Sol_140P5126R0010.pdf
PDF 620 KB Posted
- Attached to
- HVAC Upgrades, Mammoth Cave National Park
- Solicitation number
- 140P5126R0010
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment__0006___Question_and_Answers_0003.pdf | ||
| Sol_140P5126R0010_Amd_0003.pdf | ||
| Sol_140P5126R0010_Amd_0002.pdf | ||
| Sol_140P5126R0010_Amd_0001.pdf | ||
| Attachment_0003__Revised_Price_Schedule_0001.xlsx | XLSX spreadsheet | |
| Attachment_0001__Statement_of_Work.pdf | ||
| Attachment_0002__DOL_WG.pdf | ||
| Attachment_0003__Price_Schedule.docx | DOCX document | |
| Attachment_0005__Bid_Bond.pdf | ||
| Attachment_0004__Past_Performance.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140P5126R0010
NPS SER EAST MABO
100 Alabama St., SW 1924 Building Atlanta GA 30303-8701
Department of Interior, National Park Service Contracting Operations (ConOps) East 100 Alabama Street SW Atlanta, Georgia 30303
0044045559
PSE
Yanick Bard 4045075743
06/03/2026
07/06/2026
10 240
FAR 52.211-10
PROJECT TITLE: HVAC Upgrades
SITE LOCATION: Mammoth Cave National Park, Mammoth Cave, KY
Type of Contract: Firm Fixed Price Contract
The Work consists of the following: To replace aging HVAC systems that have reached or exceeded their expected service life with modern, energy-efficient systems that improve reliability, indoor air quality, and temperature control.
The Contractor shall furnish all labor, materials, tools, equipment, supervision, and transportation necessary to remove and replace eighteen (18) HVAC systems located in eleven (11) buildings at Mammoth
Cave National Park.
Continued...
1 52
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
NPS SER EAST MABO
100 Alabama St., SW 1924 Building Atlanta GA 30303-8701
PSE
Yanick Bard
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
This is a Request for Proposal for a Small
Business in accordance with Federal Acquisition
Regulation (FAR) Part 19. The Government reserves the right to award without negotiations.
In accordance with FAR Part 28, performance and payment bonds are required at 100% of the contract price and must be submitted within ten
(10) business days of receiving the award.
A certificate of insurance is required, and coverage must be at a minimum of: $100,000 per person; $500,000 per occurrence; and $1,000,000 per property and must be submitted within ten
(10) calendar days of receipt of the award.
Davis Bacon prevailing wages for Edmonson
County, KY will apply for this requirement. See attachment 0002 or KY20260099 on WDOL.gov.
Delivery Location Code: 0011283058
NPS, Mammoth Cave NP
P O Box 7
NPS Warehouse, 61 Maintenance Rd
Mammoth Cave KY 42259 US
Period of Performance: 07/15/2026 to
07/14/2028
00010 MACA - Cyclic HVAC Upgrades. The Contractor shall install all HVAC equipment in accordance with the Statement of Work.
BASE: 15 July 2026 to 14 June 2027.
