8-REQ-0007862 Specifications Vol. II.pdf

PDF 3 MB Posted

Attached to
Third-Party Design Review of Screened Final Effluent Project
Solicitation number
REQ - 0007862
Issued by
Wayne County, Michigan

About this file

Summary

This is a comprehensive specification document issued by the Great Lakes Water Authority (GLWA) for the Rehabilitation of the Screened Final Effluent (SFE) Pump Station, Contract No. 2000970, dated May 2025. The document constitutes Volume II of IV Specifications and covers Division 26 (Electrical) through Division 31 (Earthwork) requirements for the project. The work encompasses rehabilitation of the SFE pump station facility, including design and installation of medium-voltage electrical systems, low-voltage distribution equipment, motors, transformers, controls, lighting systems, and geotechnical instrumentation and monitoring. Key electrical components specified include medium-voltage switchgear with vacuum circuit breakers rated 4.16 kV and 63 kA short circuit capacity, medium-voltage liquid-filled transformers with neutral grounding resistors, motor control centers, low-voltage panelboards, adjustable frequency drives, medium and low-voltage induction motors, and comprehensive lighting systems with LED technology. The specifications also detail extensive commissioning and testing requirements in accordance with NETA standards, IEEE protocols, and NFPA 70 (National Electrical Code). The document includes geotechnical instrumentation requirements for monitoring ground movement and structural deflections throughout construction, with specific provisions for surface monitoring points, tell-tales, inclinometers, and vibration monitoring devices. All work must comply with seismic design standards for importance factor 1.5 and be installed in accordance with applicable industry standards and local regulations in Michigan.

The specifications establish rigorous quality assurance requirements including manufacturer qualifications, third-party testing and certification, factory acceptance testing, and field commissioning by factory-trained representatives. The Contractor must furnish all labor, materials, equipment, and supervision necessary for complete and functional installation, with specific emphasis on proper grounding, bonding, and lightning protection systems. Installation procedures, testing protocols, operational acceptance criteria, and maintenance documentation requirements are comprehensively detailed throughout. All electrical equipment must bear appropriate UL listing marks and comply with NFPA and IEEE standards. The geotechnical instrumentation program requires employment of licensed Professional Engineers and registered land surveyors with minimum five years of relevant experience, with daily monitoring during excavation activities and weekly readings during non-excavation phases. Damaged or inoperative instruments must be replaced within 24 hours, and comprehensive as-built documentation, calibration certificates, and monitoring data must be submitted to the Owner in electronic format upon project completion.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

I s s u e d f or P e r m it

Rehabilitation of Screened Final Effluent Pump Station

Contract No. 2000970

NORESCO for the Great Lakes Water Authority

Volume II of IV

Specifications

May 2025

Prepared By:

PROJECT NUMBER 2000970 REHABILITATION OF THE SFE PUMP STATION

MAY 2025 GLWA WRRF

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - i

TABLE OF CONTENTS

Pages

VOLUME I

PART 1—PROCUREMENT REQUIREMENTS (Not in this Submittal)

PART 2—CONTRACTING REQUIREMENTS (Not in this Submittal)

PART 3—SPECIFICATIONS

DIVISION 01—GENERAL REQUIREMENTS

01 11 00 Summary of Work.................................................................... 1- 4 01 14 00 Work Restrictions .................................................................... 1- 9 01 14 16 Coordination with Owner's Operations .................................... 1- 18 01 21 00 Allowances ............................................................................... 1- 3 01 22 01 Measurement and Payment ...................................................... 1- 5 01 25 00 Substitution Procedures ........................................................... 1- 4 01 26 13 Requests for Interpretation (RFI) Procedures .......................... 1- 3 01 26 13A Requests for Interpretation (RFI) Form ................................... 1- 1 01 29 73 Schedule of Values .................................................................. 1- 7 01 29 76 Progress Payment Procedures .................................................. 1- 5 01 31 13 Project Coordination ................................................................ 1- 5 01 31 19.13 Pre-Construction Conference ................................................... 1- 6 01 31 19.23 Progress Meetings .................................................................... 1- 3 01 31 26 Electronic Communication Protocols ...................................... 1- 6 01 32 16.20 Construction Progress Schedule .............................................. 1- 14 01 32 26 Construction Progress Reporting ............................................. 1- 2 01 32 33 Photographic Documentation................................................... 1- 6 01 33 00 Submittal Procedures ............................................................... 1- 13 01 33 30 Asset Turnover Process Requirements .................................... 1- 11 01 35 23 Owner's Safety Requirements .................................................. 1- 10 01 35 23.A GLWA Hot Works Permit ....................................................... 1- 2 01 35 23.B GLWA Confined Space Permit ............................................... 1- 2 01 35 53 Security .................................................................................... 1- 6 01 42 00 References ................................................................................ 1- 18 01 45 33 Special Inspection, Observation, and Testing .......................... 1- 6

Fabricator’s Certificate of Compliance .................................... 1- 1 Statement of Special Inspections ............................................. 1- 3 2015 IBC Tables ...................................................................... 1- 25

01 46 01 Quality Requirements .............................................................. 1- 9 01 51 00 Temporary Utilities .................................................................. 1- 9 01 51 41 Temporary Pumping ................................................................ 1- 7

Pages

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - ii

01 52 13 Field Offices and Sheds ............................................................ 1- 8 01 55 00 Vehicular Access and Parking .................................................. 1- 5 01 55 26 Maintenance and Protection of Traffic ..................................... 1- 4 01 57 00 Temporary Controls ................................................................. 1- 12 01 58 13 Temporary Project Signage ...................................................... 1- 4 01 61 00 Common Product Requirements .............................................. 1- 7

