8-05-CR27005-26361490-Geotechnical Report.pdf
PDF 5 MB Posted
- Solicitation number
- CR27005
- Issued by
- Utah
About this file
This is a Geotechnical Investigation Report prepared by Applied Geotechnical Engineering Consultants, Inc. for McNeil Engineering, Inc., supporting a State of Utah Department of Facilities Construction and Management (DFCM) construction project at the Utah Veterans Cemetery in Bluffdale, Utah. The report documents subsurface conditions and engineering recommendations for the construction of three new columbarium walls as part of a cemetery expansion project (Project #26361490). The field investigation was conducted on February 20, 2026, utilizing two exploratory borings drilled to approximately 15 feet depth to characterize soil and bedrock conditions at the proposed construction sites located north and south of existing columbarium structures. The study includes laboratory testing of soil and bedrock samples, subsurface water measurements, and comprehensive geotechnical analysis to support foundation design and construction planning.
The investigation revealed subsurface conditions consisting of approximately 3 inches of topsoil overlying lean clay extending 2 to 3 feet below grade, with tuffaceous marlstone bedrock extending to the full boring depth. Key recommendations include spread footing foundations bearing on undisturbed bedrock or compacted structural fill at an allowable bearing pressure of 2,500 pounds per square foot, with minimum footing width of 2 feet and minimum embedment depth of 30 inches for frost protection. Site-specific conditions noted include subsurface water at approximately 9 feet depth in one boring location, the necessity for heavy-duty excavation equipment due to bedrock resistance, placement of 1 to 2 feet of granular borrow for equipment access, specific fill material and compaction requirements, and negligible sulfate attack potential on concrete. The report recommends a preconstruction meeting and continued geotechnical observation during excavation, earthwork, and foundation construction phases, with total and differential settlement estimated at less than ½ inch for properly constructed foundations.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GEOTECHNICAL INVESTIGATION
PROPOSED COLUMBARIUM WALLS
UTAH VETERANS CEMETERY
17111 SOUTH CAMP WILLIAMS ROAD
BLUFFDALE, UTAH
PREPARED FOR:
MCNEIL ENGINEERING, INC
8610 SOUTH SANDY PARKWAY, SUITE 200
SANDY, UT 84007
ATTENTION: CARL GREENE
PROJECT NO. 1260074 MARCH 17, 2026
AGC.,CAGC.,C
Applied Applied GeoTechGeoTech
600600 WWesest t SSandy andy Parkway Parkway • • SSandy, andy, Utah Utah 84070 84070 • • (801) (801) 566-6399 566-6399 • • www.agecinc.comwww.agecinc.com
TABLE OF CONTENTS
EXECUTIVE SUMMARY.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 1
SCOPE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 2
SITE CONDITIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 2
FIELD STUDY.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 3
SUBSURFACE CONDITIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 3
SUBSURFACE WATER. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 4
PROPOSED CONSTRUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 4
RECOMMENDATIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 4 A. Site Grading.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 4 B. Foundations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 7 C. Concrete Slab-on-Grade. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 8 D. Lateral Earth Pressure. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 9 E. Seismicity, Faulting and Liquefaction. . . . . . . . . . . . . . . . . . . . . . . . . . Page 10 F. Water Soluble Sulfates. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 11 G. Continuing Services. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 11
LIMITATIONS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 12
REFERENCES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page 13
FIGURES
EXPLORATORY BORING LOCATIONS FIGURE 1
EXPLORATORY BORING LOGS, LEGEND AND NOTES FIGURE 2
CONSOLIDATION TEST RESULTS FIGURES 3-5
SUMMARY OF LABORATORY TEST RESULTS TABLE I
EXECUTIVE SUMMARY
1. Approximately 3 inches of topsoil overlying lean clay was encountered in the borings. The clay extended to depths of approximately 2 to 3 feet below the ground surface. Bedrock consisting of tuffaceous marlstone was encountered below the clay to the full depth of the borings, approximately 15½ feet.