Product/Service Code: N041
Product/Service Description: INSTALLATION OF
EQUIPMENT- REFRIGERATION, AIR CONDITIONING,
AND
AIR CIRCULATING EQUIPMENT
Delivery: 07/14/2027
Period of Performance: 07/15/2026 to
07/14/2027
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
00020 HVAC Upgrades MACA
Option 1: 15 July 2027 to 14 July 2028
(Option Line Item)
Anticipated Exercise Date 07/15/2027
Product/Service Code: 4530
Product/Service Description: FUEL BURNING
EQUIPMENT UNITS
Delivery: 07/14/2028
Period of Performance: 07/15/2027 to
07/14/2028
Contracting Officer and Point of Contact information for this requirement is:
Bureau: National Park Service, Contracting
Operations (ConOps) East
Contracting Officer: Yanick Bard
Email: yanick_bard@ios.doi.gov
TABLE OF CONTENTS
PART I - The Schedule
SECTION A - Solicitation/contract form…………..……………………………………………………... 6 SECTION B - Bid schedule……………………………………………………….…………………..…... 7 SECTION C - Specifications/Drawings…………………………………………………………………… 8 SECTION D - Packaging and marking………..………………………………………………………….. 9 ................Postage and Markings………..………………………………………………………………… 9 SECTION E - Inspection and acceptance………………………………………………………………… 10 .............. Inspection of Construction……..……………………………………………………………….. 10 SECTION F - Deliveries or performance………..……………………………………………………….. 11 ...............Commencement, Prosecution, and Completion of Work………………………………………. 11 ...............Suspension of Work…………………………………………………………………………….. 11 SECTION G - Contract administration data……………………………………………………………… 12 ...............Contract Administration………………………………………………………………………… 12 ...............Authorities & Delegations (subcontracting & Site Administration)…………………… SECTION H - Special Contract Requirements………………………………………………………..….. 14 ...............Safety…………………………………..……………………………………………………….. 14 ...............Progress Meetings………………………………………………………………………………. 14 ...............Operation of Facility during Construction……………………………………………………… 14 ...............Contractor Employees…………………………………………………………………………… 15
PART II - Contract Clause
SECTION I - Contract clause……………………………………………………………………………… 19 ...............Clauses by Reference…………………………………………………………………………….. 19 ...............Release of Claims - Department of Interior……………………………………………… ...............Liability Insurance - Department of Interior……………………………………………………... 22
PART III - List of Documents, Exhibits, and Other Attachments
SECTION J - List of Attachments…..……………………………………………………………………… .25 ............... Statement of Work………………………………………………………………………………. ..25 ............... Wage Determination …………………………………………………………………………….. 25 ............... Price Schedule …………………………………………………………………………………… 25 ............... Past Performance Questionnaire …………………………………………………………………. 25 ............... Bid Bond, SF-24 …………………………………………………………………………………. 25 ............... Construction Contraction Administration ……………………………………………………..…. 25
PART IV – Representations and Instructions
SECTION K - Representations, certifications, and other statements of offerors………………………….. 26 SECTION L - Instructions, conditions and notices to offerors……………………………………………. 41 ............... Site Visit……… ………………………………………………………………………………… 46 ............... Instruction to Offerors for Proposal Submission..……………………………………………..… 47 SECTION M - Evaluation factors for award……………………………………………………………….. 50
Section A - Solicitation/contract form
PROJECT TITLE: HVAC Upgrades
SITE LOCATION: NPS Mammoth Cave National Park, Mammoth Cave, KY
NOTICE TO PROSPECTIVE OFFEROR’S
SUBMISSION OF DOCUMENTS: Your offer must include the following Sections and Forms:
SF-1442, SOLICITATION, OFFER AND AWARD. PLEASE NOTE: The SF-1442 must be signed, and dated, and Blocks 14 through 20c must be completed.
SF-1442, ITEM 17, Offeror is cautioned to review acceptance time stated in Item 13d before completing this item. Proposals offering less than specified time will cause proposal to be rejected.
SECTION B, Price Schedule (“ALL” Pricing shall be submitted with attachment 0003)
SECTION K, REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS
OFFERS SHALL BE SUBMITTED VIA EMAIL ONLY TO: yanick_bard@ios.doi.gov
This project’s magnitude is between $250,000.00 and $500,000.00.
PERFORMANCE/PAYMENT BONDS - Successful offeror will be required to furnish Performance and Payment bonds on Standard Forms 25 and 25A based on total contract amounts in the following ranges: 100% performance bond, 100% payment bond. Offerors understand that the Government will inspect, accept, and possess the completed work and release the bonding when the work is completed and accepted under FAR 28.203-5.
There will be a site visit scheduled on June 8, 2026 at 10:00 A.M, CDT and June 10, 2026 at 10:00 A.M CDT.
See site visit instructions in Section L.14 of this document.
All questions regarding this solicitation must be submitted in writing to the Contracting Officer. Questions must be submitted by June 19, 2026 at 1:00 P.M. CDT. Questions submitted after this time may NOT be considered.
Proposals are due on July 6, 2026 at 5:00 P.M. ET.
Section B – Bid schedule
The Contractor should provide all labor, parts, tools, equipment, supervision, and all incidentals as necessary for the HVAC Upgrades at the NPS Mammoth Cave National Park, Mammoth Cave, KY.
NOTE: PROVIDE A DETAILED COST BREAKOUT OF YOUR LUMP SUM PRICE PROPOSAL WITH
ATTACHMENT 0003 SHALL INCLUDE ALL COSTS ASSOCIATED WITH YOUR PROPOSAL.
