certificates of Payments
4.1.5 Designer may Reject Work, Order Inspection, Tests
4.1.6 Designer Review Contractor’s Submittals
4.1.6 (1) Submittal Review
4.1.6 (2) Time for Submittal Review
4.1.6 (3) Submittal Accuracy
4.1.6 (4) Contractor’s Obligation
4.1.6 (5) Contractor’s Liability
4.1.6 (6) Submittal Content
4.1.6 (7) Designer’s Indemnification
4.1.7 Designer’s On-Site Representatives
4.1.8 Designer’s Role in Preliminary Resolution Process
4.1.9 Criteria for Designer’s Determination for Decisions Under 4.1.8
4.1.10 Products Approvals
4.2 Inspections Substantial and Final
4.2.1 Substantial Completion Inspection
4.2.2 Final Completion Inspection
4.3 Procedure for Preliminary Resolution Effort (PRE)
4.3.1 Request for Preliminary Resolution Effort (PRE)
4.3.2 Time for Filing
4.3.3 Content Requirement of PRE
4.3.4 Time for Decision
4.3.5 Contractor to Continue Performance
4.3.6 If Decision Not Issued
4.3.7 Decision Final Unless Claim Submitted
4.4 Claims and Disputes
4.4.1 Claim Content Requirement
4.4.2 Time Limits and Content of Claims
4.4.3 Continuing Contract Performance
4.4.4 Waiver of Claims: Final Payment
4.5 Resolution of Claims and Disputes
4.5.1 Agreement of Claimant on Method and Person(s) Evaluating Claims
4.6 Payment of Claim
4.6.1 Payment Provisions
4.6.2 Term of Payment
4.6.3 Date of Final Determination
4.6.4 No Delay of Payment
4.6.5 Payment Conditions
4.6.6 Subcontractor Payment
4.6.7 Release of Claim
vi
4.7 Allocation of Cost of Claim Resolution
4.7.1 Cost of Filing Fee
4.7.2 Cost of Resolution
4.7.3 Cost Allocation
4.7.4 Cost of Representation
4.8 Alternative Procedures
4.9 Impact on Future Selections
4.10 GSD’s Right to have Issues, Disputes of Claims Considered
ARTICLE 5: SUBCONTRACTORS
5.1 Award of Subcontracts and Other Contracts for Portions of the Work
5.1.1 Approval Required
5.1.2 Requirements
5.1.3 Adjustments if Objections
5.1.4 Subsequent Changes
5.2 Sub-Contractual Relations
5.2.1 Comply with Contract Documents
5.2.2 Rights
5.2.3 Sub-Subcontractors
5.2.4 Document Copies
5.2.5 UCC Provisions
5.3 Contingent Assignment of Subcontracts
5.3.1 Conditions for Assignment to GSD
ARTICLE 6: CONSTRUCTION BY GSD OR BY SEPARATE CONTRACTORS
6.1 GSD’s Right to Perform Construction and to Award Separate Contracts
6.1.1 In General
6.1.2 Coordination and Revisions
6.2 Mutual Responsibility
6.2.1 Contract Coordination
6.2.2 Reporting Problems to GSD and Designer
6.2.3 Costs
6.2.4 Contractor Remedial Work
6.2.5 Claims Between Contractor and Separate Contractor
ARTICLE 7: MODIFICATIONS
7.1 Modifications
7.1.1 In General
7.1.2 By Whom Issued
7.1.3 Performance Requirements
7.1.4 Adjusting Unit Prices
7.2 Change Orders
7.2.1 Defined
7.2.2 Adjusting Price
7.2.3 Resolution of Price and Standards
7.2.4 Credits
7.2.5 Agreement; Change Order Issued
7.2.6 Disagreements; Claims Process Still Applies; Construction Change Directive May Be Issued
7.3 Construction Change Directives
7.3.1 Defined
7.3.2 Used When Lack of Agreement on Change Order
vii
7.3.3 Proceed with Work and Notify Designer about Adjustment Method
7.3.4 Is Change Order If Contractor Agrees
7.4 DSI (Designer’s Supplemental Instructions)
ARTICLE 8: TIME
8.1 Progress and Completion
8.1.1 Time of Essence
8.1.2 Notice to Proceed and Insurance
8.1.3 Complete within Contract Time
8.2 Schedule Preparation
8.2.1 Schedule Preparation
8.2.2 Initial Contract Time
8.2.3 Interim Completion Dates and Milestones
8.2.4 GSD’s Right to Take Exception
8.2.5 Initial Schedule Submission
