DRAFT Attachment J-2 Task Order Activity Report DRD.pdf
PDF 211 KB Posted
- Solicitation number
- 80MSFC24R0015
About this file
This document is a Draft Data Requirements Description (DRD) for Task Order Activity Reports for the Engineering Services and Science Capability Augmentation (ESSCA) II contract with NASA's Marshall Space Flight Center (MSFC). The reports will provide comprehensive monthly status updates on all active Task Orders (TOs), including management and technical content such as work accomplished, planned tasks, vacancy status, potential performance problems, schedule milestones, and cost variances.
The reports must be submitted electronically within 8 business days after the contractor's accounting month, with the initial submission due no later than 30 days after the phase-in period. They require detailed reporting across multiple dimensions, including labor hours broken down by Prime, Teammates, and Subcontractors, cost expenditures compared to negotiated costs, and monthly phased cost reporting with variances against the approved Task Order Plan. The electronic submissions should use Excel for cost data and MS Word or PowerPoint for technical content, and be available through the contractor's system.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT Attachment J-2
J-2-2
DATA REQUIREMENTS DESCRIPTION (DRD)
1. DPD NO.: 1839 ISSUE: Draft RFP 2. DRD NO.: 1839MA-006
3. DATA TYPE: 3 4. DATE REVISED:
5. PAGE: 1/2
6. TITLE: Task Order Activity Reports
7. DESCRIPTION/USE: To provide data for the assessment of contract progress by Task
Order (TO) and any related sub-task and to provide visibility to the Contractor and MSFC Management of actual and potential problems and their progress toward meeting the requirements of the contract.
8. OPR: ED01 9. DM: ED01
10. DISTRIBUTION: Per Contracting Officer’s letter
11. INITIAL SUBMISSION: No later 30 days after conclusion of the phase-in period
12. SUBMISSION FREQUENCY: Monthly thereafter; submitted within eight (8) business days following the end of the Contractor’s accounting month.
13. REMARKS:
14. INTERRELATIONSHIP: DRD 1839MA-007, Financial Management Report (533M).
PWS paragraph 2.5.5
15. DATA PREPARATION INFORMATION:
15.1 SCOPE: The Task Order Activity Reports provide a comprehensive status on all active TOs and any related sub-tasks and include the necessary information to assess status and identify problems that need resolution for accomplishment of the contract tasks.
15.2 APPLICABLE DOCUMENTS/CLAUSES: None
15.3 CONTENTS: The Task Order Activity Reports shall include:
a. Management and Technical content:
1. Review of work accomplished, including quantitative description, during the reporting period.
2. Discussion of non-routine tasks planned for the next reporting period.
3. Vacancy Status providing the open vacancies per TO (include details such as labor category and any specialty requirements of the position), age of the unfilled vacancy, status of fulfillment.
4. Indication of any problems, which may impede performance or impact performance, schedule or cost; to include Government-provided data, hardware, or decisions.
5. Schedule with milestones, status, and time to completion if different than original milestone dates resulting from the problem identified in 3.
DRAFT Attachment J-2
J-2-3
DRD Continuation Sheet TITLE: Task Order Activity Reports DRD NO.: 1839MA-006
DATA TYPE: 3 PAGE: 2/2
6. Any estimated impact to cost resulting from the problem identified in 3.
7. Any other information that may assist the technical evaluators in evaluating the technical and administrative program; such as innovative processes, cost-reduction initiatives, etc.
b. Cost content shall include variance explanations down to sub-task level 7 as defined in Attachment J-9, Contract Work Breakdown Structure (CWBS), and reconcile with the Financial Management Report (533M) submitted in accordance with DRD 1839MA- 007 for the following:
1. Labor hours (broken down by Prime, Teammates and Subcontractor hours) expended by labor category showing overtime hours separately for each TO and any related sub-task.
2. Cost expended (broken down by Prime, Teammates and Subcontractor hours and broken down by cost element) versus negotiated cost for each TO and any related sub-task.
3. In those cases where multiple funding WBS’s are provided on a TO sub-task, cost detail shall be delineated to the appropriate level of the CWBS.
c. A separate cost report for the current Task Order period, phased by month, for each TO, identifying actual costs through the reporting perio, and planned costs for the remainder of the period, broken down, includes separate data for each subtask, and for the total roll-up of all subtasks in the TO.
1. Reporting categories shall be labor costs, and each of the non-labor cost categories.
2. Show a variance of actual costs against the approved Task Order Plan (TOP), and variance of the planned costs against the approved TOP.
15.4 FORMAT: Contractor format is acceptable. Electronic submission of Contractor data shall be submitted in Excel® format for cost data, technical content in either MS Word® or MS PowerPoint®, and be available via Contractor system.