Section C – Specifications/Drawings
C.1 The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified). To perform to the Statement of Work, included as Attachment 0001 in accordance with the Contract Documents:
Attachment 0001, Statement of Work
Section D – Packaging and marking
D.1 Payment of Postage and Fees
The Contractor shall pay all postage and fees related to submitting documents to the Contracting Officer (CO) or the Contracting Officer’s Representative (COR).
D.2 Marking
All documents submitted to the Contracting Officer or Contracting Officer’s Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.
Section E – Inspection and acceptance
E.1 Notice Listing Contract Clause Incorporated By Reference
The following contract clauses pertinent to this section are hereby incorporated by reference (by Citation Number, Title and Date) in accordance with the clauses at FAR 52.252-2 CLAUSES INCORPORTATED BY REFERENCE in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to the full text of a clause.
Number Title Date
52.246-12 Inspection of Construction Aug 1996 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements Aug 1996
Section F – Deliveries or performance
F.1 Notice Listing Contract Clause Incorporated By Reference
The following contract clauses pertinent to this section are hereby incorporated by reference (by Citation Number, Title and Date) in accordance with the clauses at FAR 52.252-2 CLAUSES INCORPORTATED BY REFERENCE in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to the full text of a clause.
Number Title Date 52.236-15 Schedules for Construction Contracts Apr 1984 52.242-14 Suspension of Work Apr 1984
Section G – Contract administration data
G.1 Contracting Officer’s Representative(s) for this contract will be:
To Be Determined at time of Award
G.2 Contract Officer responsible for administering this contract:
Yanick Bard, Contracting Officer National Park Service 100 S.W. Alabama Street, Atlanta, Georgia 30303 Email: yanick_bard@ios.doi.gov
G.3 Technical Direction
The performance of the work required in this contract shall be subject to the COR’s technical direction and surveillance. As used in this contract, “technical direction” is direction to the Contractor that requires pursuit of certain lines of inquiry, filing in detail or otherwise serving to accomplish the contract specifications. The technical direction, to be valid:
(a) Must be issued in writing consistent with the general scope of the work stated in the contract;
(b) May not constitute a new assignment of work changes to the expressed terms, conditions, or specifications incorporated into this contract; it shall not constitute a reason to extend the contract delivery schedule.
Nothing contained in this part authorizes the Contractor to incur costs that exceeds the contract price or other limitation of funds stated in the contract due to extra work performed in response to informal directions, suggestions, or instructions (oral or written) given by the CO’s representatives, unless before commencing the work, the Contractor: 1) directly notifies the CO; 2) requests a formal contract modification; and 3) receives written authorization to proceed from the CO.
G.4 Correspondence
Any correspondence initiated by the Contractor shall include the Contract Number and shall be addressed to the CO (original and one copy) at the address provided in the clause entitled “Contractor administration”.
G.5 Job Site Administration
The COR will be available at the site to inspect the work as it progresses. The COR is not authorized to make technical decisions or give technical directions; the Contractor or the Contractor’s Superintendent must contact the COR regarding such decisions and directions.
The Contractor shall have a competent superintendent (the Contractor’s Superintendent) who is (i) deemed acceptable to the Government; (ii) authorized to act on the Contractor’s behalf; and (iii) to be present on the job site at all times when contract work is being performed.
G.6 1452.201-70 Authorities and Delegations (Sep 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority.
The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
Section H – Special Contract Requirements
H.1 Safety
The Contractor is responsible for establishing and maintaining compliance with all applicable laws, regulations, rules, and standards, including without limitation, those regulations, rules, and standards, promulgated for the administration and enforcement of the following laws: the Occupational Safety and Health Act (OSHA) or Federally approved State equivalent(s); the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) as amended by Superfund Amendments and Reauthorization Act (SARA); Emergency Planning and Community Right-to-Know Act (EPCRA); Clean Air Act (CAA); Clean Water Act (CWA) and Toxic Substances Control Act (TSCA); and Solid Waste Disposal Act (SWDA), as amended by Resource Conservation and Recovery Act (RCRA).
H.2 Progress Meetings
(a) The Contractor shall be available to meet with the CO or his or her representative at the job site during construction to discuss work progress.