Manufacturer’s Certificate of Compliance ............................... 1- 1 01 66 00 Product Storage and Handling Requirements .......................... 1- 6 01 71 13 Mobilization ............................................................................. 1- 2 01 71 16 Acceptance of Conditions ........................................................ 1- 2 01 71 23 Field Engineering ..................................................................... 1- 9 01 71 33 Protection of Work and Property .............................................. 1- 6 01 73 19 Installation ................................................................................ 1- 5 01 73 29 Cutting and Patching ................................................................ 1- 8 01 74 13 Progress Cleaning ..................................................................... 1- 4 01 74 19 Construction Waste Management and Disposal ....................... 1- 4 01 74 23 Final Cleaning .......................................................................... 1- 4 01 75 11 Checkout and Startup Procedures ............................................. 1- 6 01 77 19 Closeout Requirements ............................................................. 1- 6 01 78 23 Operation and Maintenance Data ............................................. 1- 10 01 78 39 Project Record Documents ....................................................... 1- 8 01 78 40 OnBase Digital Document Turnover ........................................ 1- 18 01 78 43 Spare Parts ................................................................................ 1- 4 01 79 23 Instruction of Operation and Maintenance Personnel .............. 1- 16 01 88 15 Anchorage and Bracing ............................................................ 1- 5 01 91 00 Commissioning ......................................................................... 1- 16

DIVISION 02—EXISTING CONDITIONS

02 41 00 Demolition ................................................................................ 1- 7 02 61 00 Removal and Disposal of Contaminated Soil ........................... 1- 8

DIVISION 03—CONCRETE

03 30 10 Structural Concrete ................................................................... 1- 27 Concrete Mix Design, Class 5000F2S1P1C1 ........................... 1- 3 Concrete Mix Design, Class 4500F1S1P0C1 ........................... 1- 2 Concrete Mix Design, Class CF00F0S1P0C1 .......................... 1- 2

03 40 00 Precast Concrete ....................................................................... 1- 5 03 62 00 Grouting .................................................................................... 1- 7

24-hour Evaluation of Nonshrink Grout Test Form and Grout Testing Procedures .................................................. 1- 3

Pages

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - iii

DIVISION 04—MASONRY

04 21 13.13 Masonry Veneer ....................................................................... 1- 12 04 22 00 Concrete Unit Masonry ............................................................ 1- 13

DIVISION 05—METALS

05 05 19 Post-Installed Anchors ............................................................. 1- 9 05 05 23 Welding .................................................................................... 1- 6

Welding and Nondestructive Testing Table ............................ 1- 1 05 12 00 Structural Steel Framing .......................................................... 1- 12 05 31 00 Steel Decking ........................................................................... 1- 6 05 50 00 Metal Fabrications ................................................................... 1- 18 05 52 16 Aluminum Railings .................................................................. 1- 8 05 53 00 Metal Gratings ......................................................................... 1- 5

DIVISION 06—WOOD, PLASTICS, AND COMPOSITES

06 82 00 Glass-Fiber-Reinforced Plastic ................................................ 1- 10

DIVISION 07—THERMAL AND MOISTURE PROTECTION

07 21 01 Thermal Insulation ................................................................... 1- 2 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing ........................ 1- 9 07 62 00 Sheet Metal Flashing and Trim ................................................ 1- 8 07 70 01 Roof Specialties and Accessories ............................................ 1- 5 07 92 01 Sealants and Caulking .............................................................. 1- 2 07 95 13 Expansion Joint Cover Assemblies .......................................... 1- 3

DIVISION 08—OPENINGS

08 11 16 Aluminum Doors and Frames .................................................. 1- 3

08 45 00 Translucent Wall Assemblies .................................................. 1- 8 08 71 00 Door Hardware......................................................................... 1- 11

DIVISION 09—FINISHES

09 81 10 Pipe Joint Coating—Weld After Backfill ................................ 1- 7 09 81 12 Pipe Joint Coating—Weld Before Backfill.............................. 1- 6 09 90 00 Painting and Coating ................................................................ 1- 26 09 90 05 Pipeline Polyurethane Coating ................................................. 1- 14 09 96 35 Chemical-Resistant Coatings ................................................... 1- 16

Chemical-Resistant Coating System Data Sheet (CRCSDS) .. 1- 1 Chemical-Resistant Coating Product Data Sheet (CRCPDS). . 1- 1

09 97 13.01 Pipeline Tape Coating .............................................................. 1- 12

Pages

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - iv

DIVISION 10—SPECIALTIES

10 44 00 Fire Protection Specialties and Safety Equipment ................... 1- 4 10 73 13 Awnings .................................................................................... 1- 3

DIVISION 11 THROUGH DIVISION 20 (NOT USED)

DIVISION 21—FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems ..................................................... 1- 17

DIVISION 22—PLUMBING

22 07 00 Building Mechanical Thermal Insulation ................................. 1- 6 22 10 01 Plumbing Piping and Accessories ............................................ 1- 15 22 10 01.02 Polyvinyl Chloride Drain Waste and Vent (PVC-DWV)

Pipe and Fittings ....................................................................... 1- 1 22 30 00 Plumbing Equipment ................................................................ 1- 5

Instantaneous Water Heater ...................................................... 1- 1 Backflow Preventers ................................................................. 1- 1 Simplex, Submersible Pumps ................................................... 1- 1

22 40 00 Plumbing Fixtures .................................................................... 1- 7

DIVISION 23—HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 05 93 Testing, Adjusting, and Balancing for HVAC ......................... 1- 6 23 07 00 HVAC Insulation ...................................................................... 1- 8 23 09 00 Instrumentation and Control Devices for HVAC ..................... 1- 15 23 09 00.01 Open Temperature Control System .......................................... 1- 30 23 09 13 HVAC Controls, Field Components, and Instruments ............. 1- 8 23 09 40 Master Systems Integration Services (For Reference .............. 1- 28 23 09 94 Sequences of Operation for HVAC Controls ........................... 1- 19 23 31 13 Metal Ducts and Accessories ................................................... 1- 21 23 31 13.01 Ductwork Schedule .................................................................. 1- 2 23 31 16.16 Thermoset Fiberglass-Reinforced Plastic Ducts and Accessories ........................................................................ 1- 9 23 34 00 HVAC Fans .............................................................................. 1- 13 23 37 00 Air Outlets and Inlets ............................................................... 1- 3

