This document is a project specification for the construction of Bismarck O&M Service Center Vehicle Storage Building No. 4 in North Dakota. The project consists of constructing a six-bay, approximately 80' x 109' pre-engineered steel vehicle storage building. Key requirements include providing six drive-through vehicle bays with overhead doors, space along the east and west walls for future rack storage, four personnel doors with entry pads and ramps, an underfloor hydronic boiler heating system, water and storm drain systems, lighting and electrical systems, a fire protection system, floor trench drains with an oil-water separator, exterior water bibs, concrete aprons, grading and drainage, and relocating fiber-optic lines. The bidding schedule includes items for civil site preparation, concrete work, and providing the pre-engineered building, mechanical and plumbing systems, fire protection, and electrical work. Construction must commence by April 1, 2021 and be completed per the schedule. The Western Area Power Administration is the contracting agency.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BISMARCK O&M SERVICE CENTER
VEHICLE STORAGE BLDG. NO. 4
Solicitation No. 89503420BWA000020 Spec. No. 20WC136420-996
SECTION C
DESCRIPTION/SPECIFICATIONS
NORTH DAKOTA
SECTION C
DESCRIPTIONS/SPECIFICATIONS
BISMARCK O&M SERVICE CENTER
VEHICLE STORAGE BLDG. NO. 4
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
B. DESCRIPTION OF WORK:
1. Six (6) drive-thru vehicle bays
2. Additional space along both east and west walls for rack storage systems
3. Four (4) personnel doors, (2) on east side, and (2) on west side
4. Equipment to be stored in building
5. Under floor hydronic (electric) boiler heating system
6. Water and storm drain systems
7. Lighting and electrical systems i
8. Fire protection system
9. Floor trench drain system with water oil separator
10. Water “bibs” for hosing off vehicles and floor
11. 30 feet-long x 109 feet-wide concrete aprons
12. Grading and drainage requirements
13. Relocation of fiber-optic communication lines and installation of pull box
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work”
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK:
2. SUBMITTAL APPROVAL TIME:
3. CONSTRUCTION SCHEDULE RESTRICTIONS:
4. TYPICAL FOUNDATIONS FOR BUILDING FOUNDATION:
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME:
F. MATERIAL:
1. Furnish all material for completing the work
G. RIGHTS-OF-WAY:
1. GENERAL:
H. GEOLOGIC INVESTIGATIONS:
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
J. WATER FOR CONSTRUCTION PURPOSES:
K. EXPLOSIVES AND BLASTING:
L. BURIED UTILITIES:
M. EMPLOYEE REQUIREMENTS:
N. ELECTRICAL MINIMUM APPROACH DISTANCES:
O. SUBMITTALS AND CORRESPONDENCE:
1. GENERAL:
2. TRANSMITTAL:
3. PHYSICAL SAMPLE SUBMITTALS:
4. SUBMITTAL RESPONSE:
5. APPROVAL TIME:
6. PROJECT PROTOCOL:
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Civil Site Preparation”
DIVISION 3 – CONCRETE
A. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “ “Concrete”
DIVISION 11 – SERVICE BUILDING
A. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule items “Pre-engineered Building”, “Mechanical and Plumbing”, “Fire Protection”, and “Electrical”
SECTION C
DESCRIPTIONS/SPECIFICATIONS
DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
Construct and complete Bismarck O & M Service Center, Vehicle Storage Bldg. No. 4, in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; Western Area Power Administration’s (WAPA) Construction Standards, including Standard 1 – General Requirements (September 2016), Standard 2 – Sitework (September 2016), Standard 3 – Concrete (September 2016), Standard 4 – Substation Metalwork and Transmission Line Lattice Structures (September 2016), Standard 5 – Transmission Line Steel Pole Structures (September 2016), Standard 6 – Light Duty Steel Pole Structures (September 2016), Standard 7 – Wood Poles (September 2016), Standard 8 – Glued Laminated Structures (September 2016), Standard 9 – Substation – Electrical (September 2016), Standard 10 – Transmission Line – Electrical (September 2016), Standard 12 – Painting (September 2016), Standard 13 – Environmental Quality Protection (September 2016), Standard 14 – Communication Facilities (September 2016), Standard 15 – Drawings (September 2016); Standard Drawings; and these Project Specifications and Drawings.