(b) Meetings will be scheduled by the CO with timely notification to the Contractor.
At the progress meetings, the Contractor shall give the CO progress reports on the project. If the work is behind schedule, the Contractor must (i) discuss the work and any causes of work delay(s); (ii) present a plan to bring the work back into conformance with the schedule; or, if necessary (iii) to propose a revised work schedule.
H.3 Operation of Facility During Construction
Construction activities must not interrupt the facility’s function and daily operations during construction.
Contractor must coordinate with the COR for any temporary measures. All temporary measures employed shall be at the Contractor’s expense and shall be removed upon completion of the contract.
H.4 Work Hours
Normal work hours are from 7:30 a.m. through 4:00 p.m., Monday through Friday. Contractor will not be permitted to work at the job site on Saturday, Sunday, or legal holidays unless the CO authorizes otherwise.
H.5 Use of Premises
(a) Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened, or operated on Government land or lands administered by the Government, written permission shall be obtained through the CO. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for Contractor. The permission, if granted, will be without charge to Contractor.
(b) Unless provided otherwise, the Contractor shall provide and maintain sanitation facilities for the workforce at the site. Solid waste shall be disposed of under applicable federal, state, and local regulations.
H.6 Maximum Work Week
The maximum workweek that will be approved is 40 hours. The Contractor’s proposed hours of work are to include daily starting and stopping times.
H.7 Disposal
The contractor shall follow all standards in the specification and drawings.
H.8 Contractor Employees
a) The Contractor shall furnish sufficient personnel to perform, supervise and manage all work.
b) The Contractor employees shall conduct themselves in a proper, efficient, courteous, and business-like manner.
c) The Contractor shall remove from the site any individual whose continued employment the CO deems to be contrary to public interest or inconsistent with the National Park Service’s policies.
H.9 Permits
Contractor shall, without additional expense to the government, obtain all appointments, licenses, and permits required to perform work under this contract. Contractor will provide evidence of all permits and licenses to the CO before the work begins and will always display them on the job site.
H.10 Quality of Work
Workmanship shall be of the highest quality and the best trade practices. Contractor shall conform to all requirements of the state and county code, ANSI A 10.6, and applicable codes of the National Fires Protection Association. All replacement materials shall conform to the manufacturer specifications and standards. Substitute items shall be equal to or better that the original material and must be approved by the Government.
H.11 Completion of Work
The time stated for completion of the project includes all materiel procurement, payroll records, corrections of all discrepancies (Punch List Items), and final clean up on premises as stated in the clause “Commencement, Prosecution and Completion of Work”, FAR 52.211-10 (APR 1984) Section F.
H.12 Material Approval Submittals
All submittals shall be transmitted using National Park Service form CM-SPE form that will be made available to the Contractor. No action will be taken on a submittal item unless accompanied by the CM- SPE transmittal form.
H.13 Archeological Findings
Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found in the construction area, are the property of and will be removed and only by the Government.
Should Contractor’s operations uncover, or his or her employees find any archeological remains, Contractor shall suspend operations at the discovery site; notify CO immediately of the findings; and continue operation in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for the contractor, he or she will be compensated by an equitable adjustment under the Contract’s General Provision.
H.14 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements – Internet Payment Platform (IPP) (Feb 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury’s Invoice Processing Platform System (IPP). “Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
The contractor must submit to the CO and the COR the payroll for the general contractor and any applicable sub-contractors and an updated schedule.
The contractor must us the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instruction via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippcustomersupport@fiscal.treasury.gov or phone
(866) 973-3131.
If the Contractor is unable to follow the requirement to use IPP for submitting invoices for payment the Contractor must submit a waiver request in writing to the Contracting Office with its proposal or offer.
(End of Local Clause)
H.15 Contractor Performance Assessment Reporting System (Dec 2015)
1) FAR 42.1502 directs all federal agencies to collect past performance information on contracts. The Department of the Interior has implemented the Contractor Performance Assessment Reporting System (CPARS) to follow this regulation. One or more past performance evaluations will be conducted to record your contract performance as FAR 42.15 requires.
2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report.
3) We request that you give the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm’s past performance evaluation(s) for the contract no later than 30 calendar days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.
4) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at http://www.cpars.csd.disa.mil/. The CPARS User Manual, registration for Online Training for Contractor Representatives, and a practice application may be found at this site.
