1 | P a g e

Mammoth Cave National Park

STATEMENT OF WORK

Cyclic HVAC Upgrades

PMIS# 352411

DATED: 3/9/2026

NATIONAL PARK SERVICE

SOUTHEAST REGION

2 | P a g e

DIVISION 1 – GENERAL REQUIREMENTS

1. DESCRIPTION OF WORK

The Contractor shall furnish all labor, materials, tools, equipment, supervision, and transportation necessary to remove and replace eighteen (18) HVAC systems located in eleven (11) buildings at Mammoth Cave National Park.

The purpose of this project is to replace aging HVAC systems that have reached or exceeded their expected service life with modern, energy-efficient systems that improve reliability, indoor air quality, and temperature control.

The work includes but is not limited to:

Removal and disposal of existing HVAC equipment Refrigerant recovery in accordance with EPA regulations Installation of new HVAC systems Installation of new refrigerant line sets where required Installation of Honeywell T6 programmable thermostats (or approved equal) for each unit Electrical connections and disconnects Ductwork transitions and modifications System charging and leak testing System startup and commissioning Demonstration and training for National Park Service personnel

The Contractor shall replace HVAC units located in the following facilities:

Maple Springs Quarters – Building 021 Maple Springs Bunkhouse – Building 306 Interpretation & Fee Program Offices – Building 037 Superintendent’s Office – Building 038 External Programs / IT-EE Office – Building 039 Administration & Human Resources Office – Building 040 Law Enforcement Ranger Station – Building 041 Facility Management Office – Building 063 Fitness Center / Evidence Locker – Building 064 Training Center – Building 096 Science Resource Management Office – Building 313

3 | P a g e

The Contractor shall remove and replace the existing HVAC systems identified in the project equipment schedule and integrate the new systems with existing electrical, gas, and duct systems.

4 | P a g e

2. EXISTING UTILITIES

Existing utilities serving the buildings include electrical power, propane gas service, ductwork distribution systems, and condensate drainage.

The Contractor shall verify existing utilities and connections prior to installation.

Utility connections include:

Electrical power connections Propane supply connections Condensate drain connections Ductwork supply and return connections

Any discrepancies between field conditions and contract documents shall be reported to the Contracting Officer Representative (COR).

3. CONTRACTOR USE OF PREMISES

Buildings included in this project are active operational facilities including administrative offices, staff housing, training facilities, and operational support buildings.

The Contractor shall coordinate work with the COR to minimize disruption to park operations.

The Contractor shall:

Maintain safe work areas Protect existing facilities and infrastructure Prevent disruption of essential building functions Maintain clear access to building entrances and emergency exits

Construction debris shall be removed regularly and disposed of in accordance with federal, state, and local regulations.

4. COMMENCEMENT, PROSECUTION, AND COMPLETION

The period of performance shall be 180 calendar days from issuance of the Notice to Proceed (NTP).

Within fourteen (14) days of the NTP, the Contractor shall submit a project schedule showing the sequence of work for each building.

Work shall be coordinated to minimize disruption to park operations.

5 | P a g e

5. EXAMINATION OF SITE

Prospective contractors are strongly encouraged to conduct site visits prior to submitting proposals.

Site visits will allow contractors to evaluate:

Existing HVAC equipment conditions Mechanical access and equipment clearances Electrical service availability Ductwork configuration Exterior equipment locations

Failure to conduct a site visit does not relieve the Contractor of responsibility for completing the work as specified.

6. ABBREVIATIONS

ABA – Architectural Barriers Act ANSI – American National Standards Institute ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers EPA – Environmental Protection Agency HVAC – Heating, Ventilation, and Air Conditioning MACA – Mammoth Cave National Park NPS – National Park Service OSHA – Occupational Safety and Health Administration PMIS – Project Management Information System

7. ACCIDENT PREVENTION

All work shall comply with OSHA 29 CFR 1926 Construction Safety Standards.

The Contractor shall prepare a Site-Specific Safety Plan including:

Job Hazard Analysis (JHA) Lockout/Tagout procedures Electrical safety procedures Refrigerant handling procedures Fall protection procedures when applicable

All personal protective equipment shall comply with OSHA and applicable ANSI standards.

6 | P a g e

8. PRECONSTRUCTION CONFERENCE

A preconstruction conference shall be held prior to the start of work.

Topics will include:

Project schedule Safety requirements Work sequencing Environmental compliance Coordination with park staff

9. SUBMITTALS

The Contractor shall submit the following for approval:

HVAC equipment specifications Thermostat specifications Manufacturer product data Equipment shop drawings Installation procedures Startup and commissioning documentation Warranty information Operation and maintenance manuals

10. TEMPORARY SERVICES

The Contractor shall provide any temporary utilities required for installation and testing including temporary power or ventilation.

Temporary services shall not disrupt park operations.

