This is a project scope document for Salt Lake Community College's (SLCC) Wayfinding Phase 1 project, managed by Project Manager Talieya Wallace. The project requires a qualified General Contractor to demo and install exterior and interior wayfinding improvements utilizing GSBS design plans and specifications, including associated electrical, irrigation, and landscaping work. Contractors must have a minimum of five years of experience working on similar or larger projects with SLCC. Key requirements include obtaining all necessary permits in compliance with UDOT and MUTCD standards, providing traffic control in active work areas, implementing fencing and safety barricades to protect students and staff from the active campus environment, and completing weekly Owners Authorized Representative (OAC) meetings on Thursday mornings. The contractor must secure written approval from the SLCC Project Manager before commencing any work, including the initial site mobilization, and must attend mandatory pre-construction, communication planning, risk management, substantial completion, final completion, retrospective, and one-year warranty meetings totaling approximately 15 hours.
The contractor is responsible for all debris and material disposal off-site without use of SLCC dumpsters, providing ADA-compliant weatherproof reroute signage for pedestrian traffic, and mobilizing barricades and staging areas with fencing the evening prior to work or before 7:00 a.m. on the first day. The contractor and all subcontractors must accept the state of Utah's standard terms and conditions without submitting alternative company terms, and are required to work weekends and holidays if schedule delays result from causes not attributable to the owner. Any property damage caused by the contractor shall be restored at contractor expense, with damages within two feet of marked utility lines requiring complete repair at contractor cost. The contractor must maintain adequate personnel and safety measures to ensure timely, quality completion while accommodating an active college campus environment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 6-SLCC Wayfinding Bid Set.pdf | ||
| 5-Invitation for Bid - SLCC Wayfinding Phase 1.docx | DOCX document | |
| 2-Certificate-of-Substantial-Completion (1).docx | DOCX document | |
| 1-SALT LAKE COMMUNITY COLLEGE GENERAL BID PROVISIONS.pdf | ||
| 7-25-08-01 SLCC WAYFINDING IMPLEMENTATON PHASE SPECIFICATIONS (1).pdf | ||
| 4-Subcontractors+List (1).docx | DOCX document | |
| 3-Contractors-Agreement (1).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
PROJECT SCOPE
PROJECT MANAGER: TALIEYA WALLACE
11/21/2025
OVERVIEW
I. Project
Wayfinding Phase 1
II. Project Scope
Use GSBS design plans and specifications to demo and install exterior and interior wayfinding – Including electrical, irrigation, and landscaping.
IV. High Level Requirements
• Bidders must accept the terms and conditions of the state of Utah. Do not submit a quote with your company terms and conditions printed on it. Any quote that is received with terms and conditions will be rejected.
• Only General Contractors qualify to bid on this project.
• General Contractor must have at least 5yrs experience working with SLCC on similar size or larger projects.
• Any damage caused to SLCC property by contractor shall be restored to its original or better condition.
Any Damage caused within 2 feet of a marked utility line shall be repaired at the contractor’s expense
• In areas where work may interfere or be hazardous to traffic, the contractor shall provide traffic control and obtain permitting that is in compliance with UDOT and MUTCD standards.
• Contractor should be aware that the job site is an active campus and shall provide enough personnel or additional barricades/safety devices to keep students and staff from walking through work zone areas.
Fencing is required. No Tape acceptable on this job.
• Contractor & subcontractors shall work weekends and holidays if behind schedule due to reasons not caused by owner.
• Contractor shall provide the necessary personnel needed to complete scope of work on time while ensuring quality.
• Contractors and subcontractors shall not commence work without SLCC PM’s approval. This includes but is not limited to first day on site, work awaiting RFI response, work awaiting change order, etc..
o If being on schedule depends on RFI response or change order turnaround time, it is the contractor’s sole responsibility to inform the SLCC PM if delays are interfering with the critical path. It is not acceptable for the contractor or subcontractor to work areas of the aforementioned processes without the SLCC PM’s written approval.
• This project requires a weekly OAC, held Thursday mornings.
2 | P a g e
• All road, sidewalk, and vehicular route closures require an SLCC PM approved action plan from contractor.
V. Inclusions
• Contractor shall dispose of any extra unused soil, sod, and debris from planting and other materials off site.
Contractor shall not use SLCC dumpsters.
• Contractor shall provide and place typed, ADA compliant, weatherproof reroute signage with a contrast of light and dark, for all foot traffic as determined by SLCC PM. Signage can be professionally laminated, plastic or metal. May require sandbags or weights to keep signage erected.
VI. Assumptions
• Schedule weekends and breaks for sensitive areas as requested by owner.
• Crews are supervised at all times by a qualified supervisor employed by the General Contractor.
• General Contractor’s PM and Superintendent to attend precon and closeout meetings as listed: Pre-con, Communication Management Planning, Risk Management Planning, Substantial Completion, Final Completion, Retrospective, 1yr Warranty. (15hrs total)
• Contractor to be available for emergencies related to project work, including outside of business hours.
VII. Deliverables
All tools, equipment, machinery, and personnel needed to execute the job. Provide material and personnel to put up barricades the evening before, -OR- before parking stalls fill up (generally before 7:00 a.m.) Staging requires fencing.
VIII. Affected Parties
Students, faculty, & staff- To the degree that sidewalks, parking, and resting areas may be temporarily closed off for safety purposes.
| Overview |
| I. Project |
| II. Project Scope |
| IV. High Level Requirements |
| V. Inclusions |
| VI. Assumptions |
| VII. Deliverables |
| VIII. Affected Parties |