8.2.6 Schedule of Submittals
8.3 Schedule Changes and Modifications
8.3.1 Contract Time Change Requires Modification
8.3.2 Updates
8.3.3 Resequencing and Duration Changes of Schedule
8.3.4 Time Extension Requests
8.4 Liquidated Damages
8.4.1 In General
8.4.2 Proceeding with Work Not Deemed Waiver
8.5 Consequential Damages
ARTICLE 9: PAYMENTS AND COMPLETION
9.1 Schedule of Values
9.1.1 Schedule of Values
9.1.2 Form
9.2 Applications for Payment
9.2.1 In General
9.2.2 Payment for Material and Equipment
9.2.3 Warranty of Title
9.2.4 Holdback by GSD
9.3 Certificates for Payment
9.3.1 Issued by Designer
9.3.2 Designer’s Representations
9.4 Decisions to Withhold Certification
9.4.1 When Withheld
9.4.2 Certification Issued When Reasons for Withholding Removed
9.4.3 Continue Work Even if Contractor Disputes Designer’s Determination ... 34
9.4.4 GSD Not in Breach
9.4.5 Application or Release of Withholding
9.5 Progress Payments
9.5.1 In General
9.5.2 Contractor and Subcontractor Responsibility
9.5.3 Information Furnished by Designer to Subcontractor
9.5.4 GSD and Designer Not Liable
9.5.5 Certificate, Payment or Use Not Acceptance of Improper Work
9.6 Substantial Completion
viii
9.6.1 Substantial Completion Inspection
9.6.2 Payment Upon Substantial Completion
9.6.3 Delivering Warranties and Guarantees
9.6.4 Review of Contract Price
9.7 Partial Occupancy or Use
9.7.1 In general
9.7.2 Inspection
9.7.3 Not Constitute Acceptance
9.8 Final Completion and Final Payment
9.8.1 Certificate for Payment
9.8.2 Final Inspection and Payment
9.8.3 Conditions for Final Payment and Retainage
9.8.4 Waiver by Accepting Final Payment
ARTICLE 10: PROTECTION OF PERSONS AND PROPERTY
10.1 Safety Precautions and Programs
10.1.1 Contractor Responsibility
10.1.2 Hazardous Materials
10.1.3 Hazardous Materials – Asbestos
10.1.4 Drug-Free Workplace
10.1.5 Standards of Conduct
10.2 Safety of Persons and Property
10.2.1 Contractor Responsibility
10.2.2 Safety Program, Precautions
10.2.3 Compliance with Laws
10.2.4 Erect and Maintain Safeguards
10.2.5 Utmost Care
10.2.6 Prompt Remedy
10.2.7 Safety Designee
10.2.8 Load Safety
10.2.9 Off-Site Responsibility
10.3 Emergencies
ARTICLE 11: INSURANCE AND BONDS
11.1 Liability Insurance
11.1.1 In General
11.1.2 Configurations
11.1.3 Contractor Liability
11.1.4 Certificate of Insurance, Notice Requirements, Additional Insured, Insurer Letter
11.1.5 Deductible Liability
11.1.6 Alternative Coverage
11.1.7 No Release From Liability
11.2 “Builder’s Risk” Property Insurance
11.2.1 In General
11.2.2 Inspections, Recommendations
11.2.3 Deductible
11.2.4 Adjusted With and Payable to Risk Manager as Trustee
11.2.5 Waiver
11.2.6 Special Hazards
11.3 Bonds
ix
11.3.1 Bid Bond
11.3.2 Bid Bond Submission
11.3.3 Performance and Payment Bond
ARTICLE 12: UNCOVERING, CORRECTION of WORK and WARRANTY PERIOD
12.1 Uncovering of Work
12.1.1 Uncover Uninspected Work
12.1.2 When Designer Requested Prior
12.1.3 When Designer Did Not Request Prior
12.2 Correction of Work and Warranty Period
12.2.1 Contractor Correct the Work
12.2.2 Warranty and Correction After Substantial Completion
12.2.3 Removal of Work
12.2.4 No Limit on Other Obligations
12.3 Acceptance of Nonconforming Work
12.4 General Representations and Covenants
12.4.1 Assigned Warranties
12.4.2 Survival of Warranties
12.4.3 No Warranty by GSD
ARTICLE 13: MISCELLANEOUS PROVISIONS
13.1 Designer’s Responsibilities
13.2 Successors and Assigns
13.3 Written Notice
13.3.1 Personal Delivery and Registered or Certified Mail