11. PROJECT CLOSEOUT

Project closeout shall include:

Final inspection by the COR System testing verification Delivery of warranties and manuals

7 | P a g e

Demonstration of system operation Submission of as-built documentation

8 | P a g e

DIVISION 23 – HVAC MECHANICAL SPECIFICATIONS

23.01 HVAC EQUIPMENT SPECIFICATIONS

All HVAC equipment shall meet the following minimum performance specifications:

Cooling Efficiency

• 14–15 SEER2 minimum

Heating Efficiency

• 92% AFUE gas furnace where gas heating is provided

Electrical Requirements

• 240 Volt, single phase

Refrigerant

• R-454B refrigerant

Cabinet Width

• 19–21-inch cabinet size for furnace units

Filter MERV Rating

• 8

Equipment shall be new, factory assembled and listed by a recognized testing laboratory.

Equipment shall comply with:

ASHRAE standards AHRI certification DOE energy efficiency requirements

23.02 REFRIGERANT LINE SET REQUIREMENTS

Refrigerant piping shall meet the following requirements:

Minimum 50-foot line set capacity where required Insulated suction lines Brazed copper connections Nitrogen purge during brazing Leak testing with nitrogen pressure Proper line support and protection

9 | P a g e

Line sets shall be installed in accordance with manufacturer specifications.

23.03 CONTROLS AND THERMOSTATS

Each HVAC system shall include installation of a Honeywell T6 programmable thermostat (or approved equal).

Thermostats shall provide:

Programmable scheduling Heating and cooling control Fan operation control Digital display

Thermostats shall be mounted in accessible locations in accordance with Architectural Barriers Act (ABA) accessibility guidelines.

Low-voltage wiring shall be installed and protected in accordance with NEC requirements.

23.04 SYSTEM INSTALLATION

The Contractor shall install all HVAC equipment in accordance with manufacturer installation instructions.

Installation shall include:

Proper equipment anchoring Electrical connections Refrigerant piping connections Condensate drainage connections Ductwork transitions where required

All equipment clearances required by manufacturers shall be maintained.

23.05 STARTUP AND COMMISSIONING

The Contractor shall perform startup and commissioning procedures for each installed HVAC system.

Commissioning procedures shall include:

Refrigerant evacuation and charging

10 | P a g e

Leak testing Electrical verification Thermostat calibration Airflow verification Operational testing

The Contractor shall verify proper heating and cooling performance and document system operation.

Startup reports shall be submitted to the COR prior to project acceptance.

23.06 TRAINING

The Contractor shall provide basic training to NPS maintenance personnel covering:

Thermostat operation System startup and shutdown procedures Routine maintenance requirements

23.07 WARRANTIES

The Contractor shall provide manufacturer warranties for all installed HVAC equipment.

Minimum warranty requirements:

1-year labor warranty Manufacturer equipment warranty

Warranty documentation shall be provided during project closeout.

