This is a Specifications Volume I document for Contract No. 2000970, issued by the Great Lakes Water Authority (GLWA) in Detroit, Michigan, prepared by NORESCO and Jacobs for the Rehabilitation of Screened Final Effluent (SFE) Pump Station. The project encompasses construction of a new SFE Treatment Building containing an SFE pump station with six constant-speed vertical turbine pumps (approximately 12 MGD capacity each), a Filter Room with two cloth disk filters, a Chemical Room with hypochlorite and caustic storage systems, and an Electrical Room with 15kV switchgear and transformers. Additional work includes modifications to secondary water systems in the Machine Shop Basement, installation of a sulfur dioxide carrier water pumping system at the Dechlorination Facility, a backup sodium hypochlorite feed system in the Hypochlorite Building, and quench water booster pumps in Complex II Incineration. Work is restricted to Monday through Friday, 7 a.m. to 5 p.m., excluding GLWA holidays, with specific restrictions on Secondary Effluent Conduit shutdowns limited to November 15 through March 15. The contract is organized into five construction stages with specific milestones, and work must coordinate extensively with GLWA's continuous 24-hour operations through detailed shutdown planning, Equipment Shutdown Request forms, and Maintenance of Plant Operations Plans.
The specifications detail comprehensive requirements for submittals including a Schedule of Values, progress payment applications, and detailed coordination procedures with Owner operations. Progress payments are structured with specific intermediate steps for equipment acceptance, including delivery, installation, performance acceptance testing, demonstration and training, system checkout, and operational availability demonstrations. The Schedule of Values must allocate costs by specification section and work area, with mobilization limited to three percent of the Contract Price and costs for operations and maintenance manuals and training apportioned at four percent of equipment cost. Asset Turnover Process requirements total one percent of contract value, and Record Document Turnover is valued at 0.5 percent of contract value. All work must maintain GLWA facility integrity, comply with Michigan Public Act 174 regarding underground facility damage prevention, and include detailed record documents, photographic documentation, and final training of operations and maintenance personnel prior to substantial completion.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I s s u e d f or P e r m it
Rehabilitation of Screened Final Effluent Pump Station
Contract No. 2000970
NORESCO for the Great Lakes Water Authority
Volume I of IV
Specifications
May 2025
Prepared By:
NORESCO FOR THE GREAT LAKES WATER AUTHORITY
DETROIT, MICHIGAN
BIDDING REQUIREMENTS
AND
CONTRACT DOCUMENTS
for the construction of the
REHABILITATION OF SCREENED FINAL EFFLUENT PUMP STATION
Contract Number: 2000970
JACOBS
Bingham Farms, Michigan
May 2025
© Jacobs 2025. All rights reserved.
This document and the ideas and designs incorporated herein, as an instrument of professional service, is the property of Jacobs and is not to be used in whole or part, for any other project without the written authorization of Jacobs.
Project No. C6A18000
PROJECT NUMBER 2000970 REHABILITATION OF THE SFE PUMP STATION
MAY 2025 GLWA WRRF
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - i
TABLE OF CONTENTS
Pages
VOLUME I
PART 1—PROCUREMENT REQUIREMENTS (Not in this Submittal)
PART 2—CONTRACTING REQUIREMENTS (Not in this Submittal)
PART 3—SPECIFICATIONS
DIVISION 01—GENERAL REQUIREMENTS
01 11 00 Summary of Work.................................................................... 1- 4 01 14 00 Work Restrictions .................................................................... 1- 9 01 14 16 Coordination with Owner's Operations .................................... 1- 18 01 21 00 Allowances ............................................................................... 1- 3 01 22 01 Measurement and Payment ...................................................... 1- 5 01 25 00 Substitution Procedures ........................................................... 1- 4 01 26 13 Requests for Interpretation (RFI) Procedures .......................... 1- 3 01 26 13A Requests for Interpretation (RFI) Form ................................... 1- 1 01 29 73 Schedule of Values .................................................................. 1- 7 01 29 76 Progress Payment Procedures .................................................. 1- 5 01 31 13 Project Coordination ................................................................ 1- 5 01 31 19.13 Pre-Construction Conference ................................................... 1- 6 01 31 19.23 Progress Meetings .................................................................... 1- 3 01 31 26 Electronic Communication Protocols ...................................... 1- 6 01 32 16.20 Construction Progress Schedule .............................................. 1- 14 01 32 26 Construction Progress Reporting ............................................. 1- 2 01 32 33 Photographic Documentation................................................... 1- 6 01 33 00 Submittal Procedures ............................................................... 1- 13 01 33 30 Asset Turnover Process Requirements .................................... 1- 11 01 35 23 Owner's Safety Requirements .................................................. 1- 10 01 35 23.A GLWA Hot Works Permit ....................................................... 1- 2 01 35 23.B GLWA Confined Space Permit ............................................... 1- 2 01 35 53 Security .................................................................................... 1- 6 01 42 00 References ................................................................................ 1- 18 01 45 33 Special Inspection, Observation, and Testing .......................... 1- 6
Fabricator’s Certificate of Compliance .................................... 1- 1 Statement of Special Inspections ............................................. 1- 3 2015 IBC Tables ...................................................................... 1- 25
01 46 01 Quality Requirements .............................................................. 1- 9 01 51 00 Temporary Utilities .................................................................. 1- 9 01 51 41 Temporary Pumping ................................................................ 1- 7
Pages
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - ii
