8-Project Manual - Ben Taub Loading Dock Expansion IFP Vol II.pdf

PDF 4 MB Posted

Attached to
CSP - Loading Dock Expansion at Ben Taub Hospital for Harris Health (Estimated Budget - $2, 500, 000)
Solicitation number
26/0152
Issued by
Harris County, Texas

About this file

This is a Project Manual and Mechanical, Electrical, and Plumbing (MEP) specifications document for the Ben Taub Loading Dock Expansion project, a construction initiative by Harris Health located at 1504 Taub Loop in Houston, Texas 77030. The project encompasses the design and installation of comprehensive fire suppression, plumbing, HVAC, electrical, communications, and electronic safety and security systems for a loading dock expansion. The specifications detail requirements for fire protection piping systems including standpipe and hose valve installations, plumbing systems with various pipe materials and fittings, HVAC equipment and controls, electrical systems with lighting and panelboards, communications infrastructure, and fire alarm systems with voice evacuation capabilities. The project manual establishes minimum quality standards and installation requirements in accordance with multiple industry standards including NFPA 13 and 14, ASME, ASHRAE, and local building codes. Key deliverables include comprehensive shop drawings, coordination drawings in three-dimensional format, record documents, operations and maintenance manuals, and operator training. The contractor is responsible for all coordination among trades, verification of field conditions, and compliance with the Authority Having Jurisdiction requirements.

The specifications emphasize domestic manufacturing of all materials and equipment and require extensive submittals including equipment data, dimensional drawings, product certifications, and coordination documentation within thirty days of contract award. All work must be performed by qualified installers experienced in their respective trades, with particular attention to pipe hanger spacing, support systems, insulation, and protective coatings. The contractor assumes full responsibility for identifying deficiencies in existing utilities, determining if additional components are required beyond those indicated on drawings, and bearing all costs associated with coordination and installation modifications necessitated by field conditions. A one-year warranty period begins from the date of substantial completion, with specific extended guarantees required for air compressor equipment. The estimated project budget is $2,500,000, and the work must comply with all applicable federal, state, and local regulations, including the Buy American Act requirements for federally-funded projects.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ben Taub Loading Dock Expansion

1504 Taub Loop

Houston, Texas 77030

MEP Specifications

A Project for:

Harris Health

4800 Fournace Place Bellaire, Texas 77401

Architect:

Powers Brown Architecture

2100 Travis Street, Suite 501

Houston, Texas 77002

Ben Taub Loading Dock Expansion 231304 Issue for Permit 10 March 2026

Table of Contents

00 0110

Section 00 0110 Table Of Contents

Division 21 - Fire Suppression 21 0000 Fire Protection 21 0201 Coordination Drawings 21 0529 Hangers And Supports for Fire Suppression Piping and Equipment

Division 22 - Plumbing 22 0200 Basic Materials and Methods for Plumbing 22 0201 Coordination Drawings 22 0300 Plumbing Demolition for Remodeling 22 0529 Hangers And Support for Plumbing Piping and Equipment 22 0553 Identification for Plumbing Piping and Equipment 22 0716 Plumbing Equipment Insulation 22 0719 Plumbing Piping Insulation 22 1000 Plumbing Piping 22 1119 Plumbing Specialties 22 1121 Natural Gas Piping Systems 22 3000 Plumbing Equipment 22 4000 Plumbing Fixtures

Division 23 - Heating, Ventilating and Air-Conditioning (HVAC) 23 0200 Basic Materials and Methods For HVAC 23 0201 Coordination Drawings 23 0300 Mechanical Demolition for Remodeling 23 0513 Common Motor Requirements for HVAC Equipment 23 0516 Expansion Fittings and Loops for HVAC Piping 23 0526 Variable Frequency Motor Speed Control for HVAC Equipment 23 0529 Hangers and Supports for Piping and Equipment - HVAC 23 0548 Vibration and Seismic Controls for HVAC Piping and Equipment 23 0553 Identification for HVAC Piping and Equipment 23 0593 Testing, Adjusting, and Balancing 23 0713 Duct Insulation 23 0716 HVAC Equipment Insulation 23 0719 HVAC Piping Insulation 23 0800 Commissioning of HVAC Systems 23 0963 Energy Management and Control System (EMCS) 23 2113 Above Ground Hydronic Piping 23 2116 Underground Hydronic Piping

231304 Issue for Permit 10 March 2026

Table of Contents

00 0110

23 2119 Hydronic Specialties 23 2123 Hydronic Pumps 23 2213 Steam and Condensate Heating Piping 23 2216 Steam and Condensate Specialties 23 2300 Refrigerant Piping 23 3113 Metal Ductwork 23 3300 Ductwork Accessories 23 3400 HVAC Fans 23 3713 Air Distribution Devices 23 4100 Air Filters 23 7326 Modular Outdoor Central Station Air Handling Units

Division 26 - Electrical 26 0200 Basic Materials and Methods for Electrical 26 0313 Electrical Demolition for Remodeling 26 0519 Wire, Cable and Related Materials 26 0526 Grounding 26 0533 Raceways 26 0573 Short Circuit Coordination Study Arc Flash Hazard Analysis 26 0634 Low Voltage Raceway System 26 0800 Commissioning of Electrical Systems 26 0936 Lighting Controls (Stand-Alone) 26 2416 Panelboards 26 2726 Wiring Devices 26 2813 Fuses 26 2816 Safety And Disconnect Switches 26 2926 Miscellaneous Electrical Controls and Wiring 26 4313.13 Surge Protective Devices (SPD) - Standard Interrupting 26 5119 Lighting Fixtures - Light Emitting Diode (Led)

Division 27 - Communications 27 0200 Basic Materials and Methods for Communications Systems 27 0528 Pathways for Communications Systems 27 1500 Communications Horizontal Cabling 27 4116 Integrated Audiovisual Systems and Equipment 27 5123 Intercom Communications Systems

Division 28 - Electronic Safety and Security 28 0200 Basic Materials and Methods for Safety and Security Systems

231304 Issue for Permit 10 March 2026

Table of Contents

00 0110

28 0500 Basic Materials And Methods For Fire Alarm 28 1000 Access Control System 28 2000 Video Surveillance System 28 4605 Fire Alarm System With Voice Evacuation - High Rise

231304 Issue for Permit 10 March 2026

Fire Protection

21 0000

SECTION 21 0000

FIRE PROTECTION

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. The requirements of the General Conditions and Supplementary Conditions apply to all work herein.