DIVISION 1 – GENERAL REQUIREMENTS
1. DESCRIPTION OF WORK
The Contractor shall furnish all labor, materials, tools, equipment, supervision, and transportation necessary to remove and replace eighteen (18) HVAC systems located in eleven (11) buildings at Mammoth Cave National Park.
The purpose of this project is to replace aging HVAC systems that have reached or exceeded their expected service life with modern, energy-efficient systems that improve reliability, indoor air quality, and temperature control.
The work includes but is not limited to:
Removal and disposal of existing HVAC equipment
Refrigerant recovery in accordance with EPA regulations
Installation of new HVAC systems
Installation of new refrigerant line sets where required
Installation of Honeywell T6 programmable thermostats (or approved equal) for each unit
Electrical connections and disconnects
Ductwork transitions and modifications
System charging and leak testing
System startup and commissioning
Demonstration and training for National Park Service personnel
The Contractor shall replace HVAC units located in the following facilities:
Maple Springs Quarters – Building 021
Maple Springs Bunkhouse – Building 306
Interpretation & Fee Program Offices – Building 037
Superintendent’s Office – Building 038
External Programs / IT-EE Office – Building 039
Administration & Human Resources Office – Building 040
Law Enforcement Ranger Station – Building 041
Facility Management Office – Building 063
Fitness Center / Evidence Locker – Building 064
Training Center – Building 096
Science Resource Management Office – Building 313
The Contractor shall remove and replace the existing HVAC systems identified in the project equipment schedule and integrate the new systems with existing electrical, gas, and duct systems.
2. EXISTING UTILITIES
Existing utilities serving the buildings include electrical power, propane gas service, ductwork distribution systems, and condensate drainage.
The Contractor shall verify existing utilities and connections prior to installation.
Utility connections include:
Electrical power connections
Propane supply connections
Condensate drain connections
Ductwork supply and return connections
Any discrepancies between field conditions and contract documents shall be reported to the Contracting Officer Representative (COR).
3. CONTRACTOR USE OF PREMISES
Buildings included in this project are active operational facilities including administrative offices, staff housing, training facilities, and operational support buildings.
The Contractor shall coordinate work with the COR to minimize disruption to park operations.
The Contractor shall:
Maintain safe work areas
Protect existing facilities and infrastructure
Prevent disruption of essential building functions
Maintain clear access to building entrances and emergency exits
Construction debris shall be removed regularly and disposed of in accordance with federal, state, and local regulations.
4. COMMENCEMENT, PROSECUTION, AND COMPLETION
The period of performance shall be 180 calendar days from issuance of the Notice to Proceed (NTP).
Within fourteen (14) days of the NTP, the Contractor shall submit a project schedule showing the sequence of work for each building.
Work shall be coordinated to minimize disruption to park operations.
5. EXAMINATION OF SITE
Prospective contractors are strongly encouraged to conduct site visits prior to submitting proposals.
Site visits will allow contractors to evaluate:
Existing HVAC equipment conditions
Mechanical access and equipment clearances
Electrical service availability
Ductwork configuration
Exterior equipment locations
Failure to conduct a site visit does not relieve the Contractor of responsibility for completing the work as specified.
6. ABBREVIATIONS
ABA – Architectural Barriers Act
ANSI – American National Standards Institute
ASHRAE – American Society of Heating, Refrigerating and Air-Conditioning Engineers
EPA – Environmental Protection Agency
HVAC – Heating, Ventilation, and Air Conditioning
MACA – Mammoth Cave National Park
NPS – National Park Service
OSHA – Occupational Safety and Health Administration
PMIS – Project Management Information System
7. ACCIDENT PREVENTION
All work shall comply with OSHA 29 CFR 1926 Construction Safety Standards.
The Contractor shall prepare a Site-Specific Safety Plan including:
Job Hazard Analysis (JHA)
Lockout/Tagout procedures
Electrical safety procedures
Refrigerant handling procedures
Fall protection procedures when applicable
All personal protective equipment shall comply with OSHA and applicable ANSI standards.
8. PRECONSTRUCTION CONFERENCE
A preconstruction conference shall be held prior to the start of work.
Topics will include:
Project schedule
Safety requirements
Work sequencing
Environmental compliance
Coordination with park staff
9. SUBMITTALS
The Contractor shall submit the following for approval:
HVAC equipment specifications
Thermostat specifications
Manufacturer product data
Equipment shop drawings
Installation procedures
Startup and commissioning documentation
Warranty information
Operation and maintenance manuals
10. TEMPORARY SERVICES
The Contractor shall provide any temporary utilities required for installation and testing including temporary power or ventilation.
Temporary services shall not disrupt park operations.
11. PROJECT CLOSEOUT
Project closeout shall include:
Final inspection by the COR
System testing verification
Delivery of warranties and manuals
Demonstration of system operation
Submission of as-built documentation
DIVISION 23 – HVAC MECHANICAL SPECIFICATIONS
23.01 HVAC EQUIPMENT SPECIFICATIONS
All HVAC equipment shall meet the following minimum performance specifications:
Cooling Efficiency • 14–15 SEER2 minimum
Heating Efficiency • 92% AFUE gas furnace where gas heating is provided
Electrical Requirements • 240 Volt, single phase
Refrigerant • R-454B refrigerant
Cabinet Width • 19–21-inch cabinet size for furnace units
Filter MERV Rating • 8
Equipment shall be new, factory assembled and listed by a recognized testing laboratory.
Equipment shall comply with:
ASHRAE standards
AHRI certification
DOE energy efficiency requirements
23.02 REFRIGERANT LINE SET REQUIREMENTS
Refrigerant piping shall meet the following requirements:
Minimum 50-foot line set capacity where required
Insulated suction lines
Brazed copper connections
Nitrogen purge during brazing
Leak testing with nitrogen pressure
Proper line support and protection
Line sets shall be installed in accordance with manufacturer specifications.
23.03 CONTROLS AND THERMOSTATS
Each HVAC system shall include installation of a Honeywell T6 programmable thermostat (or approved equal).
Thermostats shall provide:
Programmable scheduling
Heating and cooling control
Fan operation control
Digital display
Thermostats shall be mounted in accessible locations in accordance with Architectural Barriers Act (ABA) accessibility guidelines.
Low-voltage wiring shall be installed and protected in accordance with NEC requirements.
23.04 SYSTEM INSTALLATION
The Contractor shall install all HVAC equipment in accordance with manufacturer installation instructions.
Installation shall include:
Proper equipment anchoring
Electrical connections
Refrigerant piping connections
Condensate drainage connections
Ductwork transitions where required
All equipment clearances required by manufacturers shall be maintained.
23.05 STARTUP AND COMMISSIONING
The Contractor shall perform startup and commissioning procedures for each installed HVAC system.
Commissioning procedures shall include:
Refrigerant evacuation and charging
Leak testing
Electrical verification
Thermostat calibration
Airflow verification
Operational testing
The Contractor shall verify proper heating and cooling performance and document system operation.
Startup reports shall be submitted to the COR prior to project acceptance.
23.06 TRAINING
The Contractor shall provide basic training to NPS maintenance personnel covering:
Thermostat operation
System startup and shutdown procedures
Routine maintenance requirements
23.07 WARRANTIES
The Contractor shall provide manufacturer warranties for all installed HVAC equipment.
Minimum warranty requirements:
1-year labor warranty
Manufacturer equipment warranty
Warranty documentation shall be provided during project closeout.