01 52 13 Field Offices and Sheds ............................................................ 1- 8 01 55 00 Vehicular Access and Parking .................................................. 1- 5 01 55 26 Maintenance and Protection of Traffic ..................................... 1- 4 01 57 00 Temporary Controls ................................................................. 1- 12 01 58 13 Temporary Project Signage ...................................................... 1- 4 01 61 00 Common Product Requirements .............................................. 1- 7
Manufacturer’s Certificate of Compliance ............................... 1- 1 01 66 00 Product Storage and Handling Requirements .......................... 1- 6 01 71 13 Mobilization ............................................................................. 1- 2 01 71 16 Acceptance of Conditions ........................................................ 1- 2 01 71 23 Field Engineering ..................................................................... 1- 9 01 71 33 Protection of Work and Property .............................................. 1- 6 01 73 19 Installation ................................................................................ 1- 5 01 73 29 Cutting and Patching ................................................................ 1- 8 01 74 13 Progress Cleaning ..................................................................... 1- 4 01 74 19 Construction Waste Management and Disposal ....................... 1- 4 01 74 23 Final Cleaning .......................................................................... 1- 4 01 75 11 Checkout and Startup Procedures ............................................. 1- 6 01 77 19 Closeout Requirements ............................................................. 1- 6 01 78 23 Operation and Maintenance Data ............................................. 1- 10 01 78 39 Project Record Documents ....................................................... 1- 8 01 78 40 OnBase Digital Document Turnover ........................................ 1- 18 01 78 43 Spare Parts ................................................................................ 1- 4 01 79 23 Instruction of Operation and Maintenance Personnel .............. 1- 16 01 88 15 Anchorage and Bracing ............................................................ 1- 5 01 91 00 Commissioning ......................................................................... 1- 16
DIVISION 02—EXISTING CONDITIONS
02 41 00 Demolition ................................................................................ 1- 7 02 61 00 Removal and Disposal of Contaminated Soil ........................... 1- 8
DIVISION 03—CONCRETE
03 30 10 Structural Concrete ................................................................... 1- 27 Concrete Mix Design, Class 5000F2S1P1C1 ........................... 1- 3 Concrete Mix Design, Class 4500F1S1P0C1 ........................... 1- 2 Concrete Mix Design, Class CF00F0S1P0C1 .......................... 1- 2
03 40 00 Precast Concrete ....................................................................... 1- 5 03 62 00 Grouting .................................................................................... 1- 7
24-hour Evaluation of Nonshrink Grout Test Form and Grout Testing Procedures .................................................. 1- 3
Pages
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - iii
DIVISION 04—MASONRY
04 21 13.13 Masonry Veneer ....................................................................... 1- 12 04 22 00 Concrete Unit Masonry ............................................................ 1- 13
DIVISION 05—METALS
05 05 19 Post-Installed Anchors ............................................................. 1- 9 05 05 23 Welding .................................................................................... 1- 6
Welding and Nondestructive Testing Table ............................ 1- 1 05 12 00 Structural Steel Framing .......................................................... 1- 12 05 31 00 Steel Decking ........................................................................... 1- 6 05 50 00 Metal Fabrications ................................................................... 1- 18 05 52 16 Aluminum Railings .................................................................. 1- 8 05 53 00 Metal Gratings ......................................................................... 1- 5
DIVISION 06—WOOD, PLASTICS, AND COMPOSITES
06 82 00 Glass-Fiber-Reinforced Plastic ................................................ 1- 10
DIVISION 07—THERMAL AND MOISTURE PROTECTION
07 21 01 Thermal Insulation ................................................................... 1- 2 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing ........................ 1- 9 07 62 00 Sheet Metal Flashing and Trim ................................................ 1- 8 07 70 01 Roof Specialties and Accessories ............................................ 1- 5 07 92 01 Sealants and Caulking .............................................................. 1- 2 07 95 13 Expansion Joint Cover Assemblies .......................................... 1- 3
DIVISION 08—OPENINGS
08 11 16 Aluminum Doors and Frames .................................................. 1- 3
08 45 00 Translucent Wall Assemblies .................................................. 1- 8 08 71 00 Door Hardware......................................................................... 1- 11
DIVISION 09—FINISHES
09 81 10 Pipe Joint Coating—Weld After Backfill ................................ 1- 7 09 81 12 Pipe Joint Coating—Weld Before Backfill.............................. 1- 6 09 90 00 Painting and Coating ................................................................ 1- 26 09 90 05 Pipeline Polyurethane Coating ................................................. 1- 14 09 96 35 Chemical-Resistant Coatings ................................................... 1- 16
Chemical-Resistant Coating System Data Sheet (CRCSDS) .. 1- 1 Chemical-Resistant Coating Product Data Sheet (CRCPDS). . 1- 1
09 97 13.01 Pipeline Tape Coating .............................................................. 1- 12
Pages
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - iv
DIVISION 10—SPECIALTIES
10 44 00 Fire Protection Specialties and Safety Equipment ................... 1- 4 10 73 13 Awnings .................................................................................... 1- 3
DIVISION 11 THROUGH DIVISION 20 (NOT USED)
DIVISION 21—FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems ..................................................... 1- 17
DIVISION 22—PLUMBING
22 07 00 Building Mechanical Thermal Insulation ................................. 1- 6 22 10 01 Plumbing Piping and Accessories ............................................ 1- 15 22 10 01.02 Polyvinyl Chloride Drain Waste and Vent (PVC-DWV)
Pipe and Fittings ....................................................................... 1- 1 22 30 00 Plumbing Equipment ................................................................ 1- 5