Supplement: Air Outlets and Inlets .......................................... 1- 1 23 77 00 Air Handling Units ................................................................... 1- 29 23 81 00 Unitary Air-Conditioning Equipment ...................................... 1- 13 23 82 00 Terminal Heating and Cooling Units ....................................... 1- 6

DIVISION 24 THROUGH DIVISION 25 (NOT USED)

Pages

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - v

VOLUME II

DIVISION 26—ELECTRICAL

26 05 02 Basic Electrical Requirements ................................................. 1- 8 26 05 04 Basic Electrical Materials and Methods .................................. 1- 16 26 05 05 Conductors ............................................................................... 1- 18 26 05 26 Grounding and Bonding for Electrical Systems ...................... 1- 6 26 05 33 Raceway and Boxes ................................................................. 1- 29 26 05 70 Electrical Systems Analysis ..................................................... 1- 9

Figure 1: Example Arc Flash Label ......................................... 1- 1 26 08 00 Commissioning of Electrical Systems ..................................... 1- 28 26 09 13 Power Measurement and Control............................................. 1- 6 26 12 13 Medium-Voltage Liquid Fill Substation Transformers ........... 1- 11 26 13 13 Medium-Voltage Circuit Breaker Switchgear ......................... 1- 21 26 18 39 Medium-Voltage Motor Control .............................................. 1- 11 26 19 00 Medium-Voltage Induction Motors ......................................... 1- 17

Medium Voltage Induction Motors Data Sheet ....................... 1- 2 26 20 00 Low-Voltage AC Induction Motors ......................................... 1- 13 26 22 00 Low-Voltage Transformers ...................................................... 1- 4 26 24 16 Panelboards .............................................................................. 1- 7 26 24 19 Low-Voltage Motor Control .................................................... 1- 10 26 27 26 Wiring Devices ........................................................................ 1- 9 26 29 23 Low-Voltage Adjustable Frequency Drive System ................. 1- 12 26 41 00 Facility Lightning Protection ................................................... 1- 6 26 43 00 Surge Protective Devices (SPD) .............................................. 1- 4 26 50 00 Lighting .................................................................................... 1- 12

DIVISION 27 THROUGH 30 (NOT USED)

DIVISION 31—EARTHWORK

31 09 13 Geotechnical Instrumentation and Monitoring ........................ 1- 12 31 10 13 Site Preparation ........................................................................ 1- 4 31 14 00 Earth Stripping and Stockpiling ............................................... 1- 4 31 20 00 Earth Moving ........................................................................... 1- 16 31 22 00 Grading .................................................................................... 1- 12 31 23 03 Excavation and Fill for Utilities ............................................... 1- 22 31 23 13 Subgrade Preparation ............................................................... 1- 3 31 23 19.01 Dewatering ............................................................................... 1- 8 31 23 23 Fill and Backfill ....................................................................... 1- 9 31 40 00 Tunneled Crossings .................................................................. 1- 8 31 41 00 Shoring for Trenchless Construction ....................................... 1- 2 31 43 00 Steel Casing Pipe ..................................................................... 1- 3

Pages

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - vi

31 44 00 Settlement Monitoring for Trenchless Construction ................ 1- 9 31 45 00 Installation of Carrier Pipe in Steel Casing .............................. 1- 5 31 46 00 Backfill Grouting ...................................................................... 1- 11 31 50 00 Temporary Earth Retaining Systems ........................................ 1- 6

DIVISION 32—EXTERIOR IMPROVEMENTS

32 11 23 Aggregate Base and Subbase Courses ...................................... 1- 6 32 13 13 Concrete Paving ....................................................................... 1- 17 32 16 00 Curbs and Gutters ..................................................................... 1- 5 32 17 23 Pavement Markings .................................................................. 1- 5 32 31 13 Chain Link Fences and Gates ................................................... 1- 12 32 62 16 Steel Piles ................................................................................. 1- 15 32 92 00 Plants ........................................................................................ 1- 8

DIVISION 33—UTILITIES

33 05 01 Conveyance Piping—General .................................................. 1- 9 33 05 01.01 Welded Steel Pipe and Fittings ................................................ 1- 27 33 05 01.02 Ductile Iron Pipe and Fittings .................................................. 1- 10 33 05 01.07 Low-Head Reinforces Concrete Culvert, Storm Drain, and

Sewer Pipe (ASTM C361 Modified)........................................ 1- 6 33 05 01.10 High-Density Polyethylene (HDPE) Pressure Pipe and Fittings ............................................................................... 1- 9 33 05 13 Manholes .................................................................................. 1- 11 33 05 16.13 Precast Concrete Utility Structure ............................................ 1- 5 33 05 23 Guided Auger Boring ............................................................... 1- 11 33 13 00 Disinfection of Water Utility Distribution Facilities ................ 1- 5

DIVISION 34 THROUGH 39 (NOT USED)

DIVISION 40—PROCESS INTERCONNECTIONS

40 05 15 Piping Support Systems ............................................................ 1- 11 Table 1: Nonchemical Areas .................................................... 1- 1 Table 2: Chemical Areas .......................................................... 1- 1

40 05 33 Pipe Heat Tracing ..................................................................... 1- 5 40 27 00 Process Piping—General .......................................................... 1- 24 40 27 00.01 Cement-Mortar, Glass and Ceramic-Epoxy-Lined