2. Subsurface water was measured in Boring B-2 at a depth of approximately 9½ feet below the ground surface based on a measurement taken on March 3, 2026.
No subsurface water was encountered in Boring B-1 at the time of drilling.
3. The proposed structures may be supported on spread footings bearing on the undisturbed bedrock or on compacted structural fill extending down to the undisturbed bedrock. The topsoil, unsuitable fill, clay, and other deleterious materials should be removed from below footing areas. If a footing would bear partially on bedrock and partially on compacted structural fill, at least 2 feet of structural fill should be provided below the footing or the footing extended down to bear entirely on the bedrock.
Footings bearing on the bedrock or compacted structural fill that extends down to the bedrock may be designed using a net allowable bearing pressure of 2,500 pounds per square foot.
4. We anticipate excavation in the bedrock will require heavy-duty excavation equipment. Resistant layers of bedrock may require jack-hammering or other rock excavation methods. Additional difficulty should be expected in confined excavations, such as utility trenches.
5. The upper soil generally has a high clay content and will be easily disturbed by construction equipment traffic when it is very moist to wet. Placement of approximately 1 to 2 feet of granular borrow consisting predominantly of gravel with less than 15 percent passing the No. 200 sieve may be needed to provide limited access for rubber-tired equipment.
6. Geotechnical information relating to foundations, subgrade preparation and materials is included in the report.
APPLIED GEOTECHNICAL ENGINEERING CONSULTANTS, INC. 1260074
SCOPE
This report presents the results of a geotechnical investigation for the proposed columbarium walls to be constructed at the Utah Veterans Cemetery at 17111 South Camp Williams Road in
Bluffdale, Utah. The report presents the subsurface conditions encountered, laboratory test results and recommendations for foundations. The study was conducted in general accordance with our proposal dated February 9, 2026.
Field exploration was conducted to obtain information on the subsurface conditions at the site.
Samples obtained from the field investigation were tested in the laboratory to determine physical and engineering characteristics of the on-site soil. Information obtained from the field and laboratory investigations was used to define conditions at the site and to develop recommendations for the proposed foundations.
This report has been prepared to summarize the data obtained during the study and to present our conclusions and recommendations based on the proposed construction and the subsurface conditions encountered. Design parameters and a discussion of geotechnical engineering considerations relating to construction are included in the report.
SITE CONDITIONS
There are two existing columbarium walls at the site. The structures are approximately 8 feet tall, 5 feet wide and 40 feet long. Concrete slabs surround the columbarium walls. The proposed columbarium walls are planned in the landscaped areas north and south of the existing structures.
The site is relatively flat with a gentle slope down to the north. There is a moderately steep slope up to the west beyond the site.
The site surrounding the existing structures and concrete slabs is landscaped with grass. There is an asphalt-paved access road east of the site.
FIELD STUDY
The field study was conducted on February 20, 2026. Two borings were drilled at the approximate locations shown on Figure 1. The borings were drilled with 8-inch-diameter hollow-stem auger. The borings were logged and samples obtained by a representative of AGEC. Logs of the subsurface conditions encountered in the borings are graphically shown on Figure 2.
SUBSURFACE CONDITIONS
Approximately 3 inches of topsoil overlying lean clay was encountered in the borings. The clay extended to depths of approximately 2 to 3 feet below the ground surface. Bedrock consisting of tuffaceous marlstone and micrite was encountered below the clay to the full depth of the borings, approximately 15½ feet.
A description of the soil and bedrock encountered in the borings follows:
Topsoil - The topsoil consists of sandy lean clay with occasional gravel. It is moist, dark brown and contains roots and organics.
Sandy Lean Clay - The clay is very stiff to hard, moist and brown.
Bedrock - The bedrock consists of tuffaceous marlstone. It is hard to very hard, slightly moist and gray.