5) Within 60 days after a performance period ends, the CO will complete an interim or final past performance evaluation, and the report will be accessible at http://www.cpars.csd.disa.mil/.
a) Contractor Representatives may then provide comments in response to the evaluation or return the evaluation without comment.
b) Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official’s narrative and should provide your views on the causes and ramifications of the assessed performance.
c) In addition to the ratings and supporting narratives, blocks 1 – 17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions.
d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating “No comment” in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government.
e) If you do not sign and submit the CPARS in 30 days, it will automatically be returned to the Government and will be annotated: “The report was received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment.”
f) Your response is due within 30 calendar days after receiving the CPARS.
6) The following guidelines apply concerning your use of the past performance evaluation:
a) Protect the evaluation as “source selection information.” After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and submit the form through CPARS, contact the Contracting Officer for instructions.
b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the Contracting Officer no later than 7 calendar days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30- day review period.
8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
Section I – Contract clauses
I.1 52.252-2 Clause Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://www.acquisition.gov.
(End of clause)
Clause Title Date 1452.203-70 Restriction on Endorsements Jul 1996 1452.215-70 Examination of Records by the Department of the Interior Apr 1984 1452.224-1 Privacy Act Notification (July 1996) Deviation Jul 1996 1452.236-70 Prohibition Against Use of Lead-based Paint Jul 1996 52.202-1 Definitions Jun 2020 52.203-3 Gratuities Apr 1984 52.203-5 Covenant Against Contingent Fees May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government June 2020 52.203-7 Anti-Kickback Procedures Jun 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for
Illegal or Improper Activity May 2014
52.203-12 Limitation on Payments to Influence Certain Federal Transactions
Jun 2020
52.203-16 Preventing Personal Conflicts of Interest Jun 2020 52.203-17 Contractor Employee Whistleblower Rights and
Requirement to Inform Employees of Whistleblower Rights
Nov 2023
52.203-19 Prohibition on Requiring Certain Internal Confidentiality or statements
Jan 2017
52.204-9 Personal Identify Verification of Contractor Personnel Jan 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards Nov 2025
52.204-13 System for Award Management Maintenance Nov 2025 52.204-19 Incorporation by Reference of Representations and
Certifications Dec 2014
52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment
Jan 2025
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
Oct 2018
52.209-12 Certification Regarding Tax Matters Oct 2025
52.215-2 Audit and Records–Negotiation Jun 2020 52.215-8 Order of Precedence–Uniform Contract Format Oct 1997 52.215-10 Price Reduction for Defective Cost or Pricing Data Aug 2011 52.215-12 Subcontractor Certified Cost or Pricing Data Jun 2020 52.216-24 Limitation of Government Liability Apr 1984
52.219-6 Notice of Total Small Business Set-Aside Nov 2020 52.219-8 Utilization of Small Business Concerns Jan 2025 52.219-14 Limitation on Subcontracting Oct 2022 52.219-28 Post-Award Small Business Program Representation Jan 2025 52.222-1 Notice to the Government of Labor Disputes Feb 1997 52.222-3 Convict Labor Jun 2003 52.222-4 Contract Work Hours and Safety Standards -Overtime
Compensation May 2018
52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work
May 2014
52.222-6 Construction Wage Rate Requirements Aug 2018 52.222-7 Withholding of Funds May 2014 52.222-8 Payrolls and Basic Records Jul 2021 52.222-9 Apprentices and Trainees Jul 2005 52.222-10 Compliance with Copeland Act Requirements Feb 1988 52.222-11 Subcontracts (Labor Standards) May 2014 52.222-12 Contract Termination-Debarment May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and
Related Regulations May 2014
52.222-14 Disputes Concerning Labor Standards Feb 1988 52.222-15 Certification of Eligibility May 2014 52.222-21 Prohibition of Segregated Facilities Apr 2015 52.222-23 Notice of Requirement for Affirmative Action to Ensure