Ductile Iron Pipe and Fittings .................................................. 1- 3 40 27 00.03 Carbon Steel Pipe and Fittings—General Service ................... 1- 5 40 27 00.07 Galvanized Steel Pipe and Malleable Iron Fittings .................. 1- 3 40 27 00.08 Stainless Steel Pipe and Fittings General Service .................... 1- 3 40 27 00.11 Chlorinated Polyvinyl Chloride (CPVC) Pipe and Fittings ..... 1- 2

Pages

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - vii

40 27 00.13 Copper and Copper Alloy Pipe Tubing and Fittings ............... 1- 1 40 27 00.15 Double Wall Containment Piping ............................................ 1- 1 40 27 01 Process Piping Specialties........................................................ 1- 15 40 27 02 Process Valves and Operators .................................................. 1- 31

Electric Actuated Valve Schedule ........................................... 1- 4 Self-Regulated Valve Schedule ............................................... 1- 1

40 42 13 Process Piping Insulation ......................................................... 1- 7 Service and Insulation Thickness Table .................................. 1- 1

40 80 01 Process Piping Leakage Testing .............................................. 1- 6 40 90 00 Instrumentation and Control for Process Systems ................... 1- 37

Component Specifications ....................................................... 1- 22 Instrument List ......................................................................... 1- 8 Loop Specifications ................................................................. 1- 19 Loop Status Report .................................................................. 1- 1 Instrument Calibration Sheet ................................................... 1- 1 I&C Valve Adjustment Sheet .................................................. 1- 1 Performance Acceptance Test Sheet ........................................ 1- 1

40 95 80 Fiber Optic Communication System ........................................ 1- 29 As-Built Fiber Optic Cable Installation Form ......................... 1- 2 As-Built Conduit/Innerduct Installation Form ......................... 1- 1

DIVISION 41—MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.13 Overhead Standing Bridge Cranes ........................................... 1- 10 Crane Data Sheet, System No. 1 .............................................. 1- 1

41 22 23.19 Monorail Hoists ....................................................................... 1- 8 Hoist/Monorail Data Sheet, System No. 1 ............................... 1- 1

DIVISION 42—PROCESS HEATING, COOLING, AND DRYING EQUIPMENT

(NOT USED)

DIVISION 43—PROCESS GAS AND LIQUID HANDLING, PURIFICATION,

AND STORAGE EQUIPMENT

43 40 02 Fiberglass Reinforced Plastic Tank ......................................... 1- 8 FRP Tank Schedule.................................................................. 1- 1 Tank Data Sheets ..................................................................... 1- 2

Pages

GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS

PW\DEN003\C6A18000 00 01 10 - viii

DIVISION 44—POLLUTION AND WASTE CONTROL EQUIPMENT

44 42 56.02 Horizontal Split-Case Centrifugal Pumps ................................ 1- 8 Horizontal Split-Case Centrifugal Pump Data Sheet ............... 1- 3

44 42 56.03 Vertical Turbine Pumps ............................................................ 1- 10 SFE Pump Data Sheet .............................................................. 1- 3 LPSW Pump Data Sheet ........................................................... 1- 3

44 42 56.10 Horizontal End Suction Self-Priming Centrifugal Pumps .................................................................... 1- 10 SO2 Carrier Water Pumps Data Sheet ..................................... 1- 2

44 42 56.11 Horizontal End Suction Centrifugal Pumps ............................. 1- 6 Horizontal End Suction Centrifugal Pump Data Sheet – Quench Water Booster Pump. ..................................... 1- 2

44 42 56.16 Peristaltic Metering Pump ........................................................ 1- 6 Peristaltic Hose Pump Data Sheet ............................................ 1- 6

44 42 56.18 Flexibly Coupled Vertical Inline Centrifugal Pump ................ 1- 6 Flexibly Coupled Vertical Inline Centrifugal Pump Data Sheet – Intermediate Pressure Secondary Water Booster Pump ........... 1- 2 Flexibly Coupled Vertical Inline Centrifugal Pump Data Sheet – Quench Water Booster Pump ................................................... 1- 2

44 43 33 Motorized Automatic Strainer .................................................. 1- 7

DIVISION 45—INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT (NOT

USED)

DIVISION 46—WATER AND WASTEWATER EQUIPMENT

46 61 46 Disk Filter Equipment .............................................................. 1- 16

DIVISION 47 THROUGH 49 (NOT USED)

VOLUME III—DRAWINGS (BOUND SEPARATELY)

VOLUME IV—STANDARD DETAILS (BOUND SEPARATELY)

END OF SECTION

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 1

SECTION 26 05 02

BASIC ELECTRICAL REQUIREMENTS

PART 1 GENERAL

1.01 RELATED SECTIONS

A. Requirements specified within this section apply to Division 26, Electrical.

Work specified herein shall be performed as if specified in the individual sections.

1.02 REFERENCES

A. The following is a list of standards which may be referenced in this section:

1. National Electrical Contractors Association (NECA): National Electrical Installation Standards.

2. National Electrical Manufacturers Association (NEMA):

a. 250, Enclosures for Electrical Equipment (1000 Volts Maximum).

b. Z535.4, Product Safety Signs and Labels.

3. National Fire Protection Association (NFPA): 70, National Electrical Code (NEC).

4. UL.

5. InterNational Electrical Testing Association (NETA).

1.03 SUBMITTALS

A. Action Submittals:

1. Provide manufacturers’ data for the following:

a. Electrical service components.

b. Nameplates, signs, and labels.

2. Underground, under slab, and embedded conduit drawings.

3. Duct bank routing drawings.

1.04 QUALITY ASSURANCE

A. Provide the Work in accordance with NFPA 70. Where required by Authority Having Jurisdiction (AHJ), material and equipment shall be labeled or listed by a nationally recognized testing laboratory or other organization acceptable to the AHJ, in order to provide a basis for approval under the NEC.

