This amendment modifies a solicitation to construct Vehicle Storage Building No. 4 at the Bismarck O&M Service Center in North Dakota for the Department of Energy Western Area Power Administration. The amendment revises several project drawings, incorporates a change narrative and geotechnical engineering report, and maintains the bid receipt deadline of September 9, 2020 at 2:00 PM local time. Relevant drawings are replaced, and additional documents addressing design changes and site conditions are included to provide necessary updates prior to bid submission for constructing the vehicle storage building.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
89503420BWA000020
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
UGP-HURON
HURON SD 57350-2474
200 4th STREET SW
US DOE/WESTERN AREA POWER
WAPA (UGP)
UGP-HURON
HURON SD 57350-2474
200 4th STREET SW
US DOE/WESTERN AREA POWER
WAPA (UGP)
20WC136420-99608/31/20200003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/29/2020
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment is to incorporate changes to drawings, and add the Geological report to the solicitation.
See Page 2 for details.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jonathan D. Dittmer
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
08/31/2020
3DEPARTMENT OF ENERGY
WESTERN AREA POWER ADMINISTRATION
Bismarck O&M Service Center Solicitation No. 89503420BWA000020 Vehicle Storage Building No. 4 Amendment No. 0003, page 2 of 2 North Dakota
The purpose of this amendment is to incorporate necessary changes in the solicitation prior to receipt of bids as follows:
1. The date and time set for receipt of bids remains September 09, 2020, 2:00 PM local time at place of bid opening.
2. In Section C, Description/Specifications, Project Drawings, the following drawings are deleted and the attached revised drawings are substituted therefore:
Insert Attached
Remove Drawings Revised Drawings
16. BSM C-500 – Civil Site Details I 16. BSM C-500 – Civil Site Details I, Rev. 1
17. BSM C-501 – Civil Site Details II 17. BSM C-501 – Civil Site Details II, Rev. 1
34. BSM S001 – General Notes Sheet I 34. BSM S001 – General Notes Sheet I, Rev. 1
3. Incorporate:
• Change Narrative – Burns McDonnell
• Geotechnical Engineering Report – Dated August 25, 2020