Equal Employment Opportunity for Construction (Feb 1999) Feb 1999
52.222-26 Equal Opportunity Sept 2016 52.222-27 Affirmative Action Compliance Requirements for Construction Apr 2015 52.222-35 Equal Opportunity for Veterans Jun 2020
52.222-36 Equal Opportunity for Workers with Disabilities Jun 2020 52.222-37 Employment Reports on Veterans Jun 2020
52.222-50 Combating Trafficking in Persons Oct 2025
52.222-54 Employment Eligibility Verification Jan 2025
52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026
Jan 2022
52.222-62 Paid Sick Leave Under Executive Order 13706 Jan 2022 52.223-3 Hazardous Material Identification and Material Safety Data Feb 2021 52.223-5 Pollution Prevention and Right-to-Know Information May 2024 52.223-23 Sustainable Products and Service
(Deviation Feb 2025) May 2024
52.225-9 Buy American – Construction Materials Oct 2022
52.225-10 Notice of Buy American Act Requirement – Construction Materials
May 2014
52.225-11 Buy American-Construction Materials under Trade Agreements
Nov 2023
52.225-13 Restrictions on Certain Foreign Purchases Feb 2021 52.226-1 Utilization of Indian Organizations and Indian Owned
Economic Enterprises Jun 2000 52.226-7 Drug-Free Workplace May 2024 52.227-4 Patent Indemnity-Construction Contracts Dec 2007 52.227-17 Rights in Data Special Works Dec 2007 52.228-2 Additional Bond Security Oct 1997 52.228-5 Insurance - Work on a Government Installation Jan 1997 52.228-11 Individual Surety – Pledge of Assets Feb 2021 52.228-12 Prospective Subcontractor Requests for Bonds Dec 2022
52.228-14 Irrevocable Letter of Credit Nov 2014 52.228-15 Performance and Payment Bonds - Construction Jun 2020 52.229-3 Federal, State, and Local Taxes Feb 2013 52.229-11
Tax on Certain Foreign Procurements - Notice and Representation
Jun 2020
52.229-12
Tax on Certain Foreign Procurements Feb 2021
52.232-5 Payments under Fixed-Price Construction Contracts May 2014
52.232-16 Progress Payments Nov 2021 52.232-17 Interest May 2014 52.232-23 Assignment of Claims May 2014 52.232-27 Prompt Payment for Construction Contracts Jan 2017 52.232-33 Payment by Electronic Funds Transfer-System for Award
Management Oct 2018
52.232-39 Unenforceability of Unauthorized Obligations Jun 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors Mar 2023
52-233-1 Disputes May 2014 52.233-3 Protest after Award Aug 1996 52.233-3 Protest after Award – Alternate 1 Jun 1985 52.233-4 Applicable Law for Breach of Contract Claim Oct 2004 52.236-2 Differing Site Conditions Apr 1984 52.236-3 Site Investigation and Conditions Affecting the Work Apr 1984 52.236-5 Material and Workmanship Apr 1984 52.236-6 Superintendence by the Contractor Apr 1984 52.236-7 Permits and Responsibilities Nov 1991 52.236-8 Other Contracts Apr 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements Apr 1984
52.236-10 Operations and Storage Areas Apr 1984 52.236-11 Use and Possession Prior to Completion Apr 1984 52.236-12 Cleaning Up Apr 1984 52.236-13 Accident Prevention Nov 1991 52.236-14 Availability and Use of Utility Services Apr 1984 52.236-17 Layout of Work Apr 1984 52.236-21 Specifications and Drawings for Construction Feb 1997 52.236-28 Preparation of Proposals Construction Oct 1997 52.243-4 Changes Jun 2007 52.243-5 Changes and Changed Conditions Apr 1984
52.244-6 Subcontracts for Commercial Products and Commercial Services
Oct 2025
52.246-21 Warranty of Construction Mar 1994 52.249-2 Termination for Convenience of the Government (Fixed-
Price) Apr 2012
52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements)
Apr 2012
52.249-10 Default (Fixed-Price Construction) Apr 1984 52.253-1 Computer Generated Forms Jan 1991
I.2 1452.204-70 Release of Claims – Department of the Interior (Jul 1996)
After completion of work and before final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of Clause)
I.3 1452.228-70 Liability Insurance (Jul 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
1. Worker’s compensation and employer’s liability: $500,000
2. General Liability: $100,000 each person and $500,000 each occurrence
3. Property Damage: $1,000,000
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days before the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number, and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate before beginning the work.
(c) The Contractor shall name the United States, National Park Service, as the insured party(ties) on the liability insurance policy.