B. Materials and equipment manufactured within the scope of standards published by Underwriters Laboratories Inc. shall conform to those standards and shall have an applied UL listing mark or label.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 2

C. Provide materials and equipment acceptable to AHJ for Class, Division, and Group of hazardous area indicated.

1.05 ENVIRONMENTAL CONDITIONS

A. The following areas are classified nonhazardous, wet, and washdown areas.

Use materials and methods required for such areas.

1. Outdoor above grade areas not covered below.

2. Below grade vaults.

3. SFE Pump Room.

4. Machine Shop basement.

5. SO2 Carrier Water Pump Building.

6. Washdown (unless also corrosive).

B. The following areas are nonhazardous, wet, and corrosive. Use materials and methods required for such areas.

1. SFE Chemical Room.

2. SFE Filter Room.

3. Complex II Incineration Room.

4. Sodium Hypochlorite Room.

C. The following areas are nonhazardous, indoor, and dry: Electrical Rooms.

D. The following areas are not classified. Use NEMA 12 materials and methods.

1. Areas not covered below.

PART 2 PRODUCTS

2.01 GENERAL

A. Where two or more units of the same class of material or equipment are required, provide products of a single manufacturer. Component parts of materials or equipment need not be products of the same manufacturer.

B. Material and equipment installed in heated and ventilated areas shall be capable of continuous operation at their specified ratings within an ambient temperature range of 40 degrees F to 104 degrees F.

C. Materials and equipment installed outdoors shall be capable of continuous operation at their specified rating within the ambient temperature range stated in Section 01 61 00, Common Product Requirements.

D. Equip panels installed outdoors in direct sun with sun shields.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 3

E. Panels with terminations shall have minimum 3 feet clearance in front of them, unless more is required by the NEC. Doors shall be able to swing more than 100 degrees.

F. Follow equipment manufacturers recommendations where applicable.

2.02 EQUIPMENT FINISH

A. Manufacturer’s standard finish color, except where specific color is indicated.

If manufacturer has no standard color, finish equipment in accordance with Section 09 90 00, Painting and Coating, light gray color finish as approved by Engineer.

2.03 NAMEPLATES

A. Material: Laminated plastic.

B. Attachment Screws: Stainless steel.

C. Color: White, engraved to a black core.

D. Letter Height:

1. Pushbuttons/Selector Switches: 1/8 inch.

2. Other electrical equipment: 1/4 inch.

2.04 SIGNS AND LABELS

A. Sign size, lettering, and color shall be in accordance with NEMA Z535.4.

B. Warning labels for arc flash hazards shall be provided per NEC.

PART 3 EXECUTION

3.01 GENERAL

A. Electrical Drawings show general locations of equipment, devices, and raceway, unless specifically dimensioned. Contractor shall be responsible for actual location of equipment and devices and for proper routing and support of raceways, subject to approval of Engineer. Coordinate the conduit installation with other trades and the actual supplied equipment. Obtain information relevant to the placing of electrical work and in case of any interference with other work, proceed as directed by the Owner/Engineer and furnish all labor and materials necessary to complete the Work in an approved manner, at no additional cost to Owner/Engineer. Submit conduit layout drawings a minimum of four weeks prior to installation of raceway.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 4

B. Check approximate locations of light fixtures, switches, electrical outlets, equipment, and other electrical system components shown on Drawings for conflicts with openings, structural members, and components of other systems and equipment having fixed locations. In the event of conflicts, notify Engineer in writing. Any adjustments required in the field shall be provided at no additional cost to the Owner/Engineer.

C. Install work in accordance with NECA Standard of Installation, unless otherwise specified.

D. Keep openings in boxes and equipment closed during construction.

E. Lay out work carefully in advance. Do not cut or notch any structural member or building surface without specific approval of Engineer. Carefully perform cutting, channeling, chasing, or drilling of floors, walls, partitions, ceilings, paving, or other surfaces required for the installation, support, or anchorage of conduit, raceways, or other electrical materials and equipment. Following such work, restore surfaces to original condition.

F. Where circuits are shown as “homeruns” all necessary fittings and boxes shall be provided for a complete raceway installation.

G. Circuit layouts are not intended to show the number of fittings, or other installation details. Furnish all labor and materials necessary to install and place in satisfactory operation all power, lighting, and other electrical systems shown. Additional circuits shall be installed wherever needed to conform to the specific requirements of the approved equipment at no additional cost to the Owner.

H. Redesign of electrical or mechanical work, which is required due to the Contractor’s use of an alternate item, arrangement or equipment and/or layout other than specified herein, shall be done by the Contractor at his own expense. Redesign and detailed plans including calculations shall be submitted to the Engineer for approval. No additional compensation will be provided for changes in the work, either his own or others, caused by such redesign.

I. Surface mounted panel boxes, junction boxes, conduit, etc., shall be supported by 1/2-inch spacers to provide a clearance between wall and equipment.

J. All conduit transitions from below grade to exposed shall have housekeeping pads that extend a minimum of 6 inches above grade and extend on all sides from the edge of conduit at least 6 inches. Where next to wall or power/line poles, the conduit housekeeping pad shall only extend to the wall or pole chamfer all exposed edges, 3/4 inch, 45 degrees.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 5

K. The Contractor shall coordinate the work of the different trades so that interferences between conduits, piping, equipment, architectural and structural work will be avoided. All necessary offsets shall be furnished so as to take up a minimum space and all such offsets, fittings, etc., required to accomplish this shall be furnished and installed by the Contractor without additional expense to the Owner. In case interference develops, the Engineer is to decide which equipment, piping, etc., must be relocated, regardless of which was installed first.

L. Raceways and conductors for lighting, switches, receptacles, and other miscellaneous low voltage power and signal systems as specified are not shown on the Drawings. Raceways and conductors shall be provided as required for a complete and operating system. Homeruns, if shown on the Drawings, are to assist the Contractor in identifying raceways to be run exposed and raceways to be run concealed. Raceways shall be installed concealed in all finished spaces and may be installed exposed or concealed in all process spaces. Raceways installed exposed shall be near the ceiling or along walls of the areas through which they pass and shall be routed to avoid conflicts with HVAC ducts, cranes hoists, monorails, equipment hatches, doors, windows, etc. Raceways installed concealed shall be run in the center of concrete floor slabs, above suspended ceilings, or in partitions as required.

