This document is a Clean Water Act Section 401 Water Quality Certification and Order issued by the Central Valley Regional Water Quality Control Board for the Cameron Creek Recharge Project in Tulare County, California. The project involves constructing three new reinforced concrete check structure facilities in Cameron Creek to utilize the creek as a linear groundwater recharge facility. The City of Visalia is the project applicant, with the project located across three parcels near Visalia. The certification is effective from 28 March 2025 to 28 March 2030, with the goal of increasing groundwater recharge through linear water pools that will percolate over time.
The project will construct three check structures equipped with control gates and weir boards capable of passing high flows (250 cubic feet per second) while maintaining high water levels in the channel. The project will result in 0.10 acres of permanent stream channel impacts, which will be mitigated by purchasing 0.10 Aquatic Resource Credits from the National Fish and Wildlife Foundation's Sacramento District California In-Lieu Fee Program. The total project area spans three check structure locations: Measurement Check, Rector Check, and Lovers Check, with specific latitude and longitude coordinates provided for each. The City of Visalia will be responsible for implementing best management practices, monitoring water quality, and ensuring compliance with various environmental regulations throughout the project's duration.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Central Valley Regional Water Quality Control Board
28 March 2025
Rebecca Keenan City of Visalia 315 East Acequia Avenue
Visalia, CA, 93291
CLEAN WATER ACT SECTION 401 WATER QUALITY CERTIFICATION AND ORDER
FOR THE CAMERON CREEK RECHARGE PROJECT (WDID# 5C54CR00154),
TULARE COUNTY
Enclosed please find a Clean Water Act Section 401 Water Quality Certification and Order, authorized by the Central Valley Regional Water Quality Control Board Executive Officer, Patrick Pulupa. This Order is issued to the City of Visalia for Cameron Creek Recharge Project (Project). Attachments A through G of the Enclosure are also part of the Order.
This Order is issued in response to an application submitted by the City of Visalia for proposed Project discharge to waters of the state to ensure that the water quality standards for all waters of the state impacted by the Project are met. You may proceed with your Project according to the terms and conditions of the enclosed Order.
Please review your Order carefully to ensure that you understand all aspects of the Order. Note that this Order requires reporting and notification. Requirements for the content of the reporting and notification requirements are detailed in Attachment D, including specifications for photo and map documentation during the Project. Written reports and notifications must be submitted using the Reporting and Notification Cover Sheet located in Attachment D, which must be signed by the Permittee or an authorized representative.
These reports, notifications, and other submissions must be submitted in a searchable Portable Document Format (PDF). Documents less than 50 MB must be emailed to:
centralvalleyfresno@waterboards.ca.gov. In the subject line of the email, include the Central Valley Water Board Contact, Project name, and WDID. Documents that are 50 MB or larger must be transferred to a disk and mailed to the Central Valley Water Board Contact.
mailto:centralvalleyfresno@waterboards.ca.gov
Cameron Creek Recharge Project Reg. Meas. ID: 459901 Place ID: 899480
If you require further assistance, please contact Brandon Salazar by phone at (559) 445-6278 or by email at Brandon.Salazar@waterboards.ca.gov. You may also contact me by phone at (559) 445-6042 or by email at Matt.Scroggins@waterboards.ca.gov.
Matthew S. Scroggins Senior Water Resource Control Engineer
Enclosures (2): 1. Clean Water Act Section 401 Water Quality Certification and Order for Cameron Creek Recharge Project
2. Water Quality Order No. 2003-0017-DWQ cc: [Via email only] (w/ enclosure):
Ashley Bernard (SPK-2024-00616) United States Army Corps of Engineers Sacramento District Headquarters Regulatory Division Ashley.C.Bernard@usace.army.mil
United States Environmental Protection Agency Region 9 R9cwa401@epa.gov
Justin Sloan United States Fish & Wildlife Service justin_sloan@fws.gov
California Department of Fish and Wildlife, Region 4 R4LSA@wildlife.ca.gov
CWA Section 401 WQC Program Division of Water Quality State Water Resources Control Board Stateboard401@waterboards.ca.gov
Kira McCall Provost & Pritchard Consulting Group mailto:Brandon.Salazar@waterboards.ca.gov mailto:Matt.Scroggins@waterboards.ca.gov
Central Valley Regional Water Quality Control Board
CLEAN WATER ACT SECTION 401 WATER QUALITY CERTIFICATION AND ORDER
Effective Date: 28 March 2025
Expiration Date: 28 March 2030
Program Type: Fill/Excavation
Reg. Meas. ID: 459901 Place ID: 899480 WDID No.: 5C54CR00154 USACE No.: SPK-2024-00616
Project Type: Channel Construction and Maintenance
Project: Cameron Creek Recharge Project (Project)
Applicant: City of Visalia
Applicant Contact: Rebecca Keenan City of Visalia 315 East Acequia Avenue Visalia, CA, 93291 Phone: (559) 713-4541 Email: rebecca.keenan@visalia.city
Applicant’s Agent: Kira McCall Provost & Pritchard Consulting Group 1518 Mill Rock Way, Suite 100 Bakersfield, CA 93311 Phone: (661) 616-5900 Email: kmccall@ppeng.com
Water Board Staff: Brandon Salazar Water Resource Control Engineer 1685 E Street Fresno, CA 93706 Phone: (559) 445-6278 Email: Brandon.Salazar@waterboards.ca.gov
Water Board Contact Person: If you have any questions, please call Regional Water Quality Control Board, Central Valley Region (Central Valley Water Board) Staff listed above or (559) 445-5116 and ask to speak with the Water Quality Certification Unit Supervisor.