Laboratory tests conducted on samples of the bedrock indicate it has natural moisture contents ranging from 20 to 24 percent and natural dry densities ranging from 100 to 109 pounds per cubic foot (pcf). Consolidation tests conducted on samples of the bedrock indicate it will compress a small to moderate amount with the addition of light to moderate loads. Results of the consolidation tests are presented on Figures 3, 4 and 5.
Results of the laboratory tests are summarized on Table I and are included on the boring logs.
SUBSURFACE WATER
Subsurface water was measured in Boring B-2 at a depth of approximately 9½ feet below the ground surface based on a measurement taken on March 3, 2026. No subsurface water was encountered in Boring B-1 at the time of drilling. Slotted PVC pipe was installed in Boring B-2 to facilitate measurement of the subsurface water level. Fluctuations in the subsurface water level should we expected over time.
PROPOSED CONSTRUCTION
We understand that three columbarium walls are planned to be constructed at the site. We understand that the structures will be constructed of reinforced concrete and granite. We have assumed that loads will be less than 4 kips per lineal foot.
If the proposed construction or loads are significantly different from those described above, we should be notified to reevaluate the recommendations given.
RECOMMENDATIONS
Based on the subsurface conditions encountered, laboratory test results and our understanding of the proposed construction, the following recommendations are given:
A. Site Grading
We have assumed that relatively small amounts of cut, likely 5 feet or less, may be required for the proposed columbarium walls and associated improvements.
1. Subgrade Preparation
Prior to placing grading fill, the topsoil, unsuitable fill, organic material and other deleterious materials should be removed.
The upper soil generally has a high clay content and will be easily disturbed by construction equipment traffic when it is very moist to wet. Placement of approximately 1 to 2 feet of granular borrow consisting predominantly of gravel with less than 15 percent passing the No. 200 sieve may be needed to provide limited access for rubber-tired equipment.
2. Excavation
We anticipate excavation in the bedrock will require heavy-duty excavation equipment. Resistant layers of bedrock may require jack-hammering and other rock excavation methods. Additional difficulty should be expected in confined excavations, such as utility trenches.
3. Temporary Excavation Slopes
Temporary unretained excavation slopes up to 10 feet in height in clay and bedrock may be constructed at 1 horizontal to 1 vertical or flatter. The excavator is responsible to provide safe working conditions around temporary excavation slopes.
4. Long-term Slopes
Long-term unretained slopes may be constructed at 2 horizontal to 1 vertical or flatter. Prior to placement of fill, the subgrade should be prepared by removing the topsoil, unsuitable fill, debris and other deleterious materials.
Slopes should be protected from erosion by revegetation, erosion control mats or other methods.
5. Materials
Listed below are recommendations for imported structural fill.
Fill to Support Recommendations
Footings Non-expansive granular soil Passing No. 200 Sieve < 35% Liquid Limit < 30% Maximum size 4 inches
Floor Slab (Upper 4 inches)
Sand and/or Gravel Passing No. 200 Sieve < 5% Maximum size 2 inches
Slab Support Non-expansive granular soil Passing No. 200 Sieve < 50% Liquid Limit < 30% Maximum size 6 inches
The on-site soil and bedrock may be considered for use as site grading fill outside of the structure area if the topsoil, debris, organics and other deleterious materials are removed or they may be used in landscaped areas.
The on-site materials may require wetting or drying prior to placement and compaction if used as fill. Drying of the soil and bedrock may not be practical during cold or wet times of the year.
6. Compaction
Compaction of materials placed at the site should equal or exceed the minimum densities as indicated below when compared to the maximum dry density as determined by ASTM D 1557.
Fill To Support Compaction
Foundations $ 95%
Concrete Flatwork $ 90%
Pavement Base Course Fill Placed Below Base Course
$ 95% $ 90%
Landscaping $ 85%
Retaining Wall Backfill 85 - 90%
To facilitate the compaction process, fill should be compacted at a moisture content within 2 percent of the optimum moisture content.