M. Investigate each space in the structure through which equipment must pass to reach its final location. Coordinate shipping splits with the manufacturer to permit safe handling and passage through restricted areas in the structure.

N. The equipment shall be kept upright at all times during storage and handling.

When equipment must be tilted for passage through restricted areas, brace the equipment to ensure that the tilting does not impair the functional integrity of the equipment.

O. Based on the results of arc flash calculations performed as specified in Section 26 05 70, Electrical System Analysis, provide appropriate warning labels on all electrical equipment.

P. Panels with terminations shall have minimum three feet of clearance in front of them, and the door shall swing out more than 100 degrees.

Q. Top conduit entry is prohibited, without written permission of the Engineer.

3.02 ANCHORING AND MOUNTING

A. Equipment anchoring and mounting shall be in accordance with manufacturer’s requirements for seismic zone criteria given in Section 01 88 15, Anchorage and Bracing.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 6

3.03 COMBINING CIRCUITS INTO COMMON RACEWAY

A. Homerun circuits shown on Drawings indicate functional wiring requirements for power and control circuits. Circuits may be combined into common raceways in accordance with the following requirements:

1. Follow standards contained in the Emerson OVREF1005, Version 8 Reference Guide related to combining circuits into a common raceway.

Different types of signals, including AC Power, DC Power, AC Control, DC control, and Analog shall be in separate conduits according to Table 19 in the standards, with spacing between conduits according to Table 20 in the standards.

2. Analog control circuits from devices in same general area to same destination.

a. No power or AC discrete control circuits shall be combined in same conduit with analog circuits.

b. No Class 2 or Class 3 circuits including, but not limited to, HVAC control circuits, fire alarm circuits, paging system circuits shall be combined with power or Class 1 circuits.

c. Analog circuits shall be continuous from source to destination. Do not add TJB, splice, or combine into a multi-pair cable without authorization of Engineer.

d. Raceways shall be sized per General Circuit and Raceway Schedule and do not exceed 60 percent fill.

e. Changes shall be documented on record drawings.

3. Discrete control circuits from devices in the same general area to the same destination.

a. No power or analog control circuits shall be combined in same conduit with discrete circuits.

b. No Class 2 or Class 3 circuits including, but not limited to, HVAC control circuits, fire alarm circuits, and paging system circuits shall be combined with power or Class 1 circuits.

c. Raceway shall be sized per the General Circuit and Raceway Schedule and do not exceed 60 percent fill.

d. Changes shall be documented on record drawings.

4. Power circuits from loads in same general area to same source location

(such as: panelboard, switchboard, low voltage motor control center).

a. Lighting Circuits: Combine no more than three circuits to a single raceway. Contractor shall be responsible for increasing conduit and conductor size if derating is required by NEC.

b. Receptacle Circuits, 120-Volt Only: Combine no more than three circuits to a single raceway. Provide a separate neutral conductor for each circuit. Contractor shall be responsible for increasing conduit and conductor size if derating is required by NEC.

c. All Other Power Circuits: Do not combine power circuits without authorization of Engineer.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 7

3.04 NAMEPLATES, SIGNS, AND LABELS

A. Arc Flash Protection Warning Signs:

1. Field mark switchboards, motor control centers, panelboards and disconnects to warn qualified persons of potential arc-flash hazards.

Locate marking so to be clearly visible to persons before working on energized equipment.

2. Use arc flash hazard boundary, energy level, PPE level and description, shock hazard, bolted fault current, and equipment name from study required in Section 26 05 70, Electrical Systems Analysis as basis for warning signs.

B. Equipment Nameplates:

1. Provide a nameplate to label electrical equipment including switchgear, switchboards, motor control centers, panelboards, motor starters, transformers, terminal junction boxes, disconnect switches, switches and control stations.

2. Switchgear, motor control center, transformer, and terminal junction box nameplates shall include equipment designation.

3. Disconnect switch, starter, and control station nameplates shall include name and number of equipment powered or controlled by that device.

4. Switchboard and panelboard nameplates shall include equipment designation, service voltage, and phases.

3.05 LOAD BALANCE

A. Drawings and Specifications indicate circuiting to electrical loads and distribution equipment.

B. Balance electrical load between phases as nearly as possible on switchboards, panelboards, motor control centers, and other equipment where balancing is required.

C. When loads must be reconnected to different circuits to balance phase loads, maintain accurate record of changes made, and provide circuit directory that lists final circuit arrangement.

3.06 CLEANING AND TOUCHUP PAINTING

A. Cleaning: Throughout the Work, clean interior and exterior of devices and equipment by removing debris and vacuuming.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL REQUIREMENTS

PW\DEN003\C6A18000 26 05 02 - 8

B. Touchup Paint:

1. Touchup scratches, scrapes and chips on exterior and interior surfaces of devices and equipment with finish matching type, color, and consistency and type of surface of original finish.

2. If extensive damage is done to equipment paint surfaces, refinish entire equipment in a manner that provides a finish equal to or better than factory finish, that meets requirements of Specification, and is acceptable to Engineer.

3.07 PROTECTION FOLLOWING INSTALLATION

A. Protect materials and equipment from corrosion, physical damage, and effects of moisture on insulation and contact surfaces.