Instantaneous Water Heater ...................................................... 1- 1 Backflow Preventers ................................................................. 1- 1 Simplex, Submersible Pumps ................................................... 1- 1
22 40 00 Plumbing Fixtures .................................................................... 1- 7
DIVISION 23—HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 05 93 Testing, Adjusting, and Balancing for HVAC ......................... 1- 6 23 07 00 HVAC Insulation ...................................................................... 1- 8 23 09 00 Instrumentation and Control Devices for HVAC ..................... 1- 15 23 09 00.01 Open Temperature Control System .......................................... 1- 30 23 09 13 HVAC Controls, Field Components, and Instruments ............. 1- 8 23 09 40 Master Systems Integration Services (For Reference .............. 1- 28 23 09 94 Sequences of Operation for HVAC Controls ........................... 1- 19 23 31 13 Metal Ducts and Accessories ................................................... 1- 21 23 31 13.01 Ductwork Schedule .................................................................. 1- 2 23 31 16.16 Thermoset Fiberglass-Reinforced Plastic Ducts and Accessories ........................................................................ 1- 9 23 34 00 HVAC Fans .............................................................................. 1- 13 23 37 00 Air Outlets and Inlets ............................................................... 1- 3
Supplement: Air Outlets and Inlets .......................................... 1- 1 23 77 00 Air Handling Units ................................................................... 1- 29 23 81 00 Unitary Air-Conditioning Equipment ...................................... 1- 13 23 82 00 Terminal Heating and Cooling Units ....................................... 1- 6
DIVISION 24 THROUGH DIVISION 25 (NOT USED)
Pages
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - v
VOLUME II
DIVISION 26—ELECTRICAL
26 05 02 Basic Electrical Requirements ................................................. 1- 8 26 05 04 Basic Electrical Materials and Methods .................................. 1- 16 26 05 05 Conductors ............................................................................... 1- 18 26 05 26 Grounding and Bonding for Electrical Systems ...................... 1- 6 26 05 33 Raceway and Boxes ................................................................. 1- 29 26 05 70 Electrical Systems Analysis ..................................................... 1- 9
Figure 1: Example Arc Flash Label ......................................... 1- 1 26 08 00 Commissioning of Electrical Systems ..................................... 1- 28 26 09 13 Power Measurement and Control............................................. 1- 6 26 12 13 Medium-Voltage Liquid Fill Substation Transformers ........... 1- 11 26 13 13 Medium-Voltage Circuit Breaker Switchgear ......................... 1- 21 26 18 39 Medium-Voltage Motor Control .............................................. 1- 11 26 19 00 Medium-Voltage Induction Motors ......................................... 1- 17
Medium Voltage Induction Motors Data Sheet ....................... 1- 2 26 20 00 Low-Voltage AC Induction Motors ......................................... 1- 13 26 22 00 Low-Voltage Transformers ...................................................... 1- 4 26 24 16 Panelboards .............................................................................. 1- 7 26 24 19 Low-Voltage Motor Control .................................................... 1- 10 26 27 26 Wiring Devices ........................................................................ 1- 9 26 29 23 Low-Voltage Adjustable Frequency Drive System ................. 1- 12 26 41 00 Facility Lightning Protection ................................................... 1- 6 26 43 00 Surge Protective Devices (SPD) .............................................. 1- 4 26 50 00 Lighting .................................................................................... 1- 12
DIVISION 27 THROUGH 30 (NOT USED)
DIVISION 31—EARTHWORK
31 09 13 Geotechnical Instrumentation and Monitoring ........................ 1- 12 31 10 13 Site Preparation ........................................................................ 1- 4 31 14 00 Earth Stripping and Stockpiling ............................................... 1- 4 31 20 00 Earth Moving ........................................................................... 1- 16 31 22 00 Grading .................................................................................... 1- 12 31 23 03 Excavation and Fill for Utilities ............................................... 1- 22 31 23 13 Subgrade Preparation ............................................................... 1- 3 31 23 19.01 Dewatering ............................................................................... 1- 8 31 23 23 Fill and Backfill ....................................................................... 1- 9 31 40 00 Tunneled Crossings .................................................................. 1- 8 31 41 00 Shoring for Trenchless Construction ....................................... 1- 2 31 43 00 Steel Casing Pipe ..................................................................... 1- 3
Pages
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - vi
31 44 00 Settlement Monitoring for Trenchless Construction ................ 1- 9 31 45 00 Installation of Carrier Pipe in Steel Casing .............................. 1- 5 31 46 00 Backfill Grouting ...................................................................... 1- 11 31 50 00 Temporary Earth Retaining Systems ........................................ 1- 6
DIVISION 32—EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base and Subbase Courses ...................................... 1- 6 32 13 13 Concrete Paving ....................................................................... 1- 17 32 16 00 Curbs and Gutters ..................................................................... 1- 5 32 17 23 Pavement Markings .................................................................. 1- 5 32 31 13 Chain Link Fences and Gates ................................................... 1- 12 32 62 16 Steel Piles ................................................................................. 1- 15 32 92 00 Plants ........................................................................................ 1- 8
DIVISION 33—UTILITIES
33 05 01 Conveyance Piping—General .................................................. 1- 9 33 05 01.01 Welded Steel Pipe and Fittings ................................................ 1- 27 33 05 01.02 Ductile Iron Pipe and Fittings .................................................. 1- 10 33 05 01.07 Low-Head Reinforces Concrete Culvert, Storm Drain, and