The fill should be placed and compacted in thin enough lifts to allow for proper compaction. Fill placed for the project should be frequently tested for compaction during construction.
7. Drainage
The ground surface surrounding the proposed structures should be sloped away from the structures in all directions.
B. Foundations
1. Bearing Material
The proposed structures may be supported on spread footings bearing on the undisturbed bedrock or on compacted structural fill extending down to the undisturbed bedrock. The topsoil, unsuitable fill, clay, and other deleterious materials should be removed from below footing areas.
If a footing would bear partially on bedrock and partially on compacted structural fill, at least 2 feet of structural fill should be provided below the footing or the footing extended down to bear entirely on the bedrock.
Where structural fill is placed below footings, the structural fill should extend out away from the edge of the footing at least a distance equal to the depth of structural fill below the footing.
2. Bearing Pressure
Footings bearing on the bedrock or compacted structural fill that extends down to the bedrock may be designed using a net allowable bearing pressure of
2,500 pounds per square foot. Footings should have a minimum width of 2 feet and a minimum depth of embedment of 1 foot.
3. Settlement
We estimate total and differential settlement will be less than ½ inch for footings bearing on the bedrock or on compacted structural fill.
Care should be taken to not disturb the bedrock at the base of footing excavations so that settlement can be maintained within tolerable limits. Loose material in the base of footing excavations should be removed or be compacted.
4. Temporary Loading Conditions
The allowable bearing pressure may be increased by one-half for temporary loading conditions such as wind or seismic loads.
5. Frost Depth
Footings should be placed at least 30 inches below grade for frost protection.
6. Foundation Base
The base of foundation excavations should be cleared of loose or deleterious material prior to fill or concrete placement.
7. Construction Observations
A representative of the geotechnical engineer should observe foundation excavations prior to structural fill and concrete placement.
C. Concrete Slab-on-Grade
1. Slab Support
Concrete slabs may be supported on the undisturbed natural soil, bedrock or on compacted structural fill extending down to the undisturbed natural soil or bedrock.
Unsuitable fill, topsoil, organics or other deleterious materials should be removed from below the proposed slabs.
2. Underslab Sand and/or Gravel
A 4-inch layer of free-draining sand and/or gravel (less than 5 percent passing the
No. 200 sieve) should be placed below the concrete slabs for ease of construction and to promote even curing of the slab concrete.
D. Lateral Earth Pressure
1. Lateral Resistance for Footings
Lateral resistance for footings placed on the bedrock or compacted structural fill is controlled by sliding resistance between the footing and the foundation soil or bedrock. A friction value of 0.35 may be used in design for ultimate lateral resistance for footings. The passive resistance of the soil adjacent footings may also be considered in design for lateral resistance of footings.
2. Subgrade Walls and Retaining Structures
The following equivalent fluid weights are given for design of subgrade walls and retaining structures. The active condition is where the wall moves away from the soil. The passive condition is where the wall moves into the soil and the at-rest condition is where the wall does not move.
Soil Type Active At-Rest Passive
Clay and Silt 50 pcf 65 pcf 250 pcf
Sand and Gravel 40 pcf 55 pcf 300 pcf
3. Seismic Conditions
Under seismic conditions, the equivalent fluid weight should be increased by 37 and 22 pcf for active and at-rest conditions, respectively, and decreased by 37 pcf for the passive condition. This assumes a peak horizontal ground acceleration of
0.62g which represents a 2 percent probability of exceedance in a 50-year period.
4. Safety Factors
The values recommended above assume mobilization of the soil to achieve the soil strength under active and passive conditions. Conventional safety factors used for structural analysis for such items as overturning and sliding resistance should be used in design.
E. Seismicity, Faulting and Liquefaction
1. Seismicity
Listed below is a summary of the site parameters for the 2021 International
Building Code.