B. When equipment intended for indoor installation is installed at Contractor’s convenience in areas where subject to dampness, moisture, dirt or other adverse atmosphere until completion of construction, ensure adequate protection from these atmospheres is provided and acceptable to Engineer.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL MATERIALS

PW\DEN003\C6A18000 AND METHODS

26 05 04 - 1

SECTION 26 05 04

BASIC ELECTRICAL MATERIALS AND METHODS

PART 1 GENERAL

1.01 REFERENCES

A. The following is a list of standards which may be referenced in this section:

1. ASTM International (ASTM):

a. A167, Standard Specification for Stainless and Heat-Resisting

Chromium-Nickel Steel Plate, Sheet, and Strip.

b. A1011/A1011M, Standard Specification for Steel, Sheet, and

Strip, Hot-Rolled, Carbon, Structural, High-Strength Low Alloy and High-Strength Low Alloy Formability.

c. E814, Method of Fire Tests of Through-Penetration Fire Stops.

2. Canadian Standards Association (CSA).

3. Institute of Electrical and Electronics Engineers, Inc. (IEEE): 18, Standard for Shunt Power Capacitors.

4. International Society of Automation (ISA): RP12.06.01, Wiring

Practices for Hazardous (Classified) Locations Instrumentation–Part 1:

Intrinsic Safety.

5. National Electrical Manufacturers Association (NEMA):

a. 250, Enclosures for Electrical Equipment (1,000 Volts

Maximum).

b. AB 1, Molded Case Circuit Breakers, Molded Case Switches, and

Circuit-Breaker Enclosures.

c. C12.1, Code for Electricity Metering.

d. C12.6, Phase-Shifting Devices Used in Metering, Marking and

Arrangement of Terminals.

e. CP 1, Shunt Capacitors.

f. ICS 2, Industrial Control and Systems: Controllers, Contactors, and Overload Relays Rated 600 Volts.

g. ICS 5, Industrial Control and Systems: Control Circuit and Pilot

Devices.

h. KS 1, Enclosed and Miscellaneous Distribution Switches

(600 Volts Maximum).

6. National Fire Protection Association (NFPA): 70, National Electrical

Code (NEC).

7. Underwriters Laboratories Inc. (UL):

a. 98, Standard for Enclosed and Dead-Front Switches.

b. 248, Standard for Low Voltage Fuses.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL MATERIALS

PW\DEN003\C6A18000 AND METHODS

26 05 04 - 2

c. 486E, Standard for Equipment Wiring Terminals for use with Aluminum and/or Copper Conductors.

d. 489, Standard for Molded-Case Circuit Breakers, Molded-Case Switches, and Circuit Breaker Enclosures.

e. 508, Standard for Industrial Control Equipment.

f. 810, Standard for Capacitors.

g. 943, Standard for Ground-Fault Circuit-Interrupters.

h. 1059, Standard for Terminal Blocks.

i. 1479, Fire Tests of Through-Penetration Fire Stops.

1.02 SUBMITTALS

A. Action Submittals:

1. Provide manufacturers’ data for the following:

a. Control devices.

b. Control relays.

c. Circuit breakers.

d. Fused switches.

e. Nonfused switches.

f. Timers.

g. Fuses.

h. Magnetic contactors.

i. Intrinsic safety barriers.

j. Firestopping.

k. Enclosures: Include enclosure data for products having enclosures.

1.03 EXTRA MATERIALS

A. Furnish, tag, and box for shipment and storage the following spare parts and special tools:

1. Fuses, 0 to 600 Volts: Six of each type and each current rating installed.

PART 2 PRODUCTS

2.01 MOLDED CASE CIRCUIT BREAKER THERMAL MAGNETIC, LOW

VOLTAGE

A. General:

1. Type: Molded case.

2. Trip Ratings: 15-800 amps.

3. Voltage Ratings: 120, 240, 277, 480, and 600V ac.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL MATERIALS

PW\DEN003\C6A18000 AND METHODS

26 05 04 - 3

4. Suitable for mounting and operating in any position.

5. NEMA AB 1 and UL 489.

B. Operating Mechanism:

1. Overcenter, trip-free, toggle type handle.

2. Quick-make, quick-break action.

3. Locking provisions for padlocking breaker in open position.

4. ON/OFF and TRIPPED indicating positions of operating handle.

5. Operating handle to assume a center position when tripped.

6. Shall be mounted no higher than 6 feet above finished floor.

C. Trip Mechanism:

1. Individual permanent thermal and magnetic trip elements in each pole.

2. Variable magnetic trip elements with a single continuous adjustment 3X to 10X for frames greater than 100 amps.

3. Two and three pole, common trip.

4. Automatically opens all poles when overcurrent occurs on one pole.

5. Test button on cover.

6. Calibrated for 40 degrees C ambient, unless otherwise shown.

7. Do not provide single-pole circuit breakers with handle ties where multi-pole circuit breakers are shown.

D. Short Circuit Interrupting Ratings:

1. Equal to, or greater than, available fault current or interrupting ratings shown.

2. Equal to rating of existing equipment.

3. Not less than the following RMS symmetrical currents for the indicated trip ratings:

a. Up to 100A, less than 250V ac: 10,000 amps.

b. Up to 100A, 250-600V at 14,000 amps.

c. Over 100A: 22,000 amps.

4. Series Connected Ratings: Do not apply series connected short circuit ratings in NEC 700 Emergency Systems, except where specifically shown. Where shown, provide UL listed series ratings for the specific breaker/breaker and fuse/breaker combinations.

5. Circuit breaker ratings shall match exist equipment where new breakers are added to existing equipment.

E. Ground Fault Circuit Interrupter (GFCI): Where indicated, equip breaker as specified above with ground fault sensor and rated to trip on 5-mA ground fault within 0.025 second (UL 943, Class A sensitivity, for protection of personnel).

1. Ground fault sensor shall be rated same as circuit breaker.

2. Push-to-test button.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL MATERIALS

PW\DEN003\C6A18000 AND METHODS

26 05 04 - 4

F. Equipment Ground Fault Interrupter (EGFI): Where indicated, equip breaker specified above with ground fault sensor and rated to trip on 30-mA ground fault (UL-listed for equipment ground fault protection).

