Mill Springs National Cemetery - RFIs_Response.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
861CM3011: Facility Condition Assessment (FCA) Deficiencies Corrections Repairs, Mill Springs National Cemetery
Solicitation number
36C78625B0010
Issued by

About this file

This document is a Request for Information (RFI) response spreadsheet for the Mill Springs National Cemetery renovation project (Project Number: 36C78625B0010). The project involves correcting cemetery facility condition assessment (FCA) deficiencies, with VALIANT Construction submitting 35 detailed questions about project specifications, logistics, and implementation. Key project details include restoration of existing infrastructure such as benches, stone walls, markers, and service seals, installation of new aluminum windows, and site improvements like trench drainage and landscape elements.

The project will be completed during normal working hours, with the contractor using cemetery utilities (electricity and water) with specific metering and connection requirements. The Department of Veterans Affairs National Cemetery Administration is overseeing the project, with an anticipated award within 90 days of bid reading. The contractor will be responsible for various technical aspects including restoration processes, mockup demonstrations, and coordination with specialized vendors like US Bronze for service seal refinishing. Notable requirements include on-site stone restoration, preservation of existing site conditions, and adherence to specific technical specifications for infrastructure improvements.

View the file

Other files

File Type Posted
36C78625B0010 0004.docx DOCX document
36C78625B0010 0003.docx DOCX document
36C78625B0010 0002.docx DOCX document
36C78625B0010 0001.docx DOCX document
S02 Bid Documents Drawings.pdf PDF
36C78625B0010.docx DOCX document
8 - Cost Estimate Worksheet.xlsx XLSX spreadsheet
P07 Mill Springs Heavy.txt TXT text file
861CM30011_BD Specifications_Correct Cemetery FCA Def Mill Springs NC_Rev1.pdf PDF
P07 Mill Springs Highway.txt TXT text file
P07 Mill Spring Building.txt TXT text file
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary

MILL SPRINGS NATIONAL CEMETERY - AE RESPONSE TO CONTRACTOR RFI
PROJECT TITLE:Correct Cemetery FCA Deficiencies at the Mill Springs National Cemetery
PROJECT NUMBER:36C78625B0010ClosedPartically AddressedClosedTotal
0
ItemSubmitted ByDrawing/ SpecificationQuestionsResponse/ ActionLandscape Architect0
Civil0
Structural0
1VALIANT ConstructionSolicitationAre we to submit a price on all of the alternates?Please follow price schedule as per Amendement 00002.Electrical0
2VALIANT ConstructionSolicitationThe SF1442 block 17 has a line for base bid only. Do we need to include any other alternates here?Please follow price schedule as per Amendement 00002.Irrigation0
3VALIANT ConstructionCS101Will the new curb have a square edge or taper to the flush elevation?Refer to sheet CS101/keynote 3 also See detail 3 on sheet C-501Architectural0
4VALIANT ConstructionNote 7A - CS102Please provide details on how we are to refinish the existing benchesStrip away rust and chiping paint. Repaint to match original state.0
5VALIANT ConstructionNote 3 - CS105Note 3 on CS105 points to one side of the stone wall. Is the scope of work mentioned in note 3 only required on the side of the wall it is pointed to or is this work required for all sides of the wall?This work is required for all sides of the wall.
6VALIANT ConstructionCS101 & CS107CS101 & CS107 - Please provide details for the hatched symbol wrapping the trench drain at the entrance.Refer to sheet CD101 /keynote 5 and see detail 2 on sheet C-502
7VALIANT ConstructionDetail 1 - IR502IR502 - Detail 1 - Is the resident engineer by the owner and designer of record?"Resident Engineer" means "COR"
8VALIANT ConstructionL500Can the marker be taken off site for restoration or is the restoration restricted to on-site work only?Headstones must remain on-site
9VALIANT ConstructionSolicitationWhat mock-up of the marker restoration will be required? (i.e. pinning, stone fill adhesion, delamination, etc)A mockup of the service emblem attachment showing the emblem attachment, setting of limestone mounting stone to cmu, anchoring, mortaring and joint sealing.
10VALIANT ConstructionL504Has the Owner finalized the contract with USBronze for the 5 existing service seals to be removed and refinished?Contractor is responsible for removal of existing service seals and coordination with US Bronze for refinishing
11VALIANT ConstructionL504What is the duration for US Bronze to refinish the bronze service seals?Contractor to coordinate schedule with US Bronze.
12VALIANT ConstructionL504Are the benches shown in 3/A504 new? If so, will this be provided and installed by the Contractor? Please provide specs.Benches are existing and not a part of this contract.
13VALIANT ConstructionAD101Will we need to provide temporary ADA access to the restrooms?No temporary measures are required by the contractor. If NCA deems necessary, cemetery may contract portable toilet rentals.
14VALIANT ConstructionNote 4 - AD102Does the 20% substrate repair mentioned in Note 4 on AD102 include the repair to the frieze board behind the gutters?No. Substrate repair 20% applies to roof deck replacement only.
15VALIANT ConstructionSolicitationWill the maintenance building be emptied and vacant for the duration of the project?No, grounds maintenance contractor staff and equipment will remain.
16VALIANT ConstructionSolicitationAre we to remove and dispose of the benches under the committal shelter we are demoing?Sheet CS102 note 7a - Specifies that these benches be restored.
17VALIANT ConstructionSolicitationWill the Owner provide the final certification of the lightning protection system?No, contractor shall be certifier that work was performed by Lightning Protection System Certified Installer and with UL listed components.
18VALIANT ConstructionNote 1.3 - C501Can the GC's superintendent on site serve as the the restoration supervisor?Yes
19VALIANT ConstructionNote 7.1 - C501Is the Owner responsible for hiring the Archtectural Conservator or Preservation Architect mentioned in note 7.1 on C501?This is a contractor responsibility for Quality Control and to follow proper restoration processes.
20VALIANT ConstructionAE201Can you please provide the sizes of the new aluminum windows?"A" unit is 3'-2"w x 3'-1/4"h "B" unit is 3'-8"w x 2'-8"h. Verify all window opng sizes in the field.
21VALIANT Construction6/L504Is there a specific location to obtain the "salvaged field stones" mentioned on 6/L504?The intent is to avoid purchasing and matching new stone to the existing. We recommend the reuse of salvaged stone removed from wall where the new limestone mounting stone is to be installed. The contactor is to take care with stone veneer removal to provide the required quantity of stones.
22VALIANT ConstructionSolicitationWill the owner accept Procore Project Management software as the primary submittal and data tracking tool for this project?Yes
23VALIANT ConstructionSolicitationIs this project tax-exempt, and will the CO/COR provide the necessary tax-exempt certificates?No tax exemption form will be provided.
24VALIANT ConstructionSolicitationBecause of COVID-19 throughout the U.S. and the resulting Federal, State and local governments’ responses/requirements, are there any new work requirements or mandates that will be required by the VA on this project?No, see contract clauses.
25VALIANT ConstructionSolicitationWhat is the approximate duration between issuing the award and issuing the NTP?The award and NTP will be issued the same day
26VALIANT ConstructionSolicitationFor planning the preliminary project schedule, please provide an anticipated award date.Bids pricing should be available to the Government . Award should be made within 90 days of bid reading.
27VALIANT ConstructionSolicitationHow many calendar days should be included in the critical-path method schedule for the owner and A/E to review and respond to RFIs?14 days
28VALIANT ConstructionSolicitationHow many calendar days should be included in the critical-path method schedule for owner and A/E submittal review?013217-3 1.6.A.3 [The duration for VA approval of any required submittal, shop drawing, or other submittals shall not be

