This document provides revisions to questions and answers for a solicitation seeking proposals for the Total and Spectral solar Irradiance Sensor-2 (TSIS-2) spacecraft. The National Aeronautics and Space Administration Goddard Space Flight Center updated requirements to specify over-current protection instead of fusing for instrument power feeds and clarified that factor of safety requirements are in addition to quasi-static load specifications. Offerors are invited to submit proposals by February 6, 2020 for a firm-fixed price contract awarded in May 2020 to acquire a spacecraft and related services including mission operations. The work will be performed offsite at the contractor's facilities to support the TSIS-2 Project through June 2023.

View the file

Other files for this federal contract opportunity

Other files attached to Total and Spectral solar Irradiance Sensor-2 (TSIS-2) Spacecraft, newest first.
File Type Posted
Questions and Responses Set #2.pdf PDF
GPR 7120_4D.pdf PDF
Enclosure 1 - Quality Assurance Surveillance Plan-1.27.20_Clean.pdf PDF
TSIS2-SC-REQ-0005_Rev-B_Draft-1_Observatory Requirements Document_Redline (1).pdf PDF
TSIS2-SC-CDRL-0002_Rev-B_Observatory_CDRL_Released_01-27-2020 (1).pdf PDF
TSIS2-SC-SOW-0002_Rev-D_Draft-1_TSIS-2 Observatory SOW_Redline (1).pdf PDF
TSIS2-SC-REQ-0006_Rev-B_TSIS-2_Spacecraft MAR_released_01-27-2020_ (1).pdf PDF
TSIS2-SC-REQ-0005_Rev-B_TSIS-2_Observatory_Requirements_Document_released_01-27-2020 (1).pdf PDF
TSIS2-SC-SOW-0002_Rev-D_TSIS-2_Observatory_SOW_Released_01-27-2020 (1).pdf PDF
TSIS2-SC-REQ-0006_Rev-B_DRAFT-1_TSIS-2_Spacecraft MAR_Redline (1).pdf PDF
TSIS2-SC-TN-0003_Rev-B_Spacecraft IARD_Released_01-27-2020 (1).pdf PDF
TSIS2-SC-TN-0003_Rev-B_DRAFT-2_Spacecraft IARD_Redlined.pdf PDF
TSIS2-SC-CDRL-0002_Rev-B_DRAFT-1_Observatory_CDRL_Redlined.pdf PDF
Amendment 2 signed.pdf PDF
TSIS-2-Decal-FINAL.pdf PDF
GPR 7120.4A.pdf PDF
TSIS-Decal-FINAL.png PNG image
Questions and Responses - Set #1 - FINAL.pdf PDF
Attachment B - Requirements Document (REQ) Rev - A.pdf PDF
Attachment E - Mission Assurance Requirements (MAR) Rev - A.pdf PDF
Amendment #1 80GSFC20R0009.pdf PDF
Attachment F - Major Payment Events (Post Amendment_.pdf PDF
Request for Proposal (RFP) 80GSFC20R0009 (AMENDMENT #1).pdf PDF
Exhibit 2 - Firm Fixed Price Breakdown.pdf PDF
Request for Proposal (RFP) 80GSFC20R0009.pdf PDF
Attachment E - Mission Assurance Requirements (MAR) Rev - A.pdf PDF
Exhibit 1 - Past Performance Questionnaire.pdf PDF
Attachment D - Instruments Accommodation Requirements Document (IARD) Rev - A.pdf PDF
Attachment C - Contract Data Requirements List (CDRL) Rev - A.pdf PDF
Exhibit 4 - Small Business Subcontracting Plan Goals.pdf PDF
Attachment F - Major Payment Events.pdf PDF
Attachment B - Requirements Document (REQ) Rev -.pdf PDF
Exhibit 3 - Requirements-to-Proposal Cross Reference.pdf PDF
Attachment A - Statment of Work (SOW) Rev - C.pdf PDF
Enclosure 1 - Quality Assurance Surveillance Plan.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This question and response document revises the responses to questions #35 & 46 which was posted on

January 18, 2020 to beta.SAM.gov entitled, “Questions and Responses – Set #1”. The questions and revised answers are listed below.

# DOC REF Contractor Question/Comment Project Response

35 REQ 4.4.15 Recommend changing requirement to “Each instrument power feed shall have over-current protection.” Specifying fusing is prescribing a design where other approaches may be more appropriate and/or lower cost.

This requirement has been updated to incorporate over-current protection instead of fusing.

46 REQ 6.3.2.1 Requirement states that +/- 15g, does this take into account the factor of safety, or should the factor of safety be applied in addition to the stated quasi-static load?

Table 5 shows factor of safety requirements.