G. Accessories: Shunt trip, auxiliary switches, handle lock ON devices, mechanical interlocks, key interlocks, unit mounting bases, double lugs as shown or otherwise required. Shunt trip operators shall be continuous duty rated or have coil-clearing contacts.

H. Connections:

1. Supply (line side) at either end.

2. Mechanical wire lugs, except crimp compression lugs where shown.

3. Lugs removable/replaceable for breaker frames greater than

100 amperes.

4. Suitable for 75 degrees C rated conductors without derating breaker or conductor ampacity.

I. Enclosures for Independent Mounting:

1. See Article Enclosures.

2. Service Entrance Use: Breakers in required enclosure and required accessories shall be UL 489 listed.

3. Interlock: Enclosure and switch shall interlock to prevent opening cover with switch in the ON position. Provide bypass feature for use by qualified personnel.

2.02 FUSED SWITCH, INDIVIDUAL, LOW VOLTAGE

A. UL 98 listed for use and location of installation.

B. NEMA KS 1.

C. Short Circuit Rating: 200,000 amps RMS symmetrical with Class R, Class J, or Class L fuses installed.

D. Quick-make, quick-break, motor rated, load-break, heavy-duty (HD) type with external markings clearly indicating ON/OFF positions.

E. Connections:

1. Mechanical lugs, except crimp compression lugs where shown.

2. Lugs removable/replaceable.

3. Suitable for 75 degrees C rated conductors at NEC 75 degrees C ampacity.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL MATERIALS

PW\DEN003\C6A18000 AND METHODS

26 05 04 - 5

F. Fuse Provisions:

1. 30-amp to 600-amp rated shall incorporate rejection feature to reject all fuses except Class R.

2. 601-amp rated and greater shall accept Class L fuses, unless otherwise shown.

G. Enclosures: See Article Enclosures.

H. Interlock: Enclosure and switch to prevent opening cover with switch in ON position. Provide bypass feature for use by qualified personnel.

2.03 NONFUSED SWITCH, INDIVIDUAL, LOW VOLTAGE

A. NEMA KS 1.

B. Quick-make, quick-break, motor rated, load-break, heavy-duty (HD) type with external markings clearly indicating ON/OFF positions.

C. Lugs: Suitable for use with 75 degrees C wire at NEC 75 degrees C ampacity.

D. Auxiliary Contact:

1. Operation: Make before power contacts make and break before power contacts break.

2. Contact Rating: 7,200VA make, 720VA break, at 600V, NEMA ICS 5 Designation A600.

E. Enclosures: See Article Enclosures.

F. Interlock: Enclosure and switch to prevent opening cover with switch in ON position. Provide bypass feature for use by qualified personnel.

2.04 FUSE, 250-VOLT AND 600-VOLT

A. Power Distribution, General:

1. Current-limiting, with 200,000 ampere rms interrupting rating.

2. Provide to fit mountings specified with switches.

3. UL 248.

B. Power Distribution, Ampere Ratings 1 Amp to 600 Amps:

1. Class: RK-1.

2. Type: Dual element, with time delay.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL MATERIALS

PW\DEN003\C6A18000 AND METHODS

26 05 04 - 6

3. Manufacturers and Products:

a. Bussmann; Types LPS-RK (600 volts) and LPN-RK (250 volts).

b. Littelfuse; Types LLS-RK (600 volts) and LLN-RK (250 volts).

C. Power Distribution, Ampere Ratings 601 Amps to 6,000 Amps:

1. Class: L.

2. Double O-rings and silver links.

3. Manufacturers and Products:

a. Bussmann; Type KRP-C.

b. Littelfuse, Inc.; Type KLPC.

2.05 PUSHBUTTON, INDICATING LIGHT, AND SELECTOR SWITCH

A. All devices shall be 30mm type.

B. Contact Rating: 7,200VA make, 720VA break, at 600V, NEMA ICS 5 Designation A600.

C. Selector Switch Operating Lever: Standard.

D. Indicating Light: LED, full voltage.

E. Pushbutton Color:

1. ON or START: Black.

2. OFF or STOP: Black.

F. Pushbutton and selector switch lockable in OFF position where indicated.

G. Legend Plate:

1. Material: Aluminum.

2. Engraving: Enamel filled in high contrasting color.

3. Text Arrangement: 11-character/spaces on one line, 14-character/spaces on each of two lines, as required, indicating specific function.

4. Letter Height: 7/64-inch.

H. Manufacturers and Products:

1. Heavy-Duty, Oil-Tight Type:

a. Allen-Bradley; Type 800T

b. ABB.; Type CR 104P.

c. Schneider Electric; Type K.

d. Eaton/Cutler-Hammer; Type 10250T.

GREAT LAKES WATER AUTHORITY BASIC ELECTRICAL MATERIALS

PW\DEN003\C6A18000 AND METHODS

26 05 04 - 7

2. Heavy-Duty, Watertight, and Corrosion-Resistant Type:

a. Allen-Bradley; Type 800T

b. Schneider Electric; Type SK.

c. ABB.; Type CR 104P.

d. Eaton/Cutler-Hammer; Type E34.

2.06 POTENTIOMETER, WATERTIGHT

A. Potentiometer, Watertight:

B. Three-terminal, heavy-duty NEMA 250, Type 4 construction, resolution of 1 percent and linearity of plus or minus 5 percent.

C. Single-hole, panel mounting accommodating panel thicknesses between 1/8 inch and 1/4 inch.

D. Include engraved legend plates with service markings.

E. Manufacturer and Product: Allen-Bradley; Bulletin 800T or approved equal.

2.07 TERMINAL BLOCK, 600 VOLTS

A. UL 486E and UL 1059.

B. Size components to allow insertion of necessary wire sizes.

C. Capable of termination of control circuits entering or leaving equipment, panels, or boxes.

D. Screw clamp, dead front barrier type, with current bar providing direct contact with wire between…