If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.
WAPA’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.
WAPA Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.
B. DESCRIPTION OF WORK:
The project consists of a 6 Bay, approximately 80’ x 109’ pre-engineered steel vehicle storage building with the following attributes:
1. Six (6) drive-thru vehicle bays. Five (5) bays will have 14’ wide x 14’ high overhead doors; one
(1) bay will have 12’ wide x 14’ high overhead doors.
2. Additional space along both east and west walls for rack storage systems (not in this contract);
note that this will be in areas not utilized for under floor heating boiler system, electrical equipment, water bibs, and eye wash stations (not part of this contract).
3. Four (4) personnel doors, (2) on east side, and (2) on west side of the building. Each door to be provided with entry pads and ramps.
4. Equipment to be stored in building includes semi-tractors with trailers, man-lifts, cranes, wire reel trailers, etc.
5. Under floor hydronic (electric) boiler heating system; no cooling, radiant heat in building is an optional requirement.
6. Water and storm drain systems including connections to main utilities as shown on drawings.
https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx
7. Lighting and electrical systems including transformer and connections to main power source as shown on drawings.
8. Fire protection system as shown on drawings.
9. Floor trench drain system with water oil separator.
10. Water “bibs” for hosing off vehicles and floor.
11. 30 feet-long x 109 feet-wide concrete aprons on north and south sides of building.
12. Grading and drainage requirements as shown on drawings.
13. Relocation of fiber-optic communication lines and installation of pull box as shown on drawings.
The summary of “Bidding Schedule Items” are more fully described in the following divisions in this specification and in the Construction Standards listed in Division 1, Section A above.
The work is located in Burleigh County, Bismarck, North Dakota.
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
a. Performing mobilization and preparatory work in accordance with Sections H and M of the contract clauses.
b. Preparing and submitting a Construction Schedule and furnishing a Safety and Health
Program.
c. Complying with DOE O 442.2, Differing Professional Opinions for Technical Issues Involving Environment Safety and Health.
d. Complying with applicable Environmental Standards.
e. Providing jobsite office trailer and the items listed below. Prior to any jobsite work, the Contractor shall provide the office trailer for the exclusive use of WAPA.
(1) Relocation: If the Contractor changes the location of his office during the term of the contract, then the Contractor shall also move the mobile office trailer provided for WAPA, simultaneously with the transportation of his own unit.
(a) Installation: Install anchors and tie-downs for the trailer complying with local, State and Federal regulations. The office trailer shall be grounded. Entry points to the trailer shall be provided with stairways complying with OSHA (29
CFR 1926.1052).
(b) Office Space Requirements:
1) Size and Arrangement: At least 250-square feet (minimum) consisting of two separate rooms (one office and one larger workroom).
2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.
3) Lighting and Electrical: Adequate lighting and 120 V electrical outlets.
4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power, and heating and cooling energy.
5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained.
(2) Emergency Equipment: Provide and maintain the following emergency equipment:
(a) First aid kit that meets or exceeds ANSI Z308.1 (latest version) Class B, Type
IV. Mount to the wall inside the workroom.
(b) Dry chemical fire extinguishers, classified 4-A:60-B:C, one to be located inside each entrance to the trailer.
(3) Window Coverings: Provide adjustable mini-blinds.
(4) Office Furniture: Provide good quality, fully functional, office furniture as follows:
Quantity Description
5 Folding Office Chairs.
1 Office desk (30” x 60” minimum).
2 Office tables (30” x 60” minimum).
1 Five-drawer file cabinet.
1 Bookcase (30” x 13” x 48”).
12 “Plan Hold” binders No. 1CB-24 (including one plan rack).
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK: See FAR 52.211- 10 in Section F of the solicitation/contract.
2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 30-calendar days for review of drawings or data submitted for approval.
3. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply:
a. The Contractor shall not work more than 12 hours per day and not more than 60-hours in one continuous period without approval from the COR.
b. Work at the site shall not commence until April 1, 2021.