B. The Basic Materials and Methods, Section 22 0200, are included as a part of this Section as though written in full in this document.

1.02 SCOPE

A. The scope of the work shall include the furnishing and complete installation of the fire protection piping, valves, hose connections, and equipment covered by this Section, with all appurtenances, ready for owner's use.

1.03 RELATED WORK

A. Section 21 0201 - Coordination Drawings B. Section 21 0529 - Hangers and Supports for Fire Suppression Piping and Equipment C. Section 21 1313 - Wet Pipe Sprinkler System D. Section 211316 - Dry Pipe Sprinkler Systems E. Section 21 31 13 - Fire Pumps, Electric Drive F. Section 221200 - Facility Potable-Water Storage Tanks

1.04 REFERENCES

A. ASTM A53/A53M - Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless B. ASTM A135/A135M - Standard Specification for Electric-Resistance-Welded Steel Pipe C. ASTM A795/A795M - Standard Specification for Black and Hot-Dipped Zinc-Coated

(Galvanized) Welded and Seamless Steel Pipe for Fire Protection Use D. FM Global Fire Protection Standards E. NFPA 13 - Standard for the Installation of Sprinkler Systems F. NFPA 14 - Standard for the Installation of Standpipe and Hose Systems G. UL - Underwriters Laboratories

1.05 QUALITY ASSURANCE

A. Manufacturer: For each product specified, provide components by the same manufacturer throughout.

B. Valves: Manufacturer's name, size, and pressure rating shall be cast or marked on valve body or handle.

C. Piping shall be labeled along its entire length indicating size, class, material specification, manufacturer’s name and country of origin.

D. Domestic Manufacture: All valves, pipe, fittings, hose connections, and equipment shall be by a domestic manufacturer.

1.06 SUBMITTALS

A. Submit shop drawings in accordance with Section 22 0200 and as described below.

231304 Issue for Permit 10 March 2026

Fire Protection

21 0000

B. Submit shop drawings of entire water-based building fire protection system with all standpipe, hose valve, and hose connection locations, including the accompanying hydraulic calculations to the Architect/Engineer for review. A current and fully documented fire hydrant flow test must be included.

C. Submit complete product data for 21 31 13 - Fire Pumps, Electric Drive concurrently with the submittal for this Section, for all systems served by such equipment.

D. Service Utility Diagram: Furnish Architect with an accurately marked print showing location of underground pipes and valves as installed upon completion of underground work.

E. Submit product data to include pipe materials, pipe fittings, valves, hose connections, waterflow and alarm devices, and other appurtenances. Provide manufacturer’s catalog information, product certifications, and country of origin. Indicate valve data and ratings.

1.07 REGULATORY REQUIREMENTS

A. Work in accordance with:

1. NFPA 13 - Standard for the Installation of Sprinkler Systems.

2. NFPA 14 - Standard for the Installation of Standpipe and Hose Systems

3. NFPA 24 - Standard for the Installation of Private Fire Service Mains and Their

Appurtenances

4. NFPA 25 - Standard for the Inspection, Testing, and Maintenance of Water-Based Fire

Protection Systems

5. Local codes that have jurisdiction.

B. Products in accordance with:

1. UL (Underwriters Laboratories) listed.

2. FM (Factory Mutual) approved.

3. Requirements of the local Authority Having Jurisdiction (AHJ).

1.08 CERTIFICATE OF TESTING

A. Furnish Owner with test certificate certifying the system approved by:

1. Fire Marshal.

2. Insurance Services Officials.

PART 2 - PRODUCTS

2.01 GENERAL

A. Work included:

1. Design, coordination, furnishing, and installation of inside and outside piping, valves, hose connections, drain and test risers, hangers, supports, and sleeves.

2. The standpipe system to be provided shall be an automatic wet standpipe system to serve all required stairways for the entire building unless specifically indicated otherwise.

a. The Contract Drawings indicate the general extent and arrangement.

b. The Contract Drawings identify water supply, pipe routing, control valves, and hose connections.

c. The fire protection contractor shall make a final determination whether additional hose connections and associated piping are required and shall provide accordingly.

d. For sprinklered buildings, the system may be a combined system.

e. Permanently installed drain risers shall be provided at each standpipe equipped with pressure-regulating devices.

f. All standpipes shall be provided with a means of draining and shall be arranged to discharge water at an approved location.

3. The Drawings provide a preliminary layout with locations of water service entry/water supply, control valves, hose connections, and fire department connection(s). These are a guide for the subsequent preparation of the Licensed Fire Sprinkler Contractor's detailed working drawings.

231304 Issue for Permit 10 March 2026

Fire Protection

21 0000

4. Coordinate work and installation with electrical and fire alarm contractors accordingly to interface system with the building fire and smoke alarm systems.

B. Requirements:

1. Materials and installation to meet or exceed the requirements of NFPA 13 and 14, (prevailing editions) and the local authority having jurisdiction (AHJ).

2. All components of the system shall be UL listed for the intended service.

3. Provide components with minimum pressure ratings as suited for system working pressure(s).

4. All hose connections shall be provided with approved threads, caps, and chains.

2.02 VALVES

A. General Requirements:

1. Valves shall be rated for no less than 175 psi.

2. All valves controlling connections to water supplies and to standpipes shall be listed indicating valves.

3. Drain and test valves shall be approved.

4. All control, drain, and test connection valves shall be provided with permanently marked weatherproof metal identification signs.

5. Provide as indicated on the Drawings and configured in accordance with the requirements of the local Authority Having Jurisdiction.

