8 - Cost Estimate Worksheet.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
861CM3011: Facility Condition Assessment (FCA) Deficiencies Corrections Repairs, Mill Springs National Cemetery
Solicitation number
36C78625B0010
Issued by

About this file

This is a contractor cost estimate worksheet template designed for submitting pricing for facility repairs at Mill Springs National Cemetery (Project 861CM3011). The worksheet is structured using Construction Specifications Institute (CSI) divisions from Division 0 through Division 33, requiring contractors to provide lump sum costs for each applicable division of work. The template includes dedicated sections for General Conditions, Mobilization, Site Investigation, and various construction categories including concrete, masonry, metals, finishes, HVAC, electrical, and utilities.

The worksheet calculates total base construction costs by combining mechanical/electrical/plumbing and general construction subtotals, with additional fields for insurance, bonding, overhead percentage, and profit percentage to determine the final grand total. The template is specifically tied to VA National Cemetery Administration solicitation 36C78625B0010 for Facility Condition Assessment (FCA) Deficiencies Corrections Repairs.

View the file

Other files

File Type Posted
Mill Springs National Cemetery - RFIs_Response.xlsx XLSX spreadsheet
36C78625B0010 0004.docx DOCX document
36C78625B0010 0003.docx DOCX document
36C78625B0010 0002.docx DOCX document
36C78625B0010 0001.docx DOCX document
S02 Bid Documents Drawings.pdf PDF
36C78625B0010.docx DOCX document
P07 Mill Springs Heavy.txt TXT text file
861CM30011_BD Specifications_Correct Cemetery FCA Def Mill Springs NC_Rev1.pdf PDF
P07 Mill Springs Highway.txt TXT text file
P07 Mill Spring Building.txt TXT text file
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

IFB Contractor Cost Estimate Worksheet
Lump Sums are required for each Division that will be utilized in this project to total the Final Lump Sum number.

If a Division is not being used put N/A in that field.

Additional lines/items can be added if needed or appropriate.

Offeror shall use and edit to fit Task Order Project
Project Number:
Solicitation Number:
Project Title:
DivisionUnit of Measure# of UnitsUnit Cost $Extended/Total Cost $Comments / Remarks
Division 0 - Special Sections
General Conditions and AdministrationJB1
Division 01 - General Requirements
MobilizationJB1
Division 02 - Existing Conditions
Site InvestigationJB1
Division 03 - Concrete

Division 04 - Masonry

Division 05 - Metals

Division 06 - Wood, Plastic, and Composites

Division 07 - Thermal and Moisture Protection

Division 08 - Openings (Doors, Windows, etc...)

Division 09 - Finishes

Division 10 - Specialties

Division 11 - Equipment

Division 12- Furnishings

Division 13 - Special Construction

Division 14 - Fire Suppression

Division 22 - Plumbing

Division 23 - Heat, Ventilating, and Air Conditioning

Division 25 - Integrated Automation

Division 26 - Electrical

Division 27 - Communications

Division 28 - Electronic Safety and Security

Division 31 - Earthwork

Division 32 - Exterior Improvements

Division 33 - Utilities

Mechanical, Electrical, Plumbing Subtotal
General Construction Subtotal
Total Base Construction Cost
Insurance (if applicable)
Bonding (if applicable)
Overhead________ %$0.00
Profit________ %$0.00
GRAND TOTALS$