less than ten (10) workdays.]

29VALIANT ConstructionSolicitationWill the Government provide the 3-D REVIT Design model in native file format for the creation of coordination drawings and use by contractor?AutoCAD files are available.
30VALIANT ConstructionSolicitationCan the contractor use the existing on-site utilities for temporary electrical and water free of charge?Electricity (for Construction and Testing): Furnish all temporary electric services.

Obtain electricity by connecting to the Cemetery electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Where not available or not convenient to connect to the Cemetery distribution system, the contractor shall supply power via portable generators at own expense. Generators shall be acoustically screened so as not to disturb committal services and/or visitation to the adjacent columbarium.

Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Cemetery irrigation distribution system. Backflow preventer may not be required at connections to the irrigation system. Water is available at no cost to the Contractor.

2. If potable water is required and convenient connection is available the contractor may connect to the Cemetery potable water distribution system. The contractor shall install reduced pressure backflow preventer at each connection at own expense.

3. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at VA COR's discretion) of use of water from the Cemetery's system.

31VALIANT ConstructionSolicitationPlease confirm that the project scope will be completed during normal working hours, not nights and weekends.Confirmed, work during normal working hours unless requested in advance to the COR and Cemetery.
32VALIANT ConstructionSolicitationCan the contractor use the existing restroom facilities in the work area or adjacent ones nearby?No, existing restrooms are reserved for visitors
33VALIANT ConstructionSolicitationCan the contractor use an existing office inside the building for a temporary construction office during construction instead of setting up a temporary trailer?No, building is currently occupied by grounds maintenance contractor.
34VALIANT ConstructionSolicitationHas the facility Operation & Maintenance team reviewed the Contract Documents for operability to avoid change orders?Yes, unknown what concern this is related to.
35VALIANT ConstructionSolicitationSpecifications section 01 35 26 para 1.7.C explains that SSHO has to be a separate qualified individual from the Prime Contractor’s Superintendent. Specifications section 01 45 00 para 3.4.B mandates that CQC System Manager can not have duties as project superintendent. Please confirm that the superintendent cannot dual hat as CQC or SSHO.The superintendent can be dual hatted as CQC or SSHO.