B. Gate valves

1. Gate valves shall be UL listed, FM approved bronze trimmed resilient wedge gate type.

2. Provide bronze bodied, rising stem, inside screw type for sizes 2" and smaller. Provide ductile iron bodied, rising stem, outside screw and yoke type for sizes 2-1/2" and larger.

3. Acceptable manufacturers:

a. Mueller Company

b. Kennedy Valve

c. Clow Valve Company

d. Nibco

C. Check valves

1. Check valves shall be UL listed, FM approved ductile or cast iron bodied, bronze or stainless fitted, non-slam type, suited for horizontal or vertical installation.

2. Acceptable manufacturers:

a. Mueller Company

b. Kennedy Valve

c. Clow Valve Company

d. Nibco

e. Tyco-Grinnell

D. Drain and trim valves shall be UL listed, bronze body and bonnet, with bronze stem and packing nut, and aluminum handwheel handle, by Nibco.

2.03 PIPE AND FITTINGS

A. All standpipe piping above grade shall be:

1. ASTM A53/A53M schedule 40 black steel pipe with roll-grooved ends, joined with mechanical couplings and cut groove cast iron 300 psi rated fittings.

B. Acceptable manufacturers:

1. Wheatland Tube Company

2. Bull Moose Tube Company

3. Tex-Tube

4. Allied Tube

C. Acceptable mechanical coupling manufacturers:

231304 Issue for Permit 10 March 2026

Fire Protection

21 0000

1. Victaulic

2. Tyco-Grinnell

3. Anvil-Gruvlok

2.04 FIRE HOSE VALVES, CONNECTIONS, AND EQUIPMENT

A. General requirements: All hose valves shall be listed. All hose connections shall be provided complete with connections, caps and chains conforming to local Fire Department requirements.

B. Acceptable Manufacturers:

1. Potter-Roemer

2. Dixon

3. Elkhart Brass

4. Croker

C. STANDPIPE HOSE VALVES: Female to male, straight or angle pattern as necessary to minimize intrusion into stair traffic area while ensuring clearance for connectivity and valve operation. Provide pressure regulating type (complete with visual indicator) as necessary, based on design and system pressure to ensure compliance with NFPA 14 maximum pressure requirements. 2-1/2” cast brass valve with red metal wheel handle and 1-1/2” reducer. Potter- Roemer Model 4065 or similar model with features as required and as described above.

D. ROOF MANIFOLD: Where there is no stairway access to the roof to provide a highest landing hose connection at this elevation, a hose connection shall be provided on the roof. Provide in accordance with NFPA 14 requirements for roof outlet piping, complete with hose valve, indicating control valve and ball drip connection to drain. Minimum two-way type cast brass body, Potter Roemer 5870 series with 2-1/2” hose valves.

E. FIRE DEPARTMENT CONNECTIONS: No less than 4” and two-way type, with additional connections and in larger size in accordance with system demand per NFPA. Polished chrome plated brass with lettering consistent with system type and service. Back, top, or bottom outlet as required for placement and wall construction for building mounted variations. Provide complete with accessibly located, listed check valve with approved automatic drip valve. Potter- Roemer Model 5751 (building mounted), Model 5761 (free-standing) or similar model with features as required and as described above.

PART 3 - EXECUTION

3.01 DESIGN

A. The Contractor shall conform to the requirements of NFPA 14 for standpipe and hose system design and installation. It shall be the Contractor's responsibility to determine if any deficiency or deviations exist, such as an inadequate water supply, or any other item which would materially affect the acceptability of the system.

3.02 INSTALLATION

A. Install all items in accordance with applicable codes.

B. Piping shall be protected accordingly where subject to mechanical damage and/or fire damage.

C. Do not install risers or mains in MDF/IDF/Data closets or electrical rooms. Where sprinkler protection is provided, only the associated branch lines and sprinkler heads shall be allowed in such spaces.

D. Piping (mains and standpipes) shall be protected accordingly from freezing temperature with the use of supervised and listed heat tracing with insulation and jacketing.

E. In all locations subject to corrosive conditions, ensure to provide a suitable epoxy (spray) coating to all exposed surfaces of pipe and fittings. All job-applied protective coatings shall be provided as approved and only after verification that the proper piping has been installed, per the markings along the length of the pipe.

231304 Issue for Permit 10 March 2026

Fire Protection

21 0000

F. Piping in finished spaces shall be routed concealed. This shall not include areas such as mechanical spaces, parking garages, and stairways. Exact routing of piping shall be approved by Architect or relocated as required at no additional cost to Owner.

G. All standpipes shall be provided with a means of draining and shall be arranged to discharge water at an approved location.

H. Identify all locations requiring coordination with the electrical and fire alarm contractors accordingly to ensure connectivity with the building fire and smoke alarm systems. This shall include, but is not necessarily limited to, the following: water flow switches, alarm bells, and tamper/supervisory switches at control valves.

I. At building expansion joints provide approved system expansion joint fittings/assemblies accordingly and per manufacturer's recommendations and NFPA 13 requirements. Victaulic Style 155 carbon steel expansion joint for sizes up to and including 12" pipe.

3.03 PAINTING AND PIPE IDENTIFICATION

A. Painting of fire protection piping and appurtenances shall be provided as follows:

1. Surfaces to be painted shall be cleaned as necessary to ensure they are free from dirt and oils.

2. Unless directed otherwise by Architect, heat and water resistant, air-cured, high performance one-part epoxy paint shall be provided. Coating shall be high-gloss, lead-free, suited for indoor and outdoor use, and USDA approved. Armor-Poxy or similar.

3. Fire sprinkler risers and associated alarm valves and related piping exposed in occupied spaces shall be painted red.

4. Fire protection and sprinkler piping exposed in occupied spaces shall be painted as directed by Architect.

5. Fire protection and sprinkler piping exposed in unoccupied accessory areas such as stairways shall be painted red unless directed otherwise by Architect.