Sewer Pipe (ASTM C361 Modified)........................................ 1- 6 33 05 01.10 High-Density Polyethylene (HDPE) Pressure Pipe and Fittings ............................................................................... 1- 9 33 05 13 Manholes .................................................................................. 1- 11 33 05 16.13 Precast Concrete Utility Structure ............................................ 1- 5 33 05 23 Guided Auger Boring ............................................................... 1- 11 33 13 00 Disinfection of Water Utility Distribution Facilities ................ 1- 5
DIVISION 34 THROUGH 39 (NOT USED)
DIVISION 40—PROCESS INTERCONNECTIONS
40 05 15 Piping Support Systems ............................................................ 1- 11 Table 1: Nonchemical Areas .................................................... 1- 1 Table 2: Chemical Areas .......................................................... 1- 1
40 05 33 Pipe Heat Tracing ..................................................................... 1- 5 40 27 00 Process Piping—General .......................................................... 1- 24 40 27 00.01 Cement-Mortar, Glass and Ceramic-Epoxy-Lined
Ductile Iron Pipe and Fittings .................................................. 1- 3 40 27 00.03 Carbon Steel Pipe and Fittings—General Service ................... 1- 5 40 27 00.07 Galvanized Steel Pipe and Malleable Iron Fittings .................. 1- 3 40 27 00.08 Stainless Steel Pipe and Fittings General Service .................... 1- 3 40 27 00.11 Chlorinated Polyvinyl Chloride (CPVC) Pipe and Fittings ..... 1- 2
Pages
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - vii
40 27 00.13 Copper and Copper Alloy Pipe Tubing and Fittings ............... 1- 1 40 27 00.15 Double Wall Containment Piping ............................................ 1- 1 40 27 01 Process Piping Specialties........................................................ 1- 15 40 27 02 Process Valves and Operators .................................................. 1- 31
Electric Actuated Valve Schedule ........................................... 1- 4 Self-Regulated Valve Schedule ............................................... 1- 1
40 42 13 Process Piping Insulation ......................................................... 1- 7 Service and Insulation Thickness Table .................................. 1- 1
40 80 01 Process Piping Leakage Testing .............................................. 1- 6 40 90 00 Instrumentation and Control for Process Systems ................... 1- 37
Component Specifications ....................................................... 1- 22 Instrument List ......................................................................... 1- 8 Loop Specifications ................................................................. 1- 19 Loop Status Report .................................................................. 1- 1 Instrument Calibration Sheet ................................................... 1- 1 I&C Valve Adjustment Sheet .................................................. 1- 1 Performance Acceptance Test Sheet ........................................ 1- 1
40 95 80 Fiber Optic Communication System ........................................ 1- 29 As-Built Fiber Optic Cable Installation Form ......................... 1- 2 As-Built Conduit/Innerduct Installation Form ......................... 1- 1
DIVISION 41—MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.13 Overhead Standing Bridge Cranes ........................................... 1- 10 Crane Data Sheet, System No. 1 .............................................. 1- 1
41 22 23.19 Monorail Hoists ....................................................................... 1- 8 Hoist/Monorail Data Sheet, System No. 1 ............................... 1- 1
DIVISION 42—PROCESS HEATING, COOLING, AND DRYING EQUIPMENT
(NOT USED)
DIVISION 43—PROCESS GAS AND LIQUID HANDLING, PURIFICATION,
AND STORAGE EQUIPMENT
43 40 02 Fiberglass Reinforced Plastic Tank ......................................... 1- 8 FRP Tank Schedule.................................................................. 1- 1 Tank Data Sheets ..................................................................... 1- 2
Pages
GREAT LAKES WATER AUTHORITY TABLE OF CONTENTS
PW\DEN003\C6A18000 00 01 10 - viii
DIVISION 44—POLLUTION AND WASTE CONTROL EQUIPMENT
44 42 56.02 Horizontal Split-Case Centrifugal Pumps ................................ 1- 8 Horizontal Split-Case Centrifugal Pump Data Sheet ............... 1- 3
44 42 56.03 Vertical Turbine Pumps ............................................................ 1- 10 SFE Pump Data Sheet .............................................................. 1- 3 LPSW Pump Data Sheet ........................................................... 1- 3
44 42 56.10 Horizontal End Suction Self-Priming Centrifugal Pumps .................................................................... 1- 10 SO2 Carrier Water Pumps Data Sheet ..................................... 1- 2
44 42 56.11 Horizontal End Suction Centrifugal Pumps ............................. 1- 6 Horizontal End Suction Centrifugal Pump Data Sheet – Quench Water Booster Pump. ..................................... 1- 2
44 42 56.16 Peristaltic Metering Pump ........................................................ 1- 6 Peristaltic Hose Pump Data Sheet ............................................ 1- 6
44 42 56.18 Flexibly Coupled Vertical Inline Centrifugal Pump ................ 1- 6 Flexibly Coupled Vertical Inline Centrifugal Pump Data Sheet – Intermediate Pressure Secondary Water Booster Pump ........... 1- 2 Flexibly Coupled Vertical Inline Centrifugal Pump Data Sheet – Quench Water Booster Pump ................................................... 1- 2
44 43 33 Motorized Automatic Strainer .................................................. 1- 7
DIVISION 45—INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT (NOT
USED)
DIVISION 46—WATER AND WASTEWATER EQUIPMENT
46 61 46 Disk Filter Equipment .............................................................. 1- 16
DIVISION 47 THROUGH 49 (NOT USED)
VOLUME III—DRAWINGS (BOUND SEPARATELY)
VOLUME IV—STANDARD DETAILS (BOUND SEPARATELY)
END OF SECTION
PART 1
PROCUREMENT REQUIREMENTS
PART 2
CONTRACTING REQUIREMENTS
PART 3
SPECIFICATIONS
GREAT LAKES WATER AUTHORITY SUMMARY OF WORK
PW\DEN003\C6A18000 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 WORK COVERED BY CONTRACT DOCUMENTS
A. The completed Work will provide Owner with a new Screened Final Effluent (SFE) Pump Station and Treatment Facility, modifications to the low-, intermediate-and high-pressure secondary water systems in the Machine Shop Basement, a new carrier water supply for the sulfur dioxide system at the Dechlorination Facility, a backup sodium hypochlorite feed system in the Hypochlorite Building and new quench water booster pumps in Complex II Incineration.