Description Value
Site Class C1 s RS - MCE ground motion (period=0.2s) 1.17g
1 RS - MCE ground motion (period=1.0s) 0.43g aF - Site amplification factor at 0.2s 1.2
GPGA - MCE peak ground acceleration 0.52g
MPGA - Site modified peak ground acceleration 0.62g
Site Class C was selected based on the subsurface conditions encountered and1 our understanding of the geology in the area.
2. Faulting
There are no mapped active faults extending through the project site. The closest mapped fault considered active is the Wasatch Fault, mapped approximately 3½ miles east of the site (Utah Geological Survey, 2026).
3. Liquefaction
The site is located within an area mapped as having a "very low" potential for liquefaction (Salt Lake County, 2002).
Based on conditions encountered in the borings and understanding of the geology in the area, liquefaction is not considered to be a potential hazard at the site.
F. Water Soluble Sulfates
Based on the results of a water soluble sulfate test and our experience in the area, the soil and bedrock possess a negligible sulfate attack potential on concrete. No special cement type is required for concrete placed in contact with the soil or bedrock.
G. Continuing Services
A preconstruction meeting should be held with representatives of the owner, project architect, geotechnical engineer, general contractor, earthwork contractor and other members of the design team to review construction plans, specifications, methods and schedule.
The geotechnical engineer should observe the excavation, earthwork and foundation phases of the work to determine that subsurface conditions are consistent with those used in the analysis and design. During site grading and placement of structural fill, the work should be observed and tested to confirm that the proper density has been achieved.
LIMITATIONS
This report has been prepared in accordance with generally accepted soil and foundation engineering practices in the area for the use of the client for design purposes. The conclusions and recommendations included within the report are based on the information obtained from the borings drilled at the approximate locations indicated on Figure 1, the results of laboratory tests and our experience in the area. Variations in the subsurface conditions may not become evident until additional exploration or excavation is conducted. If the subsurface conditions, proposed construction or groundwater level is found to be significantly different from what is described above, we should be notified to reevaluate the recommendations given.
APPLIED GEOTECHNICAL ENGINEERING CONSULTANTS, INC.
Jay R. McQuivey, P.E.
Reviewed by Douglas R. Hawkes, P.E., P.G.
JRM/rs
3-17-2026
REFERENCES
International Code Council, 2020; 2021 International Building Code, Falls Church, Virginia.
City, Utah.
Salt Lake County, 2002; Surface Rupture and Liquefaction Potential Special Study Areas Map, Salt Lake County, Utah, adopted March 31, 1989, updated March 2002, Salt Lake County Public Works - Planning Division, 2001 South State Street, Salt Lake City, Utah.
Utah Geological Survey, 2026; Utah Geological Hazard Portal accessed March 13, 2026 at https://geology.utah.gov/apps/hazards/.
B-2
B-1
BM - Bottom of Columbarium Elev. 100' assumed
1260074 Exploratory Boring Locations Figure 1
PROPOSED COLUMBARIUM WALLS
UTAH VETERANS CEMETERY
17111 SOUTH CAMP WILLIAMS ROAD
BLUFFDALE, UTAH
0 60 120 feet Approximate Scale
AutoCAD SHX Text N
NOTES:
1. The borings were drilled on February 20, 2026 with 8-inch diameter hollow-stem auger.
2. The locations of the borings were measured approximately by pacing from features shown on Figure 1.
3. The elevations of the borings were measured by hand level and refer to the benchmark shown on Figure 1.
4. The boring locations and elevations should be considered accurate only to the degree implied by the method used.
5. The lines between materials shown on the boring logs represent the approximate boundaries between material types and the transitions may be gradual.
6. The water level readings shown on the logs were made at the time and under the conditions indicated. Fluctuations in the water will occur with time.
7. WC = Water Content (%);
DD = Dry Density (pcf);
-200 = Percent Passing the No. 200 Sieve;
LL = Liquid Limit (%);
PI = Plasticity Index (%);
WSS = Water Soluble Sulfates (%).
Indicates the depth to free water and the number of days after drilling the measurement was taken.