B. Identification of fire protection piping shall be provided as follows:

1. All interior visible piping located in accessible spaces shall be provided with pipe markers.

Accessible spaces shall include, but not necessarily be limited to, the following: above accessible ceilings, inside equipment rooms and utility spaces, in attic spaces, in crawl spaces, and in chase spaces, etc. viewable via access panels.

2. All exterior visible piping shall be provided with pipe markers.

3. Peel-off, self-adhesive, sticker type labels shall not be acceptable.

4. Pipe markers shall be manufactured with rigid vinyl PVC, printed with UV resistant ink, abrasion and chemical resistant, suited for indoor or outdoor use and for a service temperature of -40 degrees F to 160 degrees F.

a. For pipes up to 6” provide cylindrically pre-coiled markers that snap into place without the need for tape or adhesives.

b. For pipes 6” and larger provide flat snap-around markers installed using manufacturer’s heavy-duty nylon ties or stainless steel strapping.

c. Markers shall indicate the pipe service, include flow directional arrows, and meet

ASME A13.1.

5. Acceptable manufacturers:

a. Seton Setmark Pipe Markers

b. Brimar Industries Pipemarker System 1 Pipe Markers

c. Brady Corporation

6. Markers shall be provided after final insulating, painting, jacketing, etc. of piping and per manufacturer’s installation instructions. Strapping (applies to large diameter markers only) shall be snug but shall not compromise any insulation. All such strapping shall also be cleanly trimmed of excess material.

231304 Issue for Permit 10 March 2026

Fire Protection

21 0000

7. Markers shall be provided in accordance with ASME A13.1 requirements. Specific items indicated below are not intended as a substitute for this complete standard. Markers shall be provided:

a. On both sides of each floor or wall penetration.

b. On each side of each tee.

c. On each side of each valve and/or valve group.

d. On each side of each piece of equipment.

e. On straight pipe runs at equally spaced intervals not to exceed 50 feet.

f. In congested areas, on each pipe at the point it enters and exits the area.

g. At the point of connection to each piece of equipment and automatic control valve.

h. Where they are readily visible to personnel from the point of normal approach.

i. With letter height and length of color field according to the size of the pipe served.

8. Color scheme of markers shall be as indicated below and otherwise in accordance with ANSI/ASME color recommendations. Legend color indicates color of legend text and flow directional arrow:

SYSTEM LABEL COLOR LEGEND LEGEND COLOR

Fire Protection Red Fire Protection White

Red Fire Sprinkler White

3.04 REPLACEMENT

A. Upon receipt of written notice of failure of any part of the guaranteed equipment during the guaranteed period, the Contractor will replace the affected part or parts promptly at no additional cost.

3.05 TESTING

A. Upon completion of the installation, test the system and obtain approval of the local fire insurance rating organization having jurisdiction.

3.06 TRAINING

A. Owner’s people shall be fully briefed in the normal start-up of the system, operation, normal and emergency shutdown, and maintenance of the system.

B. Routine maintenance, yearly maintenance, winterization, and spring start-up shall be fully discussed and documented.

C. Names of those instructed and dates, as well as a list of information handed over to the owner, shall be included in the final report.

END OF SECTION

231304 Issue for Permit 10 March 2026

Coordination Drawings

21 0201

SECTION 21 0201

COORDINATION DRAWINGS

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. The requirements of the General Conditions 01 31 00 and Supplementary Conditions apply to all Work herein.

1.02 COORDINATION DRAWINGS

A. The Contractor shall take the lead in coordinating the Mechanical, Electrical, Plumbing, Communications, Electronic Safety/Security and Fire Protection systems within the building.

B. The Contractor shall coordinate a three-dimensional (3D) model of the building which includes the Mechanical, Electrical, Plumbing, and Fire Protection systems. The Contractor will be provided with the REVIT model that was used to generate the contract documents and this file may be used as the background file. The Contractor shall replace the systems drawn with the actual shop drawing models. The Contractor is not limited to using REVIT and may use any 3-D software in generating and combining the coordination model.

C. Submitting the contract drawings as coordination drawings will not be acceptable.

D. The model shall include detailed and accurate representations of all equipment to be installed based upon the reviewed equipment submittals.

E. The Contractor shall hold a 3-D coordination meeting with all sub-contractors present to review the model and discuss coordination of the installation of the building systems.

F. Upon completion of the coordination meeting, the Contractor shall submit the 3-D model and

1/4” scale drawings for review.

G. The model shall detail major elements, components, and systems in relationship with other systems, installations, and building components. Indicate locations where space is limited for installation and access and where sequencing and coordination of installations are of importance to the efficient flow of the Work, including (but not necessarily limited to) the following:

1. Indicate the proposed locations of pipe, duct, equipment, and other materials. Include the following:

a. Wall and type locations.

b. Clearances for installing and maintaining insulation.

c. Locations of light fixtures and sprinkler heads.

d. Clearances for servicing and maintaining equipment, including tube removal, filter removal, and space for equipment disassembly required for periodic maintenance.

e. Equipment connections and support details.

f. Exterior wall and foundation penetrations.

g. Routing of storm and sanitary sewer piping.

h. Fire-rated wall and floor penetrations.

i. Sizes and location of required concrete pads and bases.

j. Valve stem movement.

k. Structural floor, wall and roof opening sizes and details.

2. Indicate scheduling, sequencing, movement, and positioning of large equipment into the building during construction.

3. Prepare floor plans, elevations, and details to indicate penetrations in floors, walls, and ceilings and their relationship to other penetrations and installations.

4. Prepare reflected ceiling plans to coordinate and integrate installations, air distribution devices, light fixtures, communication systems components, and other ceiling mounted items.