B. The Work includes:
1. SFE Treatment Building:
a. The work will include construction of a new SFE Treatment
Building, which will include an SFE pump station, Filter Room, Chemical Room and Electrical Room.
b. The SFE pump station will be constructed on top of the existing secondary effluent conduit and will require construction of a 5-foot thick concrete slab on top of the conduit. Coring of the secondary effluent conduit roof slab for SFE pump openings will require the isolation and shutdown of the East and West Conduits at separate times during construction.
c. The pump station will include six constant-speed, vertical turbine pumps, with a capacity of about 12 MGD each, and space for two future pumps of the same size. Each pump will have a strainer for removing larger debris from the secondary effluent. Backwash water will be returned to the secondary effluent channel.
d. Two 36-inch SFE header pipes on the East and West side of the pump station will exit the station and combine to a 54-inch pipe.
The 54-inch pipe will connect to the existing 60-inch SFE pipe near the existing SFE Pump Station.
e. The Filter Room will include two cloth disk filters for treatment of the SFE to a water quality that will make the water suitable for use in the WRRF’s low pressure secondary water system. Filter influent water will come from each of the SFE header pipes in the pump station. Pressure reducing valves will be included on the lines from each header. Filter effluent will be routed to the Filtered Water Storage Tank located beneath the Filter Room.
Hypochlorite and caustic solutions will be added to the filtered effluent water before the FWST to make the treated water chemically suitable for the LPSW distribution system. Filter backwash from each filter will be routed to drain.
GREAT LAKES WATER AUTHORITY SUMMARY OF WORK
PW\DEN003\C6A18000 01 11 00 - 2
f. The Filter Room will include three variable speed, vertical turbine LPSW pumps, with a capacity of about 1,700 gpm each. The pumps will pump LPSW (treated effluent) from the FWST through an 18-inch pipe to the secondary water pump room in the Machine Shop Basement.
g. The Filter Room will have a potable water feed line, which will provide backup water supply to the LPSW system. The potable water will go through reduced pressure zone backflow preventers, making the water non-potable water. One non-potable water line will provide supplemental water to the FWST to supplement the production of LPSW from the filters, if needed. Another non-potable water connection, together with a pressure control valve, will provide complete backup LPSW supply if the LPSW pumps are out of service.
h. The Chemical Room will include a hypochlorite storage tank and feed system and a caustic storage tank and feed system, with in-ground chemical containment. A chemical unloading system for tanker trucks to unload into the chemical storage tanks is provided just outside the Chemical Room.
i. Electrical power will come from 13.8kV power feeds that originate from EB-1. These feeds will be spliced at the existing EB-3 so that the existing cable from EB-1 to EB-3 will be reused and new cable will be provided for the section from EB-3 to the new 3750kW transformers.
j. The Electrical Room will include electrical equipment of a 15kV switchgear, medium voltage pump starters, 480 MCC, and other various electrical equipment. A separate Ovation Room will be provided for Ovation equipment and an Information Technology Room. Two 5000KVA transformers will reduce the incoming voltage from 13.8kV to 4800V. Another two 750KVA transformers will reduce the 4800V to 480V. These transformers will be located in a fenced area outside the Electrical Room. A vault will be provided under the transformers for routing cable.
k. Yard piping around the SFE Pump Station will include:
1) SFE piping (36-in. and 54-in.) from the new SFE PS to the existing 60-inch connection near the existing SFE PS;
2) A potable water line (16 in.) from immediately downstream of Meter Pit C to the new SFE PS;
3) A LPSW line (18-in.) from the new SFE PS to the Machine
Shop Basement;
4) Natural gas from a gas line running down Jefferson Avenue;
5) Stormwater and building drainage piping to MH-333; and
6) Relocated secondary water piping.
GREAT LAKES WATER AUTHORITY SUMMARY OF WORK
PW\DEN003\C6A18000 01 11 00 - 3
l. Sitework around the SFE Treatment Building will include pavement restoration around the SFE Treatment Building and in locations where the yard piping will disturb existing pavement.
Sitework will also include soil erosion control and various traffic related items.
2. Machine Shop Basement Secondary Water Modifications:
a. The work in the existing secondary water room in the Machine
Shop Basement will include piping modifications to incorporate the LPSW from the new SFE PS into the existing LPSW plant distribution system. Two intermediate pressure secondary water (IPSW) booster pumps will be added to the secondary water room to boost the LPSW up to intermediate pressure. Two high pressure secondary water (HPSW) booster pumps will replace two of the three existing HPSW pumps and pump non-potable water from the existing break tanks into the HPSW system. As a backup to potable water, LPSW will fill the break tank and be boosted to high pressure using the same HPSW pumps.
b. Work in the Complex I Dewatering basement will provide a backup water source. A connection with a pressure reducing valve from the HPSW system to the LPWS will be provided.
3. Sulfur Dioxide Carrier Water in Dechlorination Facility:
a. The work at the Dechlorination Facility will include construction of a carrier water pumping system that will pump chlorinated secondary effluent (referred to as DRO) water from the DRO access shaft to a new connection with potable water (as backup water supply) located in the existing Maintenance Room. The carrier water pumps and strainers will be housed in a new SO2 Carrier Water Pump Building located near the DRO access shaft.