13.4 Rights and Remedies
13.4.1 Not Limit
13.4.2 No Waiver
13.5 Equal Opportunity; No Discrimination; No Sexual Harassment
13.6 Independent Contractor
13.7 Right to Inspect
13.8 No Waiver of Governmental Immunity
13.9 Owner Purchased and Owner Provided Materials
13.9.1 Owner Provided Materials
13.9.2 Storage of Owner Provided Materials
13.9.3 Contractor Receipt of Owner Provided Materials
13.9.4 Contractor Responsible Upon Receipt
13.9.5 Owner Provided Same As Contractor Provided
13.9.6 Non-Owner Provided Materials
13.10 Conflicting Laws
13.11 E-Verify
13.12 Excluded Parties List System
ARTICLE 14: TERMINATION OR SUSPENSION OF THE CONTRACT
14.1 Termination by Contractor
14.1.1 In General
14.1.2 Notice
14.2 Termination by GSD for Cause
14.2.1 In General
14.2.2 GSD’s Right to Carry Out the Work
14.2.3 Items Required to be Transferred or Delivered
14.2.4 Payment
x
14.2.5 GSD Protection if Lienable
14.2.6 Credits and Deficits
14.2.7 If Contractor Found Not in Default or Excusable
14.2.8 Rights and Remedies Not Exclusive
14.3 Delay or Interruption of Work by GSD for Convenience
14.3.1 By GSD in Writing
14.3.2 Adjustments
14.4 Termination for Convenience of GSD
14.4.1 In General
14.4.2 Contractor Obligations
14.4.3 Termination Claim
14.4.4 Agreed Upon Payment
14.4.5 Payment Not Agreed Upon
14.4.6 Deductions
14.4.7 Partial Termination
14.4.8 Partial Payments
14.4.9 Preserve and Make Available Records
14.5 GSD’s Right to Stop the Work
14.6 Indemnification
General Conditions of the Contract for Construction
GRANITE SCHOOL DISTRICT
ARTICLE 1. GENERAL PROVISIONS
1.1 BASIC DEFINITIONS
ADDENDA. "Addenda" means the written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the bidding documents or the Contract Documents.
AS-BUILT DRAWINGS. "As-Built Drawings” means the record set of drawings that memorialize and denote the Work as constructed. As-Built Drawings are produced, by the DESIGNER, from the redline plans submitted by the Contractor at the conclusion of the project. The redline plans identify actual component installation and dimensional routing of system components that are different from shown in the Contract Documents.
ASSISTANT SUPERINTENDENT. “Assistant Superintendent” means the current holder of the position of Assistant Superintendent, Support Services, for the Granite School District. Assistant Superintendent may include a designee selected by the Assistant Superintendent for a particular contract function referred to in the General Conditions.
BID. "Bid" means the offer or proposal of a bidder submitted on the prescribed form setting forth the prices for the Work to be performed.
BID DOCUMENTS. "Bid Documents" are defined as the Plans, Project Manual (GSD boilerplate and technical specifications), Addenda, and additional documentation generated by the bid process for the Work.
BONDS. "Bonds" mean the bid bond, performance and payment bonds, and other instruments of security.
CERTIFICATE OF OCCUPANCY. "Certificate of Occupancy” means the certificate that is issued for the permanent occupancy of the new facility, and is issued in compliance and oversight with the Utah State Board of Education (USBE).
CHANGE ORDER. "Change Order" means a written instrument prepared by the Designer and signed by Owner, Contractor and Designer, stating their agreement upon all of the following: (1) a change in the Work; (2) the amount of the adjustment in the Contract Price, if any; and, (3) the extent of the adjustment in the Contract Time, if any.