H. Sequence of Coordination

231304 Issue for Permit 10 March 2026

Coordination Drawings

21 0201

1. Below is hierarchy of model elements and the sequencing by which the models will be coordinated.

a. Structural and Architectural model

b. Miscellaneous steel

c. Perform preliminary space allocation

d. Identify hard constraints (locations of access panels, lights, A/V space requirements, etc.)

e. Main and medium pressure ducts from the shaft out

f. Main graded plumbing lines and vents

g. Sprinkler mains and branches

h. Cold and hot water mains and branches

i. Lighting fixtures and plumbing fixtures

j. Smaller sized ducts and flex ducts

k. Smaller size cold water and hot water piping, flex ducts, etc.

I. The Contractor shall not install any item until the coordination has been completed and reviewed by the Construction Manager, Owner, and A/E team.

J. The Contractor shall be responsible for coordination of all items that will affect the installation of the Work. This coordination shall include, but not be limited to: voltage, ampacity, capacity, electrical and piping connections, space requirements, sequence of construction, building requirements and special conditions.

K. By submitting shop drawings on the project, the Contractor is indicating that all necessary coordination has been completed and that the systems, products and equipment submitted can be installed in the building and will operate as specified and intended, in full coordination with all trades.

231304 Issue for Permit 10 March 2026

Hangers and Supports for Fire Suppression Piping and

Equipment

21 0529

SECTION 21 0529

HANGERS AND SUPPORTS FOR FIRE SUPPRESSION PIPING AND EQUIPMENT

PART 1 - GENERAL

1.01 WORK INCLUDED

A. Pipe hangers, supports, and associated appurtenances.

B. Sleeves and seals.

1.02 RELATED WORK

A. Section 21 0000 - Fire Protection B. Section 21 1313 - Wet Pipe Sprinkler System C. Section 21 13 16 - Dry Pipe Sprinkler Systems D. Section 21 31 13 - Fire Pumps, Electric Drive

1.03 REFERENCES

A. ASME B31.1 - Power Piping.

B. NFPA 13 - Standard for the Installation of Sprinkler Systems.

C. NFPA 14 - Standard for the Installation of Standpipe and Hose Systems.

1.04 QUALITY ASSURANCE

A. Supports for Sprinkler Piping: In conformance with NFPA 13.

B. Supports for Standpipes: In conformance with NFPA 14.

1.05 SUBMITTALS

A. Submit shop drawings and product data under provisions of Division One.

B. Indicate hanger and support framing and attachment methods.

PART 2 - PRODUCTS

2.01 PIPE HANGERS AND SUPPORTS

A. Hangers for Pipe Sizes up through 2 Inch: Carbon steel, adjustable swivel ring type with rounded edge design, UL listed and FM approved. Anvil International Figure 69.

B. Hangers for Pipe Sizes 2-1/2 Inch and larger:

1. Carbon steel, adjustable clevis type, UL listed and FM approved. Anvil International Figure

260.

2. Carbon steel, adjustable swivel ring type, UL listed and FM approved. Anvil International

Figure 69.

3. Carbon steel, UL listed straps & hangers with beveled edge design and/or plastic coating for abrasion protection of and intended for use with CPVC piping (only where such pipe material is specified). Anvil International.

C. Building structure attachments for hangers: Ductile iron, universal C-type clamps, UL listed and FM approved. Anvil International Figure 92, 93, 94.

D. Vertical Piping Supports: Carbon steel riser clamp. Anvil International Figure 40.

E. Floor Supports for pipe headers and similar horizontal runs of pipe: Steel pipe stand assembly.

1. Cylindrical pipe stanchion assembly complete with malleable iron flange or welded steel flange base plate secured to the floor by an approved method with listed anchors.

2. Each base plate shall be attached to the floor with a minimum of four (4) anchors no smaller than 1/2" diameter, per NFPA 13.

3. Provide pipe saddle support with steel U-bolt yoke and nuts to attach piping to each stand.

231304 Issue for Permit 10 March 2026

Hangers and Supports for Fire Suppression Piping and

Equipment

21 0529

4. Anvil International Figure 63, Type P with Figure 259 saddle support.

F. Equivalent UL listed, FM approved hanger and support products by Eaton B-Line shall also be acceptable.

G. For installation of protective shields refer to Article 3.3.

2.02 HANGER RODS

A. Galvanized or cadmium plated carbon steel hanger rods: Threaded both ends, threaded one end, or continuous threaded. Provide rod couplings in matching finish.

2.03 INSERTS/FASTENERS

A. Inserts: Malleable iron case of galvanized steel shell and expander plug for threaded connection with lateral adjustment, top slot for reinforcing rods, lugs for attaching to forms; size inserts to suit threaded hanger rods.

B. Fasteners: For wood construction and for metal purlin and metal deck applications only, the use of appropriate self-drilling fasteners (UL listed, FM approved, manufactured in USA) provided in accordance with manufacturer’s recommendations shall be acceptable. ITW Buildex “Sammys” products or pre-approved equal.

2.04 SLEEVES

A. All pipe penetrations through walls, floors, floor-ceiling assemblies, etc. shall be sleeved to ensure no direct contact between the pipe and that which it passes through. All installations shall be provided consistent with the fire and smoke safeguards required by the building code per the fire-resistance rating as indicated on the architectural drawings and shall be provided consistent with the assemblies/methods indicated on the architectural drawings.

B. Unless required otherwise (the most stringent requirement shall govern), sleeves for pipes:

1. Through nonfire-resistance-rated floors shall be formed with 18 gage galvanized steel, tack welded to form a uniform sleeve.

2. Through nonfire-resistance-rated walls, through grade beams and foundation walls, and through potentially wet floors shall be formed with schedule 40 steel pipe, galvanized.

3. Through assemblies including but not limited to fire-resistance-rated walls-barriers-partitions, smoke barriers-partitions, etc. shall be schedule 40 steel pipe securely fastened to the rated assembly. All annular spaces shall be firestopped with an approved penetration firestop system (UL listed) compatible with the pipe material and installed per the manufacturer's recommendations.

C. Fire Stopping Insulation: Glass fiber type, non-combustible, UL listed.

D. Caulk: Paintable 25-year acrylic sealant.

E. Pipe Alignment Guides: Factory fabricated, of cast semi-steel or heavy fabricated steel, consisting of bolted, two-section outer cylinder and base with two-section guiding spider that bolts tightly to pipe. Length of guides shall be as recommended by manufacturer to allow indicated travel.