Cameron Creek Recharge Project Reg. Meas.ID: 459901
Table of Contents
I. Order
II. Public Notice
III. Project Purpose
IV. Project Description
V. Project Location
VI. Project Impact and Receiving Waters Information
VII. Description of Direct Impacts to Waters of the State
VIII. Description of Indirect Impacts to Waters of the State – Not Applicable
IX. Avoidance and Minimization
X. Compensatory Mitigation
XI. California Environmental Quality Act (CEQA)
XII. Petitions for Reconsideration
XIII. Fees Received
XIV. Conditions
XV. Water Quality Certification
Attachment A – Project Maps ....................................................................................A-1
Attachment B – Receiving Waters, Impacts and Mitigation Information ....................B-1
Attachment C – CEQA Findings of Fact ................................................................... C-1
Attachment D – Reports and Notification Requirements .......................................... D-1
Attachment E – Signatory Requirements ...................................................................E-1
Attachment F – Certification Deviation Procedures ................................................... F-1
Attachment G - Compliance with Code of Federal Regulations, Title 40, Section 121.7, Subdivision (d) .......................................................................................................... G-1
I. Order
This Clean Water Act (CWA) section 401 Water Quality Certification action and Order (Order) is issued at the request of the City of Visalia (hereinafter Permittee) for the Project. This Order is for the purpose described in application submitted by the Permittee. The application was received on 29 January 2025. The application was deemed complete on 27 February 2025.
II. Public Notice
The Central Valley Water Board provided public notice of the application pursuant to California Code of Regulations, title 23, section 3858 from 7 February 2025 to 28 February 2025. The Central Valley Water Board did not receive any comments during the comment period.
III. Project Purpose
The Project proposes to construct three new reinforced concrete check structure facilities in Cameron Creek to utilize the creek as a linear, groundwater recharge facility.
IV. Project Description
The Project proposes to construct three new reinforced concrete check structure facilities in Cameron Creek (Creek) to utilize the Creek as a linear recharge facility.
The goal is to increase groundwater recharge through linear water pools that would percolate over time. The three check structures would be equipped with control gates and weir boards capable of passing high flows (250 cubic feet per second) while maintaining high water levels in the channel.
V. Project Location
County: Tulare
Assessor’s Parcel Number(s): 128-020-061, 127-030-038, 127-020-031
Nearest City: Visalia
Measurement Check Structure:
Latitude: 36.317048 Degrees and Longitude: -119.224292 Degrees
Rector Check Structure:
Latitude: 36.307447 Degrees and Longitude: -119.244043 Degrees
Lovers Check Structure:
Latitude: 36.298663 Degrees and Longitude: -119.260407 Degrees
Maps showing the Project location are found in Attachment A of this Order.
VI. Project Impact and Receiving Waters Information
The Project is located within the jurisdiction of the Central Valley Water Board.
Receiving waters and groundwater potentially impacted by this Project are protected in accordance with the Water Quality Control Plan for the Tulare Lake Basin, revised Third Edition, May 2018 (Basin Plan) The plan for the region and other plans and policies may be accessed at the State Water Resources Control Board's Plans and Policies Web page (http://www.waterboards.ca.gov/plans_policies/). The Basin Plan includes water quality standards, which consist of existing and potential beneficial uses of waters of the state, water quality objectives to protect those uses, and the state and federal antidegradation policies.
It is the policy of the State of California that every human being has the right to safe, clean, affordable, and accessible water adequate for human consumption, cooking, and sanitary purposes. This Order promotes that policy by requiring discharges to meet maximum contaminant levels designed to protect human health and ensure that water is safe for domestic use.
Project impact and receiving waters information can be found in Attachment B. Table 1 of Attachment B shows the receiving waters and beneficial uses of waters of the state impacted by the Project. Individual impact location and quantity is shown in Table 2 of Attachment B.
VII. Description of Direct Impacts to Waters of the State
Temporary impacts to install the check structure facilities in each location would result from the over-excavation of soil to prepare for construction followed by backfill around the structure. These areas would be backfilled after construction of each check structure facility is complete. Permanent impacts to the Creek at each location are due to the excavation of the channel for the check structures, construction of cutoff wall, and placement of concrete and rock slope protection.
Total Project fill/excavation quantities for all impacts are summarized in Tables 1 and
2. Permanent impacts are categorized as those resulting in a physical loss in area and also those degrading ecological condition.