CLAIM. "Claim" means a demand or assertion by one of the parties seeking, as a matter of right, modification, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term "Claim" also includes other disputes and matters in question between Owner and Contractor arising out of, or relating to the Contract.
CONSTRUCTION CHANGE DIRECTIVE.
"Construction Change Directive" means a written order prepared by the Designer and signed by Owner, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Price or Contract Time, or both. Owner may, by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions, or other revisions; even if it may impact the Contract Price or Contract Time.
CONSTRUCTION PHASE. In a CM/GC Agreement, Construction Phase means the period commencing on the execution of a GMP Amendment, together with the (i) issuance by GSD of a Notice to Proceed with any on-site construction; and (ii) the issuance of a building permit by the applicable permitting authority.
CONTRACT. The Contract Documents form the Contract for Construction. The term "Contract" represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Designer and Contractor,
(2) between Owner and a Subcontractor or Sub - Subcontractor, or (3) between any persons or entities other than Owner and Contractor. The Designer shall, however, be entitled to performance and enforcement of obligations of Contractor under the Contract intended to facilitate performance of the Designer's duties.
CONTRACT DOCUMENTS. The term "Contract Documents" means the Agreement between Owner and Designer, Owner and Contractor (including, if applicable a CM/GC Agreement) (hereinafter referred to as the "Agreement"), the Conditions of the Contract (General, Supplementary, and other Conditions), the Drawings, Project Manual, Specifications, Addenda, and other documents listed in the Agreement, and Modifications issued after execution of the Agreement. The Contract Documents shall also include the Bid Documents, to the extent not in conflict with the other Contract Documents.
CONTRACT PRICE. The term "Contract Price" means the Contract Price as stated in Contractor's Agreement and, including authorized adjustments (modifications), is the total amount payable by Owner to Contractor for performance of the Work under the Contract Documents.
CONTRACT TIME. "Contract Time", unless otherwise provided in the Contract Documents, means the period of time, including authorized adjustments (modifications), allotted in the Contract Documents for Substantial Completion of the Work.
CONTRACTOR. “Contractor” is the person or entity identified as such in Contractor's Agreement and is referred to throughout the Contract Documents as if singular in number. The term "Contractor" means Contractor or Contractor's authorized representative. When separate contracts are awarded for different portions of the Project or other construction or operations on the site, the term "Contractor" in the Contract Documents in each case, shall mean Contractor who executes each separate Contractor’s Agreement.
CONTRACTOR’S AGREEMENT. “Contractor’s Agreement” means the agreement executed between the Contractor and GSD for the Work.
DAY. The term "day" as used in the Contract Documents shall mean “calendar day” unless otherwise specifically defined.
DEFECTIVE. "Defective" is an adjective which when modifying the word "Work" refers to Work that is unsatisfactory or faulty; or does not conform to the Contract Documents (including substitutions not properly authorized); or does not meet the requirements of any inspection, reference standard, test, or approval referred to in the Contract Documents; or has been damaged.
DESIGN STANDARDS. "Design Standards” means the current standards compiled by GSD, either as a Design Manual or conveyed by the GSD Representative, for use by the DESIGNER in the basis of design. The manual provides a listing of preferred materials and equipment for use in school construction. It is to be used as a guide in the basis of design and during construction of the Work.
DESIGNER. Designer means a person or entity that is lawfully licensed to practice architecture and/or engineering (including but not limited to interior design and landscape design), or other unlicensed design professional as designated by GSD, and is referred to throughout the Contract Documents as if singular in number. The term Designer is identified by a Contractual Agreement that includes subconsultants as part of the service. For projects where no Designer is hired by GSD, the references in the General Conditions to Designer shall be deemed to refer to GSD as practicable.
DESIGNER’S SUPPLEMENTAL INSTRUCTIONS
(DSI). “Designer’s Supplementary Instructions” or “DSI” means order minor changes in the Work not involving adjustment in the Contract Price or extension of the Contract Time and not inconsistent with the intent of the Contract Documents.