2.05 FABRICATION

A. Size sleeves large enough to allow for movement due to expansion and contraction. Provide for continuous insulation wrapping.

B. Design hangers without disengagement of supported pipe.

2.06 FINISH

A. Exposed steel hangers, supports, and appurtenances shall be hot-dipped galvanized. Hangers and supports located in crawl spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.

231304 Issue for Permit 10 March 2026

Hangers and Supports for Fire Suppression Piping and

Equipment

21 0529

PART 3 - EXECUTION

3.01 INSERTS

A. Provide inserts for suspending hangers from reinforced concrete slabs and sides of reinforced concrete beams. Coordinate with structural engineer for placement of inserts.

B. Provide hooked rod to concrete reinforcement section for inserts carrying pipe over 4 inches.

C. Where concrete slabs form finished ceiling, provide inserts to be flush with slab surface.

D. Where inserts are omitted, drill through concrete slab from below and provide thru-bolt with recessed square steel plate and nut recessed into and grouted flush with slab. Verify with structural engineer prior to start of work.

3.02 PIPE HANGERS AND SUPPORTS

A. Support horizontal piping with maximum distance between hangers and minimum hanger rod diameters as follows:

Pipe Size Max. Hanger Spacing Min. Rod Diameter (Steel Pipe) 1 to 1-1/4 inch 10'-0" 3/8" 1-1/2 to 3 inch 12'-0" 3/8" 4 to 6 inch 12'-0" 1/2" 8 to 10 inch 12'-0" 5/8" 12 to 14 inch 12'-0" 3/4" (CPVC Pipe, only where specified) 3/4 to 1 inch 4'-0" 3/8" 1-1/4 to 1-1/2 inch 4'-0" 3/8" 2 to 3 inch 6'-0" 3/8"

B. Where a listed CPVC pipe manufacturer’s maximum hanger spacing is more stringent than the spacing above, it shall be followed.

C. Spacing of hangers for unbroken lengths of CPVC pipe shall be permitted to be increased to a maximum of 5’-6” for 3/4" piping and 6’-0” for 1” through 1-1/2” piping.

D. Ensure to adequately secure sprinkler piping to restrict the movement of piping upon sprinkler operation. Where listed CPVC pipe is specified, supports must be provided as required in accordance with the pipe manufacturer’s recommendations.

E. Install hangers to provide minimum 1/2 inch space between finished covering and adjacent work.

F. Place a hanger within 12 inches of each horizontal elbow and at the vertical to horizontal transition.

G. For piping 2 inches and larger, provide additional hangers at offsets and changes in horizontal direction of piping. Where the spacing of adjacent hangers for the piping does not exceed the distance limits in NFPA 13, such additional hangers shall still be provided.

H. Use hangers with 1-1/2 inch minimum vertical adjustment.

I. Ensure that hanger rods are only loaded axially (along the rod). Provide additional hangers or restraints as necessary to minimize non-axial loads J. Threaded sections of rod shall not be formed or bent, neither prior to nor as a result of installation.

231304 Issue for Permit 10 March 2026

Hangers and Supports for Fire Suppression Piping and

Equipment

21 0529

K. Support vertical piping at every floor. Distances between supports for risers shall not exceed 25 feet.

L. In multi-story buildings (in addition to at every floor) riser supports shall be provided at the lowest level, above and below offsets, and at the top of the riser.

M. Where several pipes can be installed in parallel and at same elevation, provide multiple or trapeze hangers.

N. Support riser piping independently of connected horizontal piping.

O. Install hangers with a nut at the base and above the hanger; tighten upper nut to hanger after final installation adjustments.

P. Where piping is subject to seismic activity, ensure to provide protection measures in accordance with NFPA 13 requirements.

3.03 INSULATED PIPING

A. Comply with the following installation requirements.

B. Clamps: Attach galvanized clamps, including spacers (if any), to piping with clamps projecting through insulation; do not exceed pipe stresses allowed by ASME B31.9.

C. Saddles: Install galvanized protection saddles MSS Type 39 where insulation without vapor barrier is indicated. Fill interior voids with segments of insulation that match adjoining pipe insulation.

D. Shields: Install protective shields MSS Type 40 on cold and chilled water piping that has vapor barrier. Shields shall span an arc of 180 degrees and shall have dimensions in inches not less than the following:

Nominal Pipe Size Length Thickness 1/4 through 3-1/2 inch 12 inch 0.048 inch 4 inch 12 inch 0.060 inch 5 through 6 inch 18 inch 0.060 inch 8 through 14 inch 24 inch 0.075 inch 16 through 24 inch 24 inch 0.105 inch

E. Piping 2” and larger provide galvanized sheet metal shields with calcium silicate at hangers/supports.

F. Insert material shall be at least as long as the protective shield.

G. Thermal Hanger Shields: Install where indicated, with insulation of same thickness as piping.

3.04 EQUIPMENT BASES AND SUPPORTS

A. Provide equipment bases of concrete.

B. Provide templates, anchor bolts, and accessories for mounting and anchoring equipment.

C. Construct support of steel members. Brace and fasten with flanges bolted to structure.

3.05 SEALS

A. Provide flexible watertight sealant where piping penetrates waterproofed walls, floors, and roofs.

B. Where dry sprinklers are connected to wet pipe sprinkler systems protecting areas subject to freezing temperatures (such as, but not necessarily limited to, insulated freezer structures) ensure that the clearance space around the sprinkler barrel is completely sealed in accordance with the manufacturer’s recommendations.

231304 Issue for Permit 10 March 2026

Hangers and Supports for Fire Suppression Piping and

Equipment

21 0529

3.06 SLEEVES

A. Set sleeves in position in formwork. Provide reinforcing around sleeves.

B. Extend sleeves through floors minimum one inch above finished floor level. Caulk sleeves full depth with fire rated thermafiber and 3M caulking and provide floor plate.