Table 1: Total Project Fill/Excavation Quantity for Temporary Impacts1
Aquatic Resources Type Acres Cubic Yards Linear Feet
Lake
Ocean/bay/estuary
1 Includes only temporary direct impacts to waters of the state and does not include area of temporary disturbance which could result in a discharge to waters of the state. Temporary impacts, by definition, are restored to pre-project conditions and therefore do not include a physical loss of area or degradation of ecological condition.
http://www.waterboards.ca.gov/plans_policies/ http://www.waterboards.ca.gov/plans_policies/
Aquatic Resources Type Acres Cubic Yards Linear Feet
Riparian Zone
Stream Channel 0.008 239.5 168
Vernal Pool
Wetland
Table 2: Total Project Fill/Excavation Quantity for Permanent Physical Loss of Area Impacts
Aquatic Resources Type Acres Cubic Yards Linear Feet
Lake
Ocean/bay/estuary
Riparian Zone
Stream Channel 0.10 241 168
Vernal Pool
Wetland
VIII. Description of Indirect Impacts to Waters of the State – Not Applicable
IX. Avoidance and Minimization
To minimize the potential effects of construction on water quality and resources, the Permittee shall implement all measures required as described in the Order.
According to the Permittee, the following measures will be in place during construction activities to avoid, reduce, and minimize impacts to waters of the state:
Best Management Practices (BMPs) may be utilized during Project activities under the discretion of the contractor, including the following but not limited to:
• The Project contractor will be required to provide, implement, and maintain a Storm Water Pollution Prevention Plan for the construction areas for the duration of the Project, in accordance with State regulations.
• Cleaning of vehicles and equipment with soap, solvents, or steam will not occur on the job site;
• Vehicles and equipment will be inspected each day prior to use for leaks.
Leaks will be repaired immediately, or problem vehicles or equipment will be removed from the Project site;
• No fueling or servicing will be done in or near a water source;
• For stationary equipment that must be fueled or serviced on-site, containment will be provided in such a manner that any accidental spill will not be able to come in direct contact with soil, or surface water;
• Fertilizers and pesticides will not be used;
• Spill prevention kits will always be in close proximity if using hazardous materials (e.g., at crew trucks and other logical locations), and all field personnel will be advised of these locations;
• Field personnel will be appropriately trained in spill prevention, hazardous material control, and clean-up of accidental spills;
• Equipment and materials for cleanup of spills will be available on site, and spills and leaks will be cleaned up immediately and disposed of according to applicable regulatory requirements; and
• Field personnel will ensure that hazardous materials are properly handled, and natural resources are protected by all reasonable means.
Additionally, protection measures specific to concrete activities can be found in Section Eight of the application form that was submitted.
X. Compensatory Mitigation
The Permittee has agreed to provide compensatory mitigation for direct impacts, described in section XII for permanent impacts.
XI. California Environmental Quality Act (CEQA)
On 11 October 2024, the City of Visalia, as lead agency, adopted an initial study/mitigated negative declaration (IS/MND) (State Clearinghouse (SCH) No.
2024100477) for the Project and filed a Notice of Determination (NOD) at the SCH on 20 November 2024. Pursuant to CEQA, the Central Valley Water Board has made Findings of Facts (Findings) which support the issuance of this Order and are included in Attachment C.
XII. Petitions for Reconsideration
Any person aggrieved by this action may petition the State Water Board to reconsider this Order in accordance with California Code of Regulations, title 23, section 3867. A petition for reconsideration must be submitted in writing and received within 30 calendar days of the issuance of this Order.
XIII. Fees Received
A. An application fee of $4,212.00 was received on 31 January 2025. The fee amount was determined as required by California Code of Regulations, title 23, sections 3833(b)(3) and 2200(a)(3) and was calculated as Category A - Fill & Excavation Discharges (fee code 84) with the dredge and fill fee calculator.
B. Annual Fees: This Certification is subject to annual billing based on the fee schedule in effect at the time of billing. Annual billing will continue until the Project, including monitoring, is complete and the Central Valley Water Board receives an acceptable request for a Notice of Project Complete Letter (see
Attachment D). Annual invoices for fill and excavation projects are issued for projects active for any amount of time in the current fiscal year (July 1 – June 30). Annual invoices for dredging projects are based on the quantity of dredged material in the previous fiscal year. Invoices are usually sent out at the end of each calendar year.
To stop annual billing, the Permittee must request a Notice of Project Complete Letter from the Central Valley Water Board. Central Valley Water Board staff will verify if the conditions of the Certification are met and may conduct a site visit to confirm compliance.
For more information on fees, visit the State Water Board’s Water Quality Fees Web page (https://www.waterboards.ca.gov/resources/fees/water_quality/), under Water Quality Certification (WQC) Program Fees.
XIV. Conditions
The Central Valley Water Board has independently reviewed the record of the Project to analyze impacts to water quality and designated beneficial uses within the watershed of the Project. In accordance with this Order, the Permittee may proceed with the Project under the following terms and conditions:
A. Authorization
Impacts to waters of the state shall not exceed quantities shown in Tables 1 and 2.