DRAWINGS. The "Drawings" are the graphic and pictorial portions of the Contract Documents prepared by the Designer or Owner, wherever located and whenever issued, showing the design, location, and dimensions of the Work; and, which generally include the drawings, elevations, sections, details, schedules and diagrams.
FLCC. “FLCC” is the Fixed Limit of Construction Cost and shall not be exceeded unless Owner gives approval to do so prior to a Change Order or Work being performed. The FLCC includes the GMP, as defined below.
GMP. “GMP” or Guaranteed Maximum Price” is the final price that the CM/GC agrees to accept as payment in full for performance of the Project and the CM/GC Agreement, and is provided by the CM/GC in response to the construction drawings and specifications produced by the Designer. The GMP includes all fees and percentages required by this RFP, including the CM/GC’s Management Fee, all General Conditions including labor and materials, cost of subcontracts, the CM/GC’s Contingency, and all Work as required in the RFP, the CM/GC Agreement, and the Project Definitions Documents. The GMP shall not exceed the FLCC.
GSD. “GSD” means Granite School District, as established pursuant to Utah law. Unless the context requires or is noted otherwise, GSD is the “Owner”.
GSD REPRESENTATIVE. “GSD Representative” means the person directly assigned by Granite School District to work with the Contractor as Project Manager pursuant to SECTION 2.1.1.
Unless the context requires otherwise, the “GSD Representative” is the “Owner’s Representative.”
INSPECTION. The word “inspection” or its derivatives shall mean a review of the Project, including but not limited to a visual review of the Work completed to date to ascertain if the Work is in accordance with the Contract Documents, including all applicable building codes and construction standards.
MODIFICATION. A "Modification" is (1) a Change Order, (2) a Construction Change Directive, or (3) a Designer’s Supplemental Instruction (DSI). The Contract may be amended or modified only by a
Modification, or by other written amendment executed by both Owner and Contractor expressly stating its intent to amend or modify the Contract.
NOTICE TO PROCEED. A "Notice to Proceed" is a document prepared by Owner and sent to Contractor, and by its terms authorizes Contractor to commence Work, or a portion of the Work, on the Project. It is deemed issued upon being sent by Owner to the Contractor's specified address within the Bid.
OWNER. "Owner" or pronoun used in place thereof, means GSD (Granite School District.)
PARTIAL UTILIZATION. "Partial Utilization" means placing a portion of the Work in service for the purpose or use for which it is intended (or a related purpose) before reaching Substantial Completion for all the Work. Such partial utilization does not constitute “Substantial Completion.”
PRECONSTRUCTION PHASE. “Preconstruction Phase” means the period commencing upon full execution of a CM/GC Agreement by the Parties and ending upon the commencement of the Construction Phase. This phase includes, but is not limited to, design meetings, estimating, cost reconciliation meetings and cost control, schedule development, and drawing and constructability reviews, and all other requirements detailed in the applicable Article of the CM/GC Agreement.
PROJECT. The "Project" means the total construction, of which the Work performed under the Contract Documents may be the whole or a part, and which may include construction by Owner or by separate contractors.
PROJECT MANUAL (for Construction). The "Project Manual" is the written volume assembled for the Work and may include the bidding requirements, instructions for bidders, General Conditions and Supplementary General Conditions of the Contract, Specifications, and sample forms.
PROPOSAL REQUEST OR PR. A “Proposal Request” or “PR” is a submission to the
Contractor for the purposes of seeking a proposal in order to resolve an issue as part of the Change Order or Contract Modification process.
PROPOSED CHANGE ORDER OR PCO. A
“Proposed Change Order” or “PCO” is an informal request by the Contractor filed with the GSD Representative, in an effort to commence the Contract Modification Process. It shall not be considered a “Claim.” The PCO may be related to any potential, or actual delay, disruption, unforeseen condition or materials, or any other matter for which the Contractor intends to seek additional compensation or time.
REQUEST FOR INFORMATION OR RFI. A
“Request for Information” or “RFI” is any request filed by the Contractor with the Designer seeking information, direction or clarification related to the Contract Documents, plans or specifications.
SAMPLES. "Samples" mean physical examples which illustrate materials, equipment, or workmanship, and establish standards by which the Work will be judged.