C. Where piping penetrates a floor, ceiling, or wall, close off space between pipe and adjacent work with UL listed fire stopping insulation and caulk seal air tight. Provide close fitting metal collar or escutcheon covers at both sides of penetration.

D. Fire protection sleeves may be flush with floor of stairways.

231304 Issue for Permit 10 March 2026

Basic Materials and Methods for Plumbing

22 0200

SECTION 22 0200

BASIC MATERIALS AND METHODS FOR PLUMBING

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. The requirements of the General Conditions and Supplementary Conditions apply to all Work herein.

B. The Contract Drawings indicate the extent and general arrangement of the systems. If any departure from the Contract Drawings is deemed necessary by the Contractor, details of such departure and the reasons therefore shall be submitted to the Architect/Engineer for approval as soon as reasonably practicable. No such departures shall be made without the prior written approval of the Architect/Engineer.

C. Notwithstanding any reference in the Specifications to any article, device, product, material, fixture, form or type of construction by name, make or catalog number, such reference shall not be construed as limiting competition; and the Contractor, in such cases, may at his option use any article, device, product, material, fixture, form or type of construction which in the judgment of the Architect/Engineer, expressed in writing, is equal to that specified.

1.02 SCOPE OF WORK

A. The Work included under this Contract consists of the furnishing and installation of all equipment and material necessary and required to form the complete and functioning systems in all of their various phases, all as shown on the accompanying Drawings and/or described in these Specifications. The Contractor shall review all pertinent Drawings, including those of other contracts, prior to commencement of Work.

B. This Division requires the furnishing and installing of all items as specified herein, indicated on the Drawings, or reasonably inferred as necessary for safe and proper operation; including every article, device or accessory (whether or not specifically called for by item) reasonably necessary to facilitate each system's functioning as indicated by the design and the equipment specified. Elements of the work include, but are not limited to: materials, labor, supervision, transportation, storage, equipment, utilities, all required permits, licenses and inspections. All work performed under this Section shall be in accordance with the Project Manual, Drawings and Specifications and is subject to the terms and conditions of the Contract.

C. The approximate locations of Plumbing and Fire Protection items are indicated on the Drawings. These Drawings are not intended to give complete and accurate details with regards to locations of piping, appurtenances, etc. Exact locations are to be determined by actual measurements at the building/job-site, and will in all cases be subject to the Review of the Owner or Engineer, who reserves the right to make any reasonable changes in the locations indicated without additional cost to the Owner.

D. Items specifically mentioned in the Specifications but not shown on the Drawings and/or items shown on Drawings but not specifically mentioned in the Specifications shall be installed by the Contractor under the appropriate section of work as if they were both specified and shown.

E. All discrepancies between the Contract Documents and actual job-site conditions shall be reported to the Owner or Engineer so that they will be resolved prior to bidding. Where this cannot be done at least seven (7) working days prior to bid; the greater or more costly of the discrepancy shall be bid. All labor and materials required to perform the work described shall be included as part of this Contract.

F. It is the intention of this Section of the specifications to outline minimum requirements to furnish the Owner with a turn-key and fully operating system in cooperation with other trades.

231304 Issue for Permit 10 March 2026

Basic Materials and Methods for Plumbing

22 0200

G. It is the intent of the above "Scope" to give the Contractor a general outline of the extent of the Work involved; however, it is not intended to include each and every item required for the Work.

Anything omitted from the "Scope" but shown on the Drawings, or specified elsewhere, or necessary for complete and functioning plumbing systems shall be considered a part of the overall "Scope".

H. The Contractor shall rough-in fixtures and equipment furnished by others from rough-in and placement drawings furnished by others. The Contractor shall make final connection to fixtures and equipment furnished by others.

I. The Contractor shall participate in the Commissioning process as required; including, but not necessarily limited to: meeting attendance, completion of checklists, and participation in functional testing.

1.03 SCHEMATIC NATURE OF CONTRACT DOCUMENTS

A. The contract documents are schematic in nature in that they are only to establish scope and a minimum level of quality. They are not to be used as actual working construction drawings. The actual working construction drawings shall be the reviewed Shop Drawings.

B. The piping, fixture, and equipment locations as indicated on the documents do not indicate every transition, offset, or exact location. All transitions, offsets, clearances and exact locations shall be established by actual field measurements, coordination with the structural, architectural and reflected ceiling plans, and other trades. Submit Shop Drawings for review.

C. All transitions, offsets and relocations as required by actual field conditions shall be provided by the Contractor at no additional cost to the owner.

D. Additional coordination with Electrical Subcontractor may be required to allow adequate clearances of electrical equipment, fixtures, and associated appurtenances. Contractor to notify Architect and Engineer of unresolved clearances, conflicts, or equipment locations.

1.04 SITE VISIT AND FAMILIARIZATION

A. Before submitting a bid, it will be necessary for each Contractor whose work is involved to visit the site and ascertain for himself the conditions to be met therein in installing his work and make due provision for same in his bid. It will be assumed that this Contractor in submitting his bid has visited the premises and that his bid covers all work necessary to properly install the piping, fixtures and equipment shown. Failure on the part of the Contractor to comply with this requirement shall not be considered justification for the omission or faulty installation of any work covered by these Specifications and Drawings.

B. Understand the existing utilities from which services will be supplied; verify locations of utility services, and determine requirements for connections.

C. Determine in advance that equipment and materials proposed for installation fit into the confines indicated.

1.05 WORK SPECIFIED IN OTHER SECTIONS

A. Finish painting is specified elsewhere. Prime and protective painting is included in the work of this Division.

B. Owner and General Contractor furnished equipment shall be properly connected to plumbing systems.

C. Furnishing and installing all required plumbing equipment, control relays and electrical interlock devices, conduit, wire and junction boxes are included in the Work of this Division.