4. TYPICAL FOUNDATIONS FOR BUILDING FOUNDATION: Typical foundations are shown on drawings. Regarding foundations noted as “design not firm”: The engineer-of-record will design these foundations after receipt and final approval of pre-engineered steel building manufacturer’s final shop drawings and calculations from the Contractor.
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 10 calendar days after date of Notice to Proceed.
F. MATERIAL:
1. Furnish all material for completing the work.
G. RIGHTS-OF-WAY:
1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way and within Government property lines or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired by the Contractor shall have prior COR approval. During the contract period, WAPA reserves the right to use Contractor-obtained access.
H. GEOLOGIC INVESTIGATIONS:
A Geotechnical Engineering Report is pending. When available, it shall be incorporated into these Project Specifications as a requirement for design and construction of this project.
Existing geologic information is not available for this project. The Contractor shall determine the nature of the material to be excavated, the difficulties of making and maintaining required excavations, and doing other work affected by geology and ground water elevations at the work site.
I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
Electric power up to a maximum of approximately 25-kVA for construction purposes will be available without cost. Source of supply is located on the exterior walls of the warehouse building No. 1.
Power made available by WAPA will be delivered as single-phase, 60 Hz, AC, at approximately 120V, temporary single phase 240V service can also be made available. Coordinate with the COR for establishing electric power service.
Until permanent power is available, provide temporary power to the building to serve all building loads including heating & lighting. Provide temporary heating prior to beginning finish work, sufficient to keep the interior of the building at a minimum of 40 degrees Fahrenheit for 24-hours a day, until permanent heating is available.
The Contractor may furnish power for his operations by other means at no additional cost to WAPA.
Provide necessary transmission lines, distribution circuits, transformers, and other electrical equipment for distributing the power to the places of use. At contract completion, remove temporary electrical equipment and distribution lines.
J. WATER FOR CONSTRUCTION PURPOSES:
Furnish water for construction purposes. Make arrangements for obtaining the water and provide for conveying the water to the points of use.
K. EXPLOSIVES AND BLASTING:
Explosives shall not be used.
L. BURIED UTILITIES:
Prior to excavation, examine the area and determine the location of buried utilities. Utilities shall be identified with a marker denoting the type of service.
M. EMPLOYEE REQUIREMENTS:
In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted from wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing, hearing protection worn as the hazard exists, or for communication purposes while on a WAPA jobsite.
N. ELECTRICAL MINIMUM APPROACH DISTANCES:
In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances established by OSHA 1926.958(b), “Materials, Handling, and Storage”. The less stringent equipment clearance distances established by OSHA 1926.960, “Working On or Near Exposed Energized Parts”, Table V-5 and Table V-6, may only be used after the Contractor has completed and submitted WAPA’s Electrical Clearance Variance form and has received the signed form in return from the COR.
O. SUBMITTALS AND CORRESPONDENCE:
1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements:
a. Submittals shall be in standard PDF, Microsoft Word (.doc/.docx), Microsoft Excel
(.xls/.xlsx), or Electronic CAD (.dwg) (AutoCAD 2010 or 2014) formats. All submittals in .dwg format shall also be submitted in .pdf format.
b. All submittals shall include the WAPA Contract number, Specification number, WAPA project title, Bidding Schedule Contract Line Item Number (CLIN) and applicable division number.
c. Multiple CLIN’s on a single submittal are not permitted.
d. A cover transmittal letter in Microsoft Word or PDF format shall be included with each email submittal.
2. TRANSMITTAL: The Contractor shall transmit all submittals to the Construction Office.
Email: UGP-CS-B5600@WAPA.GOV
3. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e. brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlining the physical sample submittal prior to sending the sample (including tracking data when applicable) and shall deliver physical specimens to:
Western Area Power Administration Construction Office 200 4th Street SW Huron, SD 57350 mailto:UGP-CS-B5600@WAPA.GOV
4. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Accepted” or “Not Accepted” status with comments as appropriate in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph to the email address where the submittals originated.
5. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecutions, and Completion of Work” paragraph.
6. PROJECT PROTOCOL:
a. Submittals – Electronic Correspondence:
SUBJECT LINE IN EMAIL -- SUBMITTAL FORMAT
CLIN + Submittal Name – Applicable Division Number or Drawing Number – Project Title – Specification Number – Contract Number Example: 0011 Concrete Mix Design – 3.A.1 – Bismarck O&M Service Center, Vehicle Storage Building No. 4, ND – 20WC136420-996 – 89503420CWA0000XX
b. Payment Requests:
SUBJECT LINE IN EMAIL -- PAYMENT REQUEST FORMAT
Invoice Number – Project Title – Specification Number – Contract Number Example: Invoice 01 – Bismarck O&M Service Center, Vehicle Storage Building No. 4, ND –
20WC136420-996 – 89503420CWA0000XX
c. Certified Payrolls – Prime and Sub-Contractors:
SUBJECT LINE IN EMAIL -- CERTIFIED PAYROLL FORMAT
Certified Payroll (CP) – Contractor Name – Week Ending (WE) – Project Title – Specification Number – Contract Number Example: CP – Bob’s Asphalt Repair – WE 08/13/16 & 08/20/16 – Bismarck O&M Service Center, Vehicle Storage Building No. 4, ND – 20WC136420-996 – 89503420CWA0000XX
d. Request for Information:
SUBJECT LINE IN EMAIL -- REQUEST FOR INFORMATION (RFI) FORMAT
RFI Number – Subject – Project Title – Specification Number – Contract Number Example: RFI 003 – Labeling Info – Bismarck O&M Service Center, Vehicle Storage Building No.
4, ND – 20WC136420-996 – 89503420CWA0000XX
DIVISION 2 – SITEWORK
A. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Civil Site Preparation” includes providing and meeting all the sitework requirements and specifications listed on the Drawings and in Appendix A.
DIVISION 3 – CONCRETE
1. Bidding Schedule item “ “Concrete” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendix A.
DIVISION 11 – SERVICE BUILDING
1. Bidding Schedule items “Pre-engineered Building”, “Mechanical and Plumbing”, “Fire Protection”, and “Electrical” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendix A.
Message from the Administrator
At Western Area Power Administration (WAPA), we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to WAPA. In performing work for WAPA, all contractors must make the right decisions to ensure that the work environment is as safe as possible.
Our safety program is based on four points:
Safety procedures or common sense must be applied by each
Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.
Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.
Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.
Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.
By integrating these principles into every task we take, together we can ensure WAPA is a safe place to work.
Mark A. Gabriel Administrator and CEO
| DIVISION 1 – GENERAL REQUIREMENTS |
| A. CONTRACT REQUIREMENT: |
| B. DESCRIPTION OF WORK: |
| 1. Six (6) drive-thru vehicle bays. Five (5) bays will have 14’ wide x 14’ high overhead doors; one (1) bay will have 12’ wide x 14’ high overhead doors. |
| 2. Additional space along both east and west walls for rack storage systems (not in this contract); note that this will be in areas not utilized for under floor heating boiler system, electrical equipment, water bibs, and eye wash stations (not part o... |
| 3. Four (4) personnel doors, (2) on east side, and (2) on west side of the building. Each door to be provided with entry pads and ramps. |
| 4. Equipment to be stored in building includes semi-tractors with trailers, man-lifts, cranes, wire reel trailers, etc. |
| 5. Under floor hydronic (electric) boiler heating system; no cooling, radiant heat in building is an optional requirement. |
| 6. Water and storm drain systems including connections to main utilities as shown on drawings. |
| 7. Lighting and electrical systems including transformer and connections to main power source as shown on drawings. |
| 8. Fire protection system as shown on drawings. |
| 9. Floor trench drain system with water oil separator. |
| 10. Water “bibs” for hosing off vehicles and floor. |
| 11. 30 feet-long x 109 feet-wide concrete aprons on north and south sides of building. |
| 12. Grading and drainage requirements as shown on drawings. |
| 13. Relocation of fiber-optic communication lines and installation of pull box as shown on drawings. |