SHOP DRAWINGS. "Shop Drawings" means drawings, diagrams, schedules, and other data specially prepared for the Work by Contractor or a Subcontractor, Sub - Subcontractor, manufacturer, supplier, or distributor of any tier to illustrate some portion of the Work.
SPECIFICATIONS. The "Specifications" are that portion of the Contract Documents consisting of the written requirements for materials, equipment, construction systems, standards, workmanship for the Work, and performance of related systems and services.
SUBCONTRACTOR. "Subcontractor" means the person or entity that has a direct contract with Contractor to perform a portion of the Work at the site. The term "Subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or authorized representative of the Subcontractor. The term "Subcontractor" does not include a separate contractor or subcontractors retained by Owner.
SUBMITTAL. “Submittal” means shop drawings, diagrams, engineering and product data, and/or other information furnished by Contractor to illustrate conformance to the Specifications for the Work or a portion of the Work.
SUBSTANTIAL COMPLETION. "Substantial Completion" is the date certified by GSD in accordance with SECTION 9.6 SUBSTANTIAL COMPLETION and means the date the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that Owner can occupy and utilize the Work for its intended use and any lack of completion or performance does not unreasonably interfere with the ability of Owner to so occupy and utilize the Work. A final Certificate of Occupancy, where applicable, shall be required to be issued in order for the Work to be considered Substantially Complete unless the failure or unreasonable delay of such issuance is for reasons not attributable to Contractor. Notwithstanding the issuance of a Certificate of Occupancy, an unreasonably high number of “punch list” items (items not in conformance with Contract Document requirements), shall result in a determination that Substantial Completion has not occurred. The determination that the Work is Substantially Complete shall be in the sole discretion of GSD.
SUB-SUBCONTRACTOR. A "Sub-Subcontractor" means the person or entity that has a direct or indirect contract with a Subcontractor to perform a portion of the Work at the site. The term "Sub - Subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Sub -Subcontractor or an authorized representative of the Sub -Subcontractor. The term "Sub - Subcontractor" does not include the sub -subcontractors of a subcontractor for a separate contractor retained by Owner. Unless the context requires otherwise, the term Sub-Subcontractor includes all material suppliers and vendors who directly or indirectly support the Work.
SUPPLEMENTARY GENERAL CONDITIONS.
"Supplementary General Conditions" means the part of the Contract Documents which amends or supplements these General Conditions.
WORK. The term "Work" means the Preconstruction Services and the Construction Phase Work required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment, and services provided or to be provided by Contractor to fulfill Contractor's obligations. The Work may constitute the whole or a part of the Project.
1.2 CONSTRUCTION OF CONTRACT
DOCUMENTS, VENUE
1.2.1 APPLICABLE LAWS. The applicable
laws and regulations of the State of Utah, as well as any applicable local laws and regulations not superseded by State law, shall govern the execution of the Work embodied in the Contract Documents as well as the interpretation of the Contract Documents.
1.2.2 CAPITALIZATION. Terms capitalized
in these General Conditions include those which are (1) specifically defined, (2) the title of numbered articles and identified references to Paragraphs, Subparagraphs and Clauses in the document, or (3) the titles of documents published by the American Institute of Architects.
1.2.3 INTERPRETATION. In the interest of
brevity the Contract Documents frequently omit modifying words such as "all" and "any" and articles such as "the" and "an", but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement.
1.2.4 VENUE. In case of any dispute which
may arise under the Contract Documents, the place of venue shall be in the County of Salt Lake, Utah, unless otherwise agreed to by all the parties.
1.2.5 INTENT AND HIERARCHY. The
Contract Documents should be read as a whole, and wherever possible, the provisions should be construed in order that all provisions are operable.
The intent of the Contract Documents is to include all items necessary and incidental for the proper execution and completion of the Work by Contractor. The Contract Documents are complementary, and what is required by one Document or provisions thereof shall be as binding as if required by all the Documents or provisions thereof. Performance by Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from the Contract Documents as being necessary to produce the intended results. In case of an irreconcilable conflict between provisions within a Contract Document or between Contract Documents, the following priorities shall govern as listed below:
(1) A particular Modification shall govern over all
Contract Document provisions or Modifications issued prior to said particular Modification.