1.06 PERMITS, TESTS, INSPECTIONS

A. Arrange and pay for all permits, fees, tests, and all inspections as required by governmental authorities.

231304 Issue for Permit 10 March 2026

Basic Materials and Methods for Plumbing

22 0200

1.07 DATE OF FINAL ACCEPTANCE

A. The date of final acceptance shall be the date of Owner occupancy, or the date all punch list items have been completed, or the date final payment has been received. Refer to Division 01 for additional requirements.

B. The date of final acceptance shall be documented in writing and signed by the Architect, Owner and Contractor.

1.08 DELIVERY, STORAGE, AND HANDLING

A. Deliver products to the project properly identified with names, model numbers, types, grades, compliance labels, and other information needed for identification.

B. Deliver products to the project at such times as the project is ready to receive the fixtures, equipment, pipe, valves, etc. - properly protected from incidental damage and weather damage.

C. Damaged fixtures, equipment, valves, pipe, or appurtenances shall be promptly removed from the site and new, undamaged items shall be provided in its place promptly with no additional charge to the Owner.

1.09 NOISE AND VIBRATION

A. The plumbing systems and the component parts thereof shall be guaranteed to operate without objectionable noise, water hammering, and vibration.

B. Provide foundations, supports and isolators as specified or indicated, properly adjusted to prevent transmission of vibration to the building structure, piping and other items.

C. Carefully fabricate pipe and fittings with smooth interior finish to prevent turbulence and generation or regeneration of noise.

D. All equipment shall be selected to operate with minimum of noise and vibration. If, in the opinion of the Architect/Engineer, objectionable noise or vibration is produced or transmitted to or through the building structure by equipment, piping or other parts of the Work, the Contractor shall rectify such conditions without extra cost to the Owner.

E. Above ceiling piping and valves shall not be installed in direct contact with the work of other trades, including, but not limited to, suspended ceiling hanger wire.

1.10 APPLICABLE CODES

A. Obtain all required permits and inspections for all work required by the Contract Documents and pay all required fees in connection thereof.

B. Arrange with the serving utility companies for the connection, relocation, and upgrade of all required utilities and pay all charges, meter charges, connection fees and inspection fees, if required.

C. Comply with all applicable codes, specifications, local ordinances, industry standards, utility company regulations and the applicable requirements of the nationally accepted codes and standards.

D. Such codes and standards shall include, but not necessarily be limited to:

1. American Standards Association, ASA.

2. American Society of Heating, Refrigerating, and Air-Conditioning Engineers, Inc., ASHRAE.

3. American Society of Mechanical Engineers, ASME.

4. American Society of Plumbing Engineers, ASPE.

5. American Society of Testing Materials, ASTM.

6. American Water Works Association, AWWA.

7. National Bureau of Standards, NBS.

8. National Fire Protection Association, NFPA.

231304 Issue for Permit 10 March 2026

Basic Materials and Methods for Plumbing

22 0200

9. UL, LLC (formerly Underwriters Laboratories).

10. FM Global.

11. International Energy Conservation Code, IECC.

12. International Fire Code.

13. International Fuel Gas Code.

14. International Plumbing Code.

E. Where differences exist between the Contract Documents and applicable state or city building codes, state and local ordinances, industry standards, utility company regulations and the applicable requirements of the above listed nationally accepted codes and standards, the more stringent or costly application shall govern. Promptly notify the Architect/Engineer in writing of all differences.

F. When directed in writing by the Architect/Engineer, remove all work installed that does not comply with the Contract Documents and applicable state or city building codes, state and local ordinances, industry standards, utility company regulations and the applicable requirements of the above listed nationally accepted codes and standards. Correct the deficiencies and complete the work at no additional cost to the Owner.

1.11 DEFINITIONS AND SYMBOLS

A. General Explanation: A substantial amount of construction and Specification language constitutes definitions for terms found in other Contract Documents, including Drawings which must be recognized as diagrammatic and schematic in nature and not completely descriptive of requirements indicated thereon. Certain terms used in Contract Documents are defined generally in this article, unless defined otherwise in Division 01.

B. Definitions and explanations of this Section are not necessarily either complete or exclusive, but are general for work to the extent not stated more explicitly in another provision of the Contract Documents.

C. Indicated: The term "Indicated" is a cross-reference to details, notes or schedules on the Drawings, to other paragraphs or schedules in the Specifications and to similar means of recording requirements in Contract Documents. Where such terms as "Shown", "Noted", "Scheduled", "Specified" and "Detailed" are used in lieu of "Indicated", it is for the purpose of helping the reader locate cross-reference material, and no limitation of location is intended except as specifically shown.

D. Directed: Where not otherwise explained, terms such as "Directed", "Requested", "Accepted", and "Permitted" mean by the Architect or Engineer. However, no such implied meaning will be interpreted to extend the Architect's or Engineer's responsibility into the Contractor's area of construction supervision.

E. Reviewed: Where used in conjunction with the Engineer's response to submittals, requests for information, applications, inquiries, reports and claims by the Contractor the meaning of the term "Reviewed" will be held to limitations of Architect's and Engineer's responsibilities and duties as specified in the General and Supplemental Conditions. In no case will "Reviewed" by Engineer be interpreted as a release of the Contractor from responsibility to fulfill the terms and requirements of the Contract Documents.

F. Furnish: Except as otherwise defined in greater detail, the term "Furnish" is used to mean supply and deliver new to the project site, ready for unloading, unpacking, assembly, installation, etc., as applicable in each instance.

G. Install: Except as otherwise defined in greater detail, the term "Install" is used to describe operations at the project site including unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protection, cleaning and similar operations, as applicable in each instance.

231304 Issue for Permit 10 March 2026

Basic Materials and Methods for Plumbing

22 0200

H. Provide: Except as otherwise defined in greater detail, the term "Provide" is used to mean "Furnish and Install", complete and ready for intended use, as applicable in each instance.

I. Installer: Entity (person or firm) engaged by the Contractor or its Subcontractor for performance of a particular unit of work at the project site, including unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protection,…

This is the start of the file's text. The full file is on GovTribe.