A DRO line will be constructed from the SO2 Carrier Water Pump Building, through the Sulfur Dioxide Tanker Car Building, to the Maintenance Area.
b. Site work near the Dechlorination Facility will include connection of a new water line from the existing 24-inch water line to the break tank to serve as a backup for DRO water. Site work will include installation of relocated storm piping around the SO2 Carrier Water Pump Building and rerouted sanitary force main between the Dechlorination and Chlorination Facilities. Site work will include pavement restoration of affected areas.
GREAT LAKES WATER AUTHORITY SUMMARY OF WORK
PW\DEN003\C6A18000 01 11 00 - 4
4. Backup Hypochlorite Feed System: Work in the Hypochlorite Building will provide a backup disinfection system to the existing chlorine solution. Work will include the addition of two variable-speed feed pumps that will tap into existing hypochlorite piping in the Building.
The discharge piping will be routed to and tap into one of the three existing chlorine solution lines. A connection to the existing Secondary Water and SFE piping will be provided for mixing of the hypochlorite at the point of injection and as a flushing line for the hypochlorite discharge piping.
5. Quench Water Booster Pumps in Complex II Incineration: Work in Complex II Incineration will provide booster pumps for the incinerator quench water system. Piping modifications will be provided to incorporate the pumps into the existing piping system of each incinerator.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
APRIL 2025 GLWA WRRF
GREAT LAKES WATER AUTHORITY WORK RESTRICTIONS
MS REV 0.0 01 14 00
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. General Requirements.
2. Time Restrictions for Performing Work.
3. GLWA Observed Holidays and Excused Days of the Year.
4. Prohibited Activities.
5. Contractor’s Use of site.
6. Easements and Rights-of-way.
7. Notices to Owner’s and Authorities of Properties Adjacent to the Work.
8. Site Use Constraints.
9. Construction Constraints.
B. Related Sections:
1. Section 01 11 00, Summary of Work.
2. Section 01 14 16, Coordination with Owner’s Operation.
3. Section 01 51 00, Temporary Utilities.
4. Section 01 55 00, Vehicular Access and Parking.
1.02 SUBMITTALS
A. Informational Submittals: Submit the following:
1. Pre-use elevator inspection report(s): detailing pre-use condition of Owner’s elevator(s) proposed for use by Contractor.
2. Post-use elevator inspection report(s): detailing any recommended repair or rehabilitation work needed to return elevator to pre-use condition.
3. Required notices to owner’s and authorities of adjacent properties when needing to obstruct access or interrupt utilities.
1.03 GENERAL REQUIREMENTS
A. Contractor shall adhere to the work restrictions, limitations, and constraints specified in this section of the Contract Documents.
APRIL 2025 GLWA WRRF
B. Contractor shall satisfactorily complete the Work of the Contract Documents within the specified Contract Times given the work restrictions, limitations and constraints specified in this section of the Contract Documents.
C. Contractor shall allow for the work restrictions, limitations and constraints specified herein and show its plan for conforming to these on its critical path schedule for completing the Work of this Contract within the specified Contract Time.
D. Contractor shall employ sufficient labor, equipment, materials, temporary facilities, tools, incidentals to make sure that the Work executed by the Contractor does not violate the work restrictions, limitations and constraints placed on the Contractor.
1.04 TIME RESTRICTIONS FOR PERFORMING WORK
A. Contractor shall restrict work at the site and deliveries of products, equipment, etc. to the site to Monday through Friday, excluding the GLWA observed holidays noted in Article
1.05 below, between the hours of 7 a.m. and 5 p.m. eastern standard time, unless otherwise approved by GLWA in writing. No Saturday or Sunday work is allowed.
B. Owner and Engineer are aware that it may be necessary to schedule and conduct work outside of the normal working hours and/or days to minimize equipment and system shutdown durations and thereby minimize risk to GLWA’s operations that such shutdowns pose. Noted exceptions to these allowable working days and hours, if any, are specified in this Specification section. When working days and hours outside of the specified allowable working days and times are specified, the Contractor shall provide its labor, equipment, materials, tools, and incidentals in every respect needed to execute the
Work at no additional cost.
C. Unnoted exceptions to these restrictions will be handled on a case-by-case basis by review and approval from the Engineer and GLWA.
1. The Contractor shall receive written authorization from the Engineer and GLWA before working on site outside of the days and times noted.
1.05 GLWA OBSERVED HOLIDAY AND EXCUSED DAYS OF THE
YEAR
A. GLWA observes the following holidays and excused days throughout the year:
1. New Year’s Eve.
2. New Year’s Day.
3. Birthday of Martin Luther King Jr.
4. Good Friday.
5. Memorial Day.
6. Independence Day.
7. Labor Day.
8. Veteran’s Day.
APRIL 2025 GLWA WRRF
9. Thanksgiving Day.
10. The day after Thanksgiving Day.
11. Christmas Eve.
12. Christmas Day.
B. If one or more of the GLWA holiday or excused days specified above falls on a weekend, then GLWA observes those during the preceding or following Monday through Friday work week. Contractor shall coordinate with the Contracting Officer at the beginning and throughout the duration of the Contract to specifically identify GLWA’s observed holiday and excused days and plan Work at site accordingly.