(2) A particular Addendum shall govern over all other Contract Document provisions issued prior to said particular Addendum. Subsequent Addenda shall govern over prior Addenda.
(3) The Supplementary General Conditions shall govern over these General Conditions.
(4) These General Conditions shall govern over all other Contract Documents except for the Supplementary General Conditions, Addenda, and Modifications.
(5) The Drawings and Specifications shall not govern over any of the immediately preceding documents.
(6) In case of a conflict or ambiguity within the same level of hierarchy described above, Owner shall have the right to select the most stringent requirement.
1.2.6 CONFLICT RESPONSIBILITY.
Contractor shall comply with the provisions of
SUBPARAGRAPH 3.1 REVIEW OF CONTRACT
DOCUMENTS AND FIELD CONDITIONS BY
CONTRACTOR set forth below regarding review of the Contract Documents and field conditions by Contractor.
1.2.7 SEPARABILITY. The invalidity of any
part, paragraph, subparagraph, phrase, provision, or aspect of the Contract Documents shall not impair or affect in any manner the validity, enforceability or effect of the remainder of the
1.2.8 DIVIDING WORK AND CONTRACTOR
REPRESENTATION. Organization of the specifications into division, sections and articles, and arrangement of Drawings, shall not control Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade. Contractor represents that the Subcontractors and Sub- Subcontractors engaged, or to be engaged for the Work, are and will be familiar with the requirements for performance by them of their obligations.
1.2.9 CONSTRUCTION OF WORDS. Unless
otherwise stated in the Contract Documents, words which have well known technical or construction industry meanings shall be construed as having such recognized meanings. Unless the context requires otherwise, all other technical words shall be construed in accordance with the meaning normally established by the particular, applicable profession or industry. All other words, unless the context requires otherwise, shall be construed with an ordinary, plain meaning.
1.3 OWNERSHIP AND USE OF DESIGNER’S
DRAWINGS, SPECIFICATIONS AND OTHER
DOCUMENTS.
1.3.1 IN GENERAL. All Drawings, Specifications and other documents prepared by the Designer are, and shall remain, the property of either Owner or the Designer, as provided in the Designer’s Agreement, and such owner shall retain all common law, statutory and other reserved rights with respect thereto. Said documents were prepared and are intended for use as an integrated set for the Project which is the subject of this Contract. They shall not be modified or used on any other project without the prior written consent of Owner and Designer. Any such non-permissive use or modification by Contractor, Contractor's Subcontractors at any tier, or anyone for whose acts Contractor is liable, shall be at Contractor's sole risk. Contractor shall hold harmless and indemnify Owner and Designer, and their separate contractors and consultants, from and against any and all claims, actions, suits, costs, damages, loss, expenses and/or attorney fees arising out of such non-permissive use or modification by Contractor.
Contractor, Subcontractors and Sub- Subcontractors are granted a limited license to use and reproduce applicable portions of the Drawings, Specifications, and other documents prepared by the Designer appropriate to and solely for use in the execution of their Work under the Contract Documents. All copies made under this license shall bear the statutory copyright notice, if any, shown on the Drawings, Specifications, and other documents prepared by the Designer. Submittals or distributions necessary to meet official regulatory requirements or for other purposes relating to completion of the Project are not to be construed as a publication in derogation of any copyright or other reserved rights.
ARTICLE 2. GSD
2.1 INFORMATION AND SERVICES REQUIRED
OF GSD
2.1.1 PROJECT MANAGER. GSD shall
designate a Project Representative authorized to act on GSD's behalf with respect to the Project. GSD or such authorized representative shall render decisions within a reasonable time pertaining to documents submitted by the Designer and/or Contractor in order to avoid a compensable delay in the orderly and sequential progress of the Project.
2.1.2 SPECIALISTS AND INSPECTORS.
GSD will assign an inspector or specialist to note deviations from, or necessary adjustments to, the Contract Documents or to report deficiencies or defects in the Work. The inspector or specialist's activities in no way relieve the Designer or Contractor of the responsibilities set forth in the
2.1.3 SURVEYS AND LEGAL DESCRIPTION.
GSD shall furnish surveys describing known physical characteristics,…