B. Reporting and Notification Requirements
The following section details the reporting and notification types and timing of submittals. Requirements for the content of these reporting and notification types are detailed in Attachment D, including specifications for photo and map documentation during the Project. Written reports and notifications must be submitted using the Reporting and Notification Cover Sheet located in Attachment D, which must be signed by the Permittee or an authorized representative.
The Permittee must submit all notifications, submissions, materials, data, correspondence, and reports in a searchable Portable Document Format (PDF).
Documents less than 50 MB must be emailed to:
centralvalleyfresno@waterboards.ca.gov.
In the subject line of the email, include the Central Valley Water Board Contact, Project Name, and WDID No. Documents that are 50 MB or larger must be transferred to a disk and mailed to the Central Valley Water Board Contact.
Project Reporting
a. Monthly Reporting – Not Applicable
b. Annual Reporting: The Permittee shall submit an Annual Report each https://www.waterboards.ca.gov/resources/fees/water_quality/ https://www.waterboards.ca.gov/resources/fees/water_quality/ https://www.waterboards.ca.gov/resources/fees/water_quality/ year on the 1st day of the month, one year after the effective date of the Order. Annual reporting shall continue until the Central Valley Water Board issues a Notice of Project Complete Letter to the Permittee.
Project Status Notifications
a. Commencement of Construction: The Permittee shall submit a Commencement of Construction Report at least seven (7) days prior to start of initial ground disturbance activities and corresponding Waste Discharge Identification Number (WDID No.) issued under the NPDES General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities (Order No. 2022-0057-DWQ; NPDES No.
CAS000002).
b. Request for Notice of Completion of Discharges Letter: The Permittee shall submit a Request for Notice of Completion of Discharges Letter following completion of active Project construction activities, including any required restoration and permittee-responsible mitigation. This request shall be submitted to the Central Valley Water Board staff within thirty (30) days following completion of all Project construction activities. Upon acceptance of the request, Central Valley Water Board staff shall issue a Notice of Completion of Discharges Letter to the Permittee which will end the active discharge period.
c. Request for Notice of Project Complete Letter: The Permittee shall submit a Request for Notice of Project Complete Letter when construction and/or any post-construction monitoring is complete, and no further Project activities will occur. Completion of post-construction monitoring shall be determined by Central Valley Water Board staff and shall be contingent on successful attainment of restoration and mitigation performance criteria. This request shall be submitted to Central Valley Water Board staff within thirty (30) days following completion of all Project activities. Upon approval of the request, the Central Valley Water Board staff shall issue a Notice of Project Complete Letter to the Permittee which will end the post discharge monitoring period.
Conditional Notifications and Reports:
The following notifications and reports are required as appropriate.
a. Accidental Discharges of Hazardous Materials2
2 "Hazardous material" means any material that, because of its quantity, concentration, or physical or chemical characteristics, poses a significant present or potential hazard to human health and safety or to the environment if released into the workplace or the environment. "Hazardous materials" include, but are not limited to, hazardous substances, hazardous waste, and any material that a handler or the
Following an accidental discharge of a reportable quantity of a hazardous material, sewage, or an unknown material, the following applies (Water Code, Section 13271):
i. As soon as (A) Permittee has knowledge of the discharge or noncompliance, (B) notification is possible, and (C) notification can be provided without substantially impeding cleanup or other emergency measures then:
• first call – 911 (to notify local response agency)
• then call – Office of Emergency Services (OES) State Warning Center at:(800) 852-7550 or (916) 845-8911
• Lastly, follow the required OES, procedures as set forth in the Office of Emergency Services’ Accidental Discharge Notification Web page (http://www.caloes.ca.gov/FireRescueSite/Documents/CalOES- Spill_Booklet_Feb2014_FINAL_BW_Acc.pdf).
ii. Following notification to OES, the Permittee shall notify Central Valley Water Board, as soon as practicable (ideally within 24 hours).
Notification may be delivered via written notice, email, or other verifiable means.
iii. Within five (5) working days of notification to the Central Valley Water Board, the Permittee must submit an Accidental Discharge of Hazardous Material Report.
b. Violation of Compliance with Water Quality Standards:
The Permittee shall notify the Central Valley Water Board of any event causing a violation of compliance with water quality standards. Notification may be delivered via written notice, email, or other verifiable means.
i. This notification must be followed within three (3) working days by submission of a Violation of Compliance with Water Quality Standards Report.
c. In-Water Work and Diversions:
i. The Permittee shall notify the Central Valley Water Board at least forty-eight (48) hours prior to initiating work in water or stream diversions.