1.06 PROHIBITED ACTIVITIES
A. The Contractor shall not conduct and shall prevent its employees and that of its subcontractors, suppliers, vendors, specialists, consultants, agents, etc. from conducting the following activities at the site:
1. Use of alcohol, cannabis products, and illegal drugs.
2. Smoking, including but not limited to e-cigarettes and vaping.
3. Use of tobacco products, including but not limited to chewing tobacco.
4. Spitting or otherwise ejecting saliva from the mouth except inside the Contractor’s own rest room facilities.
5. Loud or abusive language.
6. Intimidating behavior.
1.07 CONTRACTOR'S USE OF SITE
A. Limit use of premises at the site to work areas shown or indicated on the Drawings and as specified in this section.
1. Access to site, access roads, and parking areas: Refer to Section 01 55 00, Vehicular
Access and Parking.
B. Safe access to the GLWA’s facilities at the site shall be maintained during the duration of the Project.
1. When GLWA employee, pedestrian or vehicle access through a construction area must be disrupted, coordinate with Contracting Officer to provide alternate access for the GLWA and/or other contractors as approved by the Contracting Officer.
C. Use of Existing Buildings and Structures: Maintain existing buildings and structures in weather-tight condition throughout construction unless otherwise indicated in the
Contract Documents. Protect buildings, structures, and occupants during construction.
1. Use of Existing Utilities, Sanitary Facilities, and First-aid Facilities:
a. Refer to Section 01 51 00, Temporary Utilities.
APRIL 2025 GLWA WRRF
b. GLWA’s facilities, including but not limited to: the rest rooms, lunch rooms, bathrooms, break areas, offices, copy rooms, office facilities, kitchens, and parking lots shall not be used by the Contractor, unless otherwise indicated in the Contract Documents, or as expressed in writing by the Engineer or
Contracting Officer.
2. Use of Existing Elevators:
a. Contractor may use Owner’s freight elevators indicated below for moving materials and equipment during construction under the following conditions:
1) Contractor shall provide pre-use and post-use inspections of proposed elevator by an independent licensed elevator service company and pay for any post-use repairs/rehabilitation recommended by said elevator service company as a result of Contractor’s use.
2) Elevators shall be available to Owner at all times unless otherwise arranged with Owner and Engineer.
3) Do not load elevator beyond posted capacity. Use of other elevators is not allowed.
4) Elevators within the Incinerator Complex.
3. Use of Existing Hoisting Equipment and Access to Work Areas for Loading:
a. Contractor may use the hoisting equipment and access ways as indicated below for moving materials and equipment during construction, but only Owner’s personnel shall operate the Owner’s equipment, as directed by Contractor.
Contractor shall coordinate with Owner to provide labor for operating Owner’s equipment.
1) Contractor shall be responsible for verifying hoisting equipment capacity and shall not load hoisting equipment beyond posted capacity.
a) If not posted, Contractor shall hire an independent hoisting equipment inspection company to establish the allowable capacity of the hoisting equipment prior to use.
2) Equipment located within the Incinerator Complex.
D. Contractor shall not perform any work which affects the operation or maintenance of
GLWA’s facilities without written approval of Contractor’s Shutdown Planning
Submittal and Equipment Shutdown Request (ESR), see Section 01 14 16, Coordination with Owner’s Operation, for details.
1. GLWA will operate its existing equipment, valves, etc. to isolate and take equipment out of service so that the Contractor is able to replace equipment, etc. as shown and specified and execute the Work of the Contract.
APRIL 2025 GLWA WRRF
2. Contractor shall not operate GLWA’s equipment, valves, systems, controls, etc.
unless specified elsewhere in the Contract documents or without GLWA’s written approval.
E. Do not use the site for operations other than those required for the Project.
F. Move stored materials and equipment that interfere with operations of Owner, other contractors, and others performing work for Owner. Owner shall have final say on relocations if affected parties cannot agree.
G. Promptly repair damage to premises caused by construction operations.
1. If damage impacts operations, repairs shall commence immediately and be expedited at no additional cost to GLWA.
2. If damage does not impact operations, repairs shall commence promptly and not exceed two weeks unless otherwise approved by GLWA.
H. Upon completion of the Work, restore premises to specified condition; if condition is not specified, restore to pre-construction condition.
1.08 EASEMENTS AND RIGHTS-OF-WAY
A. General:
1. Easements and rights-of-way required for the permanent improvements included in the Work will be provided by Owner.
2. Confine construction operations within Owner’s property, public rights-of-way, easements obtained by Owner, and limits shown, and property for which Contractor has made arrangements directly with property owner(s).
3. Use care in placing construction tools, equipment, excavated materials, and materials and equipment to be incorporated into the Work to avoid damaging property and interfering with traffic.
4. Do not enter private property outside the construction limits without permission from the owner of the property.
5. Contractor shall be advised of the existence of a railroad right-of-way adjacent to the
SFE Building project site. The right-of-way limits are the two fence lines parallel to the centerline of the tracks. Where the fences are absent, the limit of the right-of-way is an extension of the existing fencing. Contractor shall not enter into, or do work in that area, without specific permission from GLWA. For convenience, the area in question is delineated pictorially in Attachment 1.
APRIL 2025 GLWA WRRF
1.09 NOTICES TO OWNERS AND AUTHORITIES OF PROPERTIES
ADJACENT TO THE WORK
A. Notify owners of adjacent property and utility owners when prosecution of the Work may affect their property, facilities, or use of property.
B. When it is necessary to temporarily obstruct access to property, or when utility service connection will be interrupted, provide notices sufficiently in advance to enable affected persons to provide for their needs. Such notifications shall comply with laws and regulations, be delivered in writing, and shall include appropriate information concerning the interruption and instructions on how to limit inconvenience caused thereby.
C. Comply with Michigan Public Act 174 of 2013, MISS Dig Underground Facility Damage
Prevention and Safety Act.