10/12
LEGEND:
California Drive sample taken. The symbol 10/12 indicates that 10 blows from a 140 pound automatic hammer falling 30 inches were required to drive the sampler 12 inches.
Indicates slotted 1½ inch diameter PVC pipe installed in the boring to the depth shown.
Sandy Lean Clay (CL); very stiff to hard, moist, brown.
Bedrock; tuffaceous marlstone, medium hard to hard, moist, light brown to greeinsh gray.
Topsoil; sandy lean clay, occasional gravel, moist, dark brown, roots and organics.
El ev at io n/ Fe et
Elev. 98½' Elev. 101½' B-1 B-2
El ev at io n/ Fe et
105 105
23/12
22/12
16/12
31/12
38/12
21/12
54/12
22/12
70/10
Assumed Base Elevation of Structure
Assumed Base Elevation of Structure
WC = 20
DD = 109
-200 = 76
LL = 46
PI = 32
WSS = 0.02
WC = 24
DD = 107
-200 = 54
LL = 41
PI = 17
WC = 21
DD = 100
-200 = 82
Exploratory Boring Logs, Legend and Notes Figure 2 Approximate Vertical Scale 1" = 8'
1260074
Applied Geotechnical Engineering Consultants, Inc.
APPLIED PRESSURE - ksf
0.1 1.0 10 100
C om pr es si on
Moisture Content 20 % Dry Unit Weight 109 pcf Sample of: Marlstone
From: B-1 @ 2 feet
Project No. 1260074
No movement upon wetting
CONSOLIDATION TEST RESULTS Figure 3
0.1 1.0 10 100
C om pr es si on
Moisture Content 21 % Dry Unit Weight 100 pcf Sample of: Marlstone
From: B-1 @ 9 feet
Expansion under constant pressure upon wetting
Project No. 1260074 CONSOLIDATION TEST RESULTS Figure 4
0.1 1.0 10 100
C om pr es si on
Moisture Content 24 % Dry Unit Weight 107 pcf Sample of: Marlstone
From: B-2 @ 4 feet
No movement upon wetting
Project No. 1260074 CONSOLIDATION TEST RESULTS Figure 5
APPLIED GEOTECHNICAL ENGINEERING CONSULTANTS, INC.
TABLE I
SUMMARY OF LABORATORY TEST RESULTS
PROJECT NUMBER: 1250074
SAMPLE
LOCATION NATURAL
MOISTURE
CONTENT
NATURAL
DRY
DENSITY
(PCF)
GRADATION ATTERBERG LIMITS UNCONFINED
COMPRESSIVE
STRENGTH
(PSF)
WATER
SOLUBLE
SULFATE
SAMPLE CLASSIFICATION
BORING DEPTH
(FEET)
GRAVEL
SAND
SILT/
CLAY
LIQUID LIMIT
PLASTICITY
INDEX
B-1 2 20 109 76 46 32 0.02 Marlstone
9 21 100 82 Marlstone
B-2 4 24 107 54 41 17 Marlstone
| EXECUTIVE SUMMARY |
| SCOPE |
| SITE CONDITIONS |
| FIELD STUDY |
| SUBSURFACE CONDITIONS |
| SUBSURFACE WATER |
| PROPOSED CONSTRUCTION |
| RECOMMENDATIONS |
| A. Site Grading |
| B. Foundations |
| C. Concrete Slab-on-Grade |
| D. Lateral Earth Pressure |
| E. Seismicity, Faulting and Liquefaction |
| F. Water Soluble Sulfates |
| G. Continuing Services |
| LIMITATIONS |
| REFERENCES |
| 1260074.Fig2.pdf |
| Sheets and Views |
| 2 |
| 1260074.Fig3.pdf |
| Sheets and Views |
| 3. |
| 1260074.Fig4.pdf |
| Sheets and Views |
| 4. |
| 1260074.Fig5.pdf |
| Sheets and Views |
| 5. |
File details come from the government source that posted it. Updated .