Notification may be delivered via written notice, email, or other verifiable means.
ii. Within three (3) working days following completion of work in water or administering agency has a reasonable basis for believing that it would be injurious to the health and safety of persons or harmful to the environment if released into the workplace or the environment. (Health & Safety Code, Section 25501.)
http://www.caloes.ca.gov/FireRescueSite/Documents/CalOES-Spill_Booklet_Feb2014_FINAL_BW_Acc.pdf http://www.caloes.ca.gov/FireRescueSite/Documents/CalOES-Spill_Booklet_Feb2014_FINAL_BW_Acc.pdf stream diversions, an In-Water Work/Diversions Water Quality Monitoring Report must be submitted to Central Valley Water Board staff.
d. Modifications to Project:
Project modifications may require an amendment of this Order. The Permittee shall give advance notice to Central Valley Water Board staff if Project implementation as described in the application materials is altered in any way or by the imposition of subsequent permit conditions by any local, state or federal regulatory authority by submitting a Modifications to Project Report. The Permittee shall inform Central Valley Water Board staff of any Project modifications that will interfere with the Permittee’s compliance with this Order. Notification may be made in accordance with conditions in the certification deviation section of this Order.
e. Transfer of Property Ownership:
This Order is not transferable in its entirety or in part to any person or organization except after notice to the Central Valley Water Board in accordance with the following terms:
i. The Permittee must notify the Central Valley Water Board of any change in ownership or interest in ownership of the Project area by submitting a Transfer of Property Ownership Report. The Permittee and purchaser must sign and date the notification and provide such notification to the Central Valley Water Board at least 10 days prior to the transfer of ownership. The purchaser must also submit a written request to the Central Valley Water Board to be named as the permittee in a revised order.
ii. Until such time as this Order has been modified to name the purchaser as the permittee, the Permittee shall continue to be responsible for all requirements set forth in this Order.
f. Transfer of Long-Term BMP Maintenance:
If maintenance responsibility for post-construction BMPs is legally transferred, the Permittee must submit to the Central Valley Water Board a copy of such documentation and must provide the transferee with a copy of a long-term BMP maintenance plan that complies with manufacturer or designer specifications. The Permittee must provide such notification to the Central Valley Water Board with a Transfer of Long-Term BMP Maintenance Report at least 10 days prior to the transfer of BMP maintenance responsibility.
C. Water Quality Monitoring
1. General:
If surface water is present, continuous visual surface water monitoring shall be conducted during active construction periods to detect accidental discharge of construction related pollutants (e.g., oil and grease, turbidity plume, or uncured concrete). Sampling is not required in a wetland where the entire wetland is being permanently filled, provided there is no outflow connecting the wetland to surface waters. The Permittee shall perform surface water sampling:
a. when performing any in-water work;
b. during the entire duration of temporary surface water diversions;
c. in the event that the Project activities result in any materials reaching surface waters; or
d. when any activities result in the creation of a visible plume in surface waters.
2. Accidental Discharges/Noncompliance:
Upon occurrence of an accidental discharge of hazardous materials or a violation of compliance with a water quality standard, Central Valley Water Board staff may require water quality monitoring based on the discharge constituents and/or related water quality objectives and beneficial uses.
3. In-Water Work or Diversions:
During planned in-water work, dewatering activities, or during the installation or removal of temporary water diversions, any discharge(s) to waters of the state shall conform to the following water quality standards:
a. Waters shall not contain oils, greases, waxes, or other materials in concentrations that cause nuisance, result in a visible film or coating on the surface of the water or on objects in the water, or otherwise adversely affect beneficial uses.
b. The pH of water shall not be depressed below 6.5, raised above 8.3, or changed at any time more than 0.3 units from normal ambient pH.
c. Activities shall not cause turbidity increases in surface water to exceed:
i. where natural turbidity is between 0 and 5 Nephelometric Turbidity Units (NTUs), increases shall not exceed 1 NTU;
ii. where natural turbidity is between 5 and 50 NTUs, increases shall not exceed 20 percent;
iii. where natural turbidity is equal to or between 50 and 100 NTUs, increases shall not exceed 10 NTUs;
iv. where natural turbidity is greater than 100 NTUs, increases shall not exceed 10 percent.
In determining compliance with the above limits, appropriate averaging periods may be applied provided that beneficial uses will be fully protected. Averaging periods may only be used with prior permission of the Central Valley Water Board Executive Officer.
d. Elevated temperature wastes shall not cause the temperature of waters designated COLD or WARM to increase by more than 5 degrees Fahrenheit above natural receiving water temperature.
Sampling during in-water work or during the entire duration of temporary water diversions shall be conducted in accordance with Table 3 sampling parameters.3 The sampling requirements in Table 3 shall be conducted upstream out of the influence of the Project, and approximately 300 feet downstream of the work area.
The sampling frequency and/or monitoring locations may be modified for certain projects with written approval from Central Valley Water Board staff.
An In-Water Work and Diversion Water Quality Monitoring Report, as described in Attachment D, shall be submitted within two weeks of initiation of in-water construction, and every two weeks thereafter. In reporting the data, the Permittee shall arrange the data in tabular form so that the sampling locations, date, constituents, and concentrations are readily discernible. The data shall be summarized in such a manner to illustrate clearly whether the Project complies with Order requirements. The report shall include surface water sampling results, visual observations, and identification of the turbidity increase in the receiving water applicable to the natural turbidity conditions specified in the turbidity criteria in XIV.C.3
If no sampling is required, the Permittee shall submit a written statement stating, “No sampling was required” within two weeks of initiation of in-water construction, and every two weeks thereafter.