| C. DESCRIPTION OF BIDDING SCHEDULE ITEM: |
| 1. Bidding Schedule item “Mobilization and preparatory work” includes the following: |
| 1) Size and Arrangement: At least 250-square feet (minimum) consisting of two separate rooms (one office and one larger workroom). |
| 2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling. |
| 3) Lighting and Electrical: Adequate lighting and 120 V electrical outlets. |
| 4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power, and heating and cooling energy. |
| 5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained. |
| D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK: |
| 1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK: See FAR 52.211-10 in Section F of the solicitation/contract. |
| 2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, WAPA will require 30-calendar days for review of drawings or data submitted for approval. |
| 3. CONSTRUCTION SCHEDULE RESTRICTIONS: The following Construction Schedule restrictions shall apply: |
| 4. TYPICAL FOUNDATIONS FOR BUILDING FOUNDATION: Typical foundations are shown on drawings. Regarding foundations noted as “design not firm”: The engineer-of-record will design these foundations after receipt and final approval of pre-engineered ste... |
| E. CONSTRUCTION SCHEDULE: |
| 1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer (CO) within 10 calendar days after date of Notice to Proceed. |
| F. MATERIAL: |
| 1. Furnish all material for completing the work. |
| G. RIGHTS-OF-WAY: |
| 1. GENERAL: Orient construction methods and equipment to utilize Government-furnished rights-of-way and within Government property lines or obtain additional temporary access without additional cost to WAPA. Any additional temporary access acquired ... |
| H. GEOLOGIC INVESTIGATIONS: |
| I. ELECTRIC POWER FOR CONSTRUCTION PURPOSES: |
| J. WATER FOR CONSTRUCTION PURPOSES: |
| K. EXPLOSIVES AND BLASTING: |
| L. BURIED UTILITIES: |
| M. EMPLOYEE REQUIREMENTS: |
| In addition to the requirements listed in WAPA Construction Standard 1.4.3 all employees are restricted from wearing a headset, headphone, or other listening device, other than a hearing aid or instrument for the improvement of defective human hearing... |
| N. ELECTRICAL MINIMUM APPROACH DISTANCES: |
| In addition to the requirements listed in WAPA Construction Standard 1.4.9 equipment other than cranes and derricks, conductive objects, or personnel, shall not be brought closer to energized facilities than the electrical minimum approach distances e... |
| O. SUBMITTALS AND CORRESPONDENCE: |
| 1. GENERAL: The Contractor shall furnish submittals via email as specified in the Construction Standards and this Project Specification to the email address listed under the Transmittal section below and with the following requirements: |
| 2. TRANSMITTAL: The Contractor shall transmit all submittals to the Construction Office. |
| 3. PHYSICAL SAMPLE SUBMITTALS: When physical specimens or digital media are required to be submitted for approval, (i.e. brick samples, roofing material samples, carpeting, CDs, DVDs, etc.) the Contractor shall provide a digital cover letter outlinin... |
| 4. SUBMITTAL RESPONSE: WAPA will respond to submittals electronically with an “Accepted” or “Not Accepted” status with comments as appropriate in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph to the email address w... |
| 5. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecutions, and Completion of Work” paragraph. |
| 6. PROJECT PROTOCOL: |
| DIVISION 2 – SITEWORK |
| A. DESCRIPTION OF BIDDING SCHEDULE ITEM: |
| 1. Bidding Schedule item “Civil Site Preparation” includes providing and meeting all the sitework requirements and specifications listed on the Drawings and in Appendix A. |
| DIVISION 3 – CONCRETE |
| A. DESCRIPTION OF BIDDING SCHEDULE ITEM: |
| 1. Bidding Schedule item “ “Concrete” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendix A. |
| DIVISION 11 – SERVICE BUILDING |
| A. DESCRIPTION OF BIDDING SCHEDULE ITEM: |
| 1. Bidding Schedule items “Pre-engineered Building”, “Mechanical and Plumbing”, “Fire Protection”, and “Electrical” includes providing and meeting all the requirements and specifications listed on the Drawings and in Appendix A. |