L.4 1452.236-71 Additive or Deductive Items - Department of the Interior (Jul 1996)
So that the Government may obtain the most desirable features of work within the limit of its funds available at time of bid evaluation, award may be made to the bidder having the lowest total of the base bid and a combination of additive and deductive items. All bids shall be evaluated on the basis of the same additive and deductive bid items using the order of priority of the items listed in the schedule.
(End of provision)
L.5 52.216-1 Type of Contract (Nov 2025)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
L.6 52.216-23 Execution and Commencement of Work (Apr 1984)
Execution and Commencement of Work (Apr 1984)
The Contractor shall indicate acceptance of this letter contract by signing three copies of the contract and returning them to the Contracting Officer not later than To Be Determined. Upon acceptance by both parties, the Contractor shall proceed with performance of the work, including purchase of necessary materials.
I.7 52.216-25 Contract Definitization (Nov 2025)
(a) A firm fixed price definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a fixed price proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.
(b) The schedule for definitizing this contract is [insert target date for definitization of the contract and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of make-or-buy and subcontracting plans and certified cost or pricing data]:
(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) of this section, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.
(1) After the Contracting Officer’s determination of price or fee, the contract shall be governed by-
(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);
(ii) All clauses required by law as of the date of the Contracting Officer’s determination; and
(iii) Any other clauses, terms, and conditions mutually agreed upon.
(2) To the extent consistent with paragraph (c)(1) of this section, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.
(End of clause)
Alternate I (Apr 1984). In letter contracts awarded on the basis of price competition, add the following paragraph (d) to the basic clause:
(d) The definitive contract resulting from this letter contract will include a negotiated Firm Fixed Price [insert "price ceiling" or "firm fixed price"] in no event to exceed_____ [insert the proposed price upon which the award was based].
L.8 52.252-4 Alterations in Contract (Apr 1984)
Portions of this contract are altered as follows: None
L..9 52.252-6 Authorization Deviations in Clauses (Nov 2020)
As prescribed in 52.107(f), insert the following clause in solicitations and contracts that include any FAR or supplemental clause with an authorized deviation. Whenever any FAR or supplemental clause is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the clause when it is used without deviation, include regulation name for any supplemental clause, except that the contracting officer shall insert "(DEVIATION)" after the date of the clause.
AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 14) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
Section J – List of attachments
Attachment Number
Attachment Title Date Number of Pages
Document Version
0001 Statement of Work 7/1/2026 10 BASE
0002 Wage Determination 5/18/2026 5 BASE
0003 Price Schedule 6/1/2026 1 BASE
0004 Past Performance Questionnaire 6/1/2026 3 BASE
0005 Bid Bond, SF-24 6/1/2026 1 BASE
0006 Construction Contraction Administration 6/1/2026 1 BASE
Section K – Representation, certifications, and other statements of offerors
Contractors must have a completed and updated Online Representation and Certifications Application on SAM.gov.
K.1 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its Proposal or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its proposal or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://www.acquisition.gov/far
Clause Title Date
52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions Sept 2024
52.223-1 Biobased Product Certification Nov 2025
52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (Nov 2025)
K.2 52.204-20 Predecessor of Offeror (Aug 2020)
(a) Definitions. As used in this provision–
Commercial and Government Entity (CAGE) code means–
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity by unique location; or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
Predecessor means an entity that is replaced by a successor and includes any predecessors of the predecessor.
Successor means an entity that has replaced a predecessor by acquiring the assets and carrying out the affairs of the predecessor under a new name (often through acquisition or merger). The term "successor" does not include new offices/divisions of the same company or a company that only changes its name. The extent of the responsibility of the successor for the liabilities of the predecessor may vary, depending on State law and specific circumstances.
(b) The Offeror represents that it □ is or □ is not a successor to a predecessor that held a Federal contract or grant within the last three years.
(c) If the Offeror has indicated "is" in paragraph (b) of this provision, enter the following information for all predecessors that held a Federal contract or grant within the last three years (if more than one predecessor, list in reverse chronological order):
Predecessor CAGE code:____________________ (or mark "Unknown"). Predecessor legal name:_________________________________________ .(Do not use a "doing business as" name).
K.3 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021)
The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services— Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications-Commercial Products or Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.
(a) Definitions. As used in this provision—
Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition. (1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any…