1. Excavator shall provide a dig notice to the notification system not less than 72 hours, but not more than 14 days calendar days prior the start of any blasting or excavation by phone at 800-482-7171 or 811, or online at elocate.missdig.org.
1.10 SITE USE CONSTRAINTS
A. All Contractor personnel, including Subcontractors, Suppliers, and others associated with the Project shall wear, at a visible location, at all times at the site a
GLWA supplied security badge.
1. Details and badge request forms can be found in Section 01 35 53.
B. Access (i.e. ingress to and egress from) the site shall be at the location(s) shown on the
Drawings or as otherwise approved by the GLWA.
C. On-site employees of the Contractor or its Subcontractors shall not use GLWA restrooms at GLWA Facilities, unless approved by GLWA in writing. Contractor shall provide its own portable restroom/porta john facilities to be used by on-site employees only. On-site employees shall not use GLWA break areas and eating areas. Any on-site employee unauthorized use of GLWA restrooms, break areas and eating areas shall result in the on-site employee’s removal from the GLWA Facility. Repeated violations may result in the on-site employee being banned from GLWA Facilities.
D. Once fencing and gates have been erected in the SFE Building Area as shown on
Contract Drawings, that area shall be considered outside the GLWA secured area.
Contractor shall be responsible for all security and access control within that area.
1. Attachment A to this section is provided for ease of interpretation.
2. Primary access to the site shall be through the existing, unused gate located immediately north of the Employee Entrance accessing Jefferson Avenue.
a. Contractor shall be responsible for locking and unlocking that gate. GLWA shall be provided with the ability to unlock and access the gate at any time.
APRIL 2025 GLWA WRRF
b. Contractor shall provide appropriate vehicle and personnel access control for the area, as well as security as necessary to protect the site and to prevent its use to access the WRRF facility.
3. Contractor staff in the construction area are encouraged, but not required, to possess and display GLWA badges while in the construction area.
4. The two gates located at the north and south end of the area are for GLWA use only.
a. Contractor may request that GLWA open said gates for access that cannot be readily achieved through the primary entrance to the construction area.
5. Note, Contractor staff parking in the Parking Garage will not be able to access the construction area from the WRRF site. Staff shall enter and exit through the primary entrance point.
E. Work in Balance of Plant.
Work outside the immediately surrounding the SFE Building and enclosed by fencing shown on Attachment A will be performed under normal WRRF access and security requirements as detailed in the Contract Documents
F. Secondary Effluent Conduit Weight Limits
Contractor is cautioned that the Secondary Effluent Conduits underlie the SFE Building
Area (see Attachment A). If Contractor intends to locate equipment, materials, or other items in this area with loads exceeding H-20 vehicle loads, Contractor shall complete an engineering analysis of the structure and loading and submit said analysis, bearing the seal of a Professional Engineer, and Contractor’s plans to protect the conduits.
1.11 CONSTRUCTION CONSTRAINTS
A. This article specifies the constraints placed on the Contractor in its construction of certain elements of the Work of this Contract. These constraints are specified to minimize the risk of losing treatment, pumping and/or related production capabilities that are critical to
GLWA’s overall responsibility to the customers it serves in Southeast Michigan with respect to drinking water and wastewater services. The Contractor shall adhere to the construction constraints specified herein, and plan and execute his work accordingly.
B. GLWA facilities are active production facilities that operate continuously 24 hours per day, 365 days per year. As such, the Contractor shall meticulously plan and prepare its work forces prior to executing Work that requires temporary disturbances to operations and equipment shutdowns. Such temporary disturbances and equipment shutdowns shall be reviewed and approved by the Contracting Officer or its Engineer in consultation with the GLWA.
Comply with requirements of Section 01 14 16, Coordination with Owner’s Operation.
C. Construction constraints specific to this Project that the Contractor shall comply with are specified below:
APRIL 2025 GLWA WRRF
1. 01 14 16 Coordination with Owner's Operations
2. Maintenance of Plant Operation Plan (MOPO)
3. Work may be impacted by weather and high plant flow events.
D. Work that requires shutdown of the Secondary Effluent Conduit(s) shall be limited to only between November 15 and March 15, unless otherwise directed by Owner.
PART 2 - PRODUCTS: NOT USED
PART 3 - EXECUTION
3.01 ATTACHMENTS
A. The attachments indicated below, attached following this section’s “End of
Section” designation, are part of this Specifications section.
1. 01 14 00.A - Site Access Sketch
APRIL 2025 GLWA WRRF
GREAT LAKES WATER AUTHORITY COORDINATION WITH OWNER’S
OPERATIONS
MS REV 0.0 01 14 16
SECTION 01 14 16
COORDINATION WITH OWNER'S OPERATIONS
PART 1 - GENERAL
1.01 SUMMARY
A. Scope:
1. This section includes requirements for coordinating with Owner’s operations during the Project and includes requirements for tie-ins and shutdowns necessary to complete the Work without impact on Owner’s operations except as allowed in this section.
2. Contractor shall provide all labor, materials, equipment, tools, and incidentals shown, specified, and required to coordinate with Owner’s operations during the Work in accordance with this section.
B. Coordination:
1. Review construction procedures under other Specifications sections and coordinate
Work that will be performed with or before the Work specified in this section.
C. Related Sections:
1. Section 01 14 01 Work Restrictions.
2. Section 01 25 00, Substitution Procedures.
3. Section 01 51 00, Temporary Utilities.
4. Section 01 51 41, Temporary Pumping.
5. Section 01 73 29, Cutting and Patching.
D. GLWA facilities protect public health and safety, therefore the Contractor must conduct its Work with care and in a manner that causes no damage to the existing facilities:
infrastructure, utilities, structures, or equipment.