Table 3: Sample Type and Frequency Requirements
Parameter Unit of
Measurement Type of Sample
Minimum Frequency
Dissolved Oxygen mg/L and % saturation
Grab Every 4 Hours pH Standard Units Grab Every 4 hours
3 Pollutants shall be analyzed using the analytical methods described in 40 Code of
Federal Regulations Part 136; where no methods are specified for a given pollutant, the method shall be approved by Central Valley Water Board staff. Grab samples shall be taken between the surface and mid-depth and not be collected at the same time each day to get a complete representation of variations in the receiving water. A hand-held field meter may be used, provided the meter utilizes a U.S. EPA-approved algorithm/method and is calibrated and maintained in accordance with the manufacturer’s instructions. A calibration and maintenance log for each meter used for monitoring shall be maintained onsite.
Parameter Unit of
Measurement Type of Sample
Minimum Frequency
Turbidity NTU Grab Every 4 hours
Temperature Degrees F (or as degrees C)
Grab Every 4 hours
Visible construction related pollutants4
Observations Visual
Inspections
Continuous throughout the construction period
Post-Construction:
Visually inspect the Project site during the rainy season for one year following completion of active Project construction activities to ensure excessive erosion, stream instability, or other water quality pollution is not occurring in or downstream of the Project site. If water quality pollution is occurring, contact the Central Valley Water Board staff member overseeing the Project within three (3) working days. The Central Valley Water Board may require the submission of a Violation of Compliance with Water Quality Standards Report. Additional permits may be required to carry out any necessary site remediation.
D. Standard
1. This Order is subject to modification or revocation upon administrative or judicial review, including review and amendment pursuant to Water Code section 13330, and California Code of Regulations, title 23, Chapter 28, article 6 commencing with sections 3867-3869, inclusive. Additionally, the Central Valley Water Board reserves the right to suspend, cancel, or modify and reissue this Order, after providing notice to the Permittee, if the Central Valley Water Board determines that: the Project fails to comply with any of the conditions of this Order; or, when necessary to implement any new or revised water quality standards and implementation plans adopted or approved pursuant to the Porter-Cologne Water Quality Control Act (Water Code, section 13000 et seq.) or federal Clean Water Act section 303 (33 U.S.C.
section 1313). For purposes of Clean Water Act section 401(d), the condition constitutes a limitation necessary to assure compliance with water quality standards and appropriate requirements of state law.
2. This Order is not intended and shall not be construed to apply to any activity involving a hydroelectric facility requiring a Federal Energy Regulatory Commission (FERC) license or an amendment to a FERC license, unless the pertinent certification application was filed pursuant to subsection 3855(b) of
4 Visible construction-related pollutants include oil, grease, foam, fuel, petroleum products, and construction-related, excavated, organic or earthen materials.
chapter 28, title 23 of the California Code of Regulations, and that application specifically identified that a FERC license or amendment to a FERC license for a hydroelectric facility was being sought.
3. This Order is conditioned upon total payment of any fee required under title 23 of the California Code of Regulations and owed by the Permittee.
4. In the event of any violation or threatened violation of the conditions of this Order, the violation or threatened violation shall be subject to any remedies, penalties, process, or sanctions as provided for under state and federal law.
For purposes of Clean Water Act, section 401(d), the applicability of any state law authorizing remedies, penalties, processes, or sanctions for the violation or threatened violation constitutes a limitation necessary to assure compliance with the water quality standards and other pertinent requirements incorporated into this Order.
E. General Compliance
1. Failure to comply with any condition of this Order shall constitute a violation of the Porter-Cologne Water Quality Control Act and the Clean Water Act. The Permittee and/or discharger may then be subject to administrative and/or civil liability pursuant to Water Code section 13385.
2. Permitted actions must not cause a violation of any applicable water quality standards, including impairment of designated beneficial uses for receiving waters as adopted in the Basin Plans by any applicable Regional Water Board or any applicable State Water Board (collectively Water Boards) water quality control plan or policy. The source of any such discharge must be eliminated as soon as practicable.
3. In response to a suspected violation of any condition of this Order, the Central Valley Water Board may require the holder of this Order to furnish, under penalty of perjury, any technical or monitoring reports the Water Boards deem appropriate, provided that the burden, including costs, of the reports shall bear a reasonable relationship to the need for the reports and the benefits to be obtained from the reports. The additional monitoring requirements ensure that permitted discharges and activities comport with any applicable effluent limitations, water quality standards, and/or other appropriate requirement of state law.
4. The Permittee must, at all times, fully comply with engineering plans, specifications, and technical reports submitted to support this Order; and all subsequent submittals required as part of this Order. The conditions within this Order and Attachments supersede conflicting provisions within Permittee submittals.
5. This Order and all of its conditions contained herein continue to have full force and effect regardless of the expiration or revocation of any federal license or permit issued for the Project. For purposes of Clean Water Act, section
401(d), this condition constitutes a limitation necessary to assure compliance with the water quality standards and other pertinent requirements of state law.
6. Construction General Permit Requirement: The Permittee shall obtain coverage under the National Pollutant Discharge Elimination System (NPDES) General Permit for Stormwater Discharges Associated with Construction and Land Disturbance Activities (Order No. 2022-0057-DWQ;
NPDES No. CAS000002), as amended, for discharges to surface waters comprised of storm water associated with construction activity, including, but not limited to, demolition, clearing, grading, excavation, and other land disturbance activities of one or more acres, or where projects disturb less than one acre but are part of a larger common plan of development that in total disturbs one or more acres.
F. Administrative
1. Signatory requirements for all document submittals required by this Order are presented in Attachment E of this Order.
2. This Order does not authorize any act which results in the taking of a threatened, endangered or candidate species or any act, which is now prohibited, or becomes prohibited in the future, under either the California Endangered Species Act (Fish & Wildlife Code, sections 2050-2097) or the federal Endangered Species Act (16 U.S.C. sections 1531-1544). If a “take” will result from any act authorized under this Order held by the Permittee, the Permittee must comply with the California Endangered Species Act and federal Endangered Species Act prior to any construction or operation of the portion of the Project that may result in a take. The Permittee is responsible for meeting all requirements of the applicable endangered species act for the Project authorized under this Order.
3. The Permittee shall grant Central Valley Water Board staff, or an authorized representative (including an authorized contractor acting as a Water Board representative), upon presentation of credentials and other documents as may be required by law, permission to:
a. Enter upon the Project or compensatory mitigation site(s) premises where a regulated facility or activity is located or conducted, or where records are kept.
b. Have access to and copy any records that are kept and are relevant to the Project or the requirements of this Order.
c. Inspect any facilities, equipment (including monitoring and control equipment), practices, or operations regulated or required under this Order.
d. Sample or monitor for the purposes of assuring Order compliance.
4. A copy of this Order shall be provided to any consultants, contractors, and subcontractors working on the Project. Copies of this Order shall remain at the Project site for the duration of this Order. The Permittee shall be responsible for work conducted by its consultants, contractors, and any subcontractors.
5. A copy of this Order must be available at the Project site(s) during construction for review by site personnel and agencies. All personnel performing work on the Project shall be familiar with the content of this Order and its posted location at the Project site.
6. Lake or Streambed Alteration Agreement: The Permittee shall submit a signed copy of the California Department of Fish and Wildlife’s Lake or Streambed Alteration Agreement to the Central Valley Water Board immediately upon execution and prior to any discharge to waters of the state.
G. Construction
1. Dewatering
a. The Permittee shall develop and maintain on-site a Surface Water Diversion and/or Dewatering Plan(s). The Plan(s) must be developed prior to initiation of any water diversions. The Plan(s) shall include the proposed method and duration of diversion activities and include water quality monitoring conducted, as described in section XIV.C.3, during the entire duration of dewatering and diversion activities. The Plan(s) must be consistent with this Order and must be made available to the Central Valley Water Board staff upon request.
b. For any temporary dam or other artificial obstruction being constructed, maintained, or placed in operation, sufficient water shall at all times be allowed to pass downstream, to maintain beneficial uses of waters of the state below the dam. Construction, dewatering, and removal of temporary cofferdams shall not violate section XIV.C.3.
c. The temporary dam or other artificial obstruction shall only be built from clean materials such as sandbags, gravel bags, water dams, or clean/washed gravel which will cause little or no siltation. Stream flow shall be temporarily diverted using gravity flow through temporary culverts/pipes or pumped around the work site with the use of hoses.
d. This Order does not allow permanent water diversion of flow from the receiving water. This Order is invalid if any water is permanently diverted as a part of the Project.
e. The Permittee shall work with the Central Valley Water Board to obtain coverage under an NPDES permit for dewatering activities that result in discharges into surface water. The Permittee shall work with the Central Valley Water Board to obtain coverage under Waste Discharge
Requirements (WDRs) for dewatering activities that result in discharges to land.
2. Directional Drilling – Not Applicable
3. Dredging – Not Applicable
4. Fugitive Dust:
Dust abatement activities can cause discharges of sediment to streams and uplands through application of water or other fluids. Dust abatement chemicals added to water can be hazardous to wildlife and, if allowed to enter streams, detrimental to water quality. Therefore, dust abatement activities shall be conducted so that sediment or dust abatement chemicals are not discharged into waters of the state. Dust abatement products or additives that are known to be detrimental to water quality or wildlife shall not be used, unless specific management needs are documented, and product-specific application plans are approved by Central Valley Water Board staff.
Good Site Management “Housekeeping”
a. The Permittee shall develop and maintain onsite a project-specific Spill Prevention, Containment and Cleanup Plan outlining the practices to prevent, minimize, and/or clean up potential spills during construction of the Project. The Plan must detail the Project elements, construction equipment types and location, access and staging and construction sequence. The Plan must be made available to the Central Valley Water Board staff upon request.
b. Refueling of equipment within the floodplain or within 300 feet of the waterway is prohibited. If critical equipment must be refueled within 300 feet of the waterway, spill prevention and countermeasures must be implemented to avoid spills. Refueling areas shall be provided with secondary containment including drip pans and/or placement of absorbent material. No hazardous materials, pesticides, fuels, lubricants, oils, hydraulic fluids, or other construction-related potentially hazardous substances should be stored within a floodplain or within 300 feet of a waterway. The Permittee must perform frequent inspections of construction equipment prior to utilizing it near surface waters to ensure leaks from the equipment are not occurring and are not a threat to water quality.
c. All waste materials resulting from the Project shall be removed from the site and disposed of properly.
Hazardous Materials
a. The discharge of petroleum products, any construction materials, hazardous materials, pesticides, fuels, lubricants, oils, hydraulic fluids, raw cement, concrete or the washing thereof, asphalt, paint, coating material, drilling fluids, or other substances potentially hazardous to fish and wildlife resulting from or disturbed by project-related activities is prohibited and shall be prevented from contaminating the soil and/or entering waters of the state. In the event of a prohibited discharge, the Permittee shall comply with notification requirements in sections XIV.B.3.a and XIV.B.3.b.
b. Wet concrete shall be placed into stream channel habitat after the area has been completely dewatered or when the work area is naturally dry.
c. Concrete must be completely cured before coming into contact with waters of the United States and waters of the state. Surface water that contacts wet concrete must be pumped out and disposed of at an appropriate off-site commercial facility, which is authorized to accept concrete wastes.
Invasive Species and Soil Borne Pathogens
Prior to arrival at the Project site and prior to leaving the Project site, construction equipment that may contain invasive plants and/or seeds shall be cleaned to reduce the spread of noxious weeds.
Post-Construction Storm Water Management
a. The Permittee must minimize the short and long-term impacts on receiving water quality from the Project by implementing the following post-construction storm water management practices and as required by local agency permitting the Project, as appropriate:
i. Minimize the amount of impervious surface;
ii. Reduce peak runoff flows;
iii. Provide treatment BMPs to reduce pollutants in runoff;
iv. Ensure existing waters of the state (e.g., wetlands, vernal pools, or creeks) are not used as pollutant source controls and/or treatment controls;
v. Preserve and where possible, create or restore areas that provide important water quality benefits, such as riparian corridors, wetlands, and buffer zones;
vi. Limit disturbances of natural water bodies and natural drainage systems caused by development (including development of roads, highways, and bridges);
vii. Use existing drainage master plans or studies to ensure incorporation of structural and non-structural BMPs to mitigate the projected pollutant load increases in surface water runoff;
viii. Identify and avoid development in areas that are particularly susceptible to erosion and sediment loss, or establish development guidance that protects areas from erosion/ sediment loss; and
ix. Control post-development peak storm water run-off discharge rates and velocities to prevent or reduce downstream erosion, and to protect stream habitat.
Roads
a. The number of access routes, number and size of staging areas, and the total area of the activity must be limited to the minimum necessary to achieve the project goal. Routes and work area boundaries must be clearly demarcated.
b. Bridges, culverts, dip crossings, or other structures must be installed so that water and in-stream sediment flow is not impeded. Appropriate design criteria, practices and materials must be used in areas where access roads intersect waters of the state.
c. Temporary materials placed in any water of the state must be removed as soon as construction is completed at that location, and all temporary roads must be removed or re-contoured and restored according to approved re-vegetation and restoration plans.
d. Any structure, including but not limited to, culverts, pipes, piers, and coffer dams, placed within a stream where fish (as defined in California Fish and Game Code section 45) exist or may exist, must be designed, constructed, and maintained such that it does not constitute a barrier to upstream or downstream movement of aquatic life, or cause an avoidance reaction by fish due to impedance of their upstream or downstream movement. This includes, but is not limited to, maintaining the supply of water and maintaining flows at an appropriate depth, temperature, and velocity to facilitate upstream and downstream fish migration. If any structure results in a long-term reduction in fish movement, the discharger shall be responsible for restoration of conditions as necessary (as determined by the Water Board) to secure passage of fish across the structure.
e. A method of containment must be used below any temporary bridge, trestle, boardwalk, and/or other stream crossing structure to prevent any debris or spills from falling into the waters of the state. Containment must be maintained and kept clean for the life of the temporary stream crossing structure.
Sediment Control
a. Except for activities permitted by the United States Army Corps of Engineers under Section 404 of the Clean Water Act and/or Section 10 of the Rivers and Harbors Act, soil, silt, or other organic materials shall not be placed where such materials could pass into surface water or surface water drainage courses.
b. Silt fencing, straw wattles, or other effective management practices must be used along the construction zone to minimize soil or sediment along the embankments from migrating into the waters of the state through the entire duration of the Project.
c. The use of netting material (e.g., monofilament-based erosion blankets) that could trap aquatic dependent wildlife is prohibited within the Project area.
Special Status Species – Not Applicable
Stabilization/Erosion Control
a. All areas disturbed by Project activities shall be protected from washout and erosion.
b. Hydroseeding shall be performed with California native seed mix.
Storm Water
a. During the construction phase, the Permittee must employ strategies to minimize erosion and the introduction of pollutants into storm water runoff.
These strategies must include the following:
i. An effective combination of erosion and sediment control Best Management Practices (BMPs) must be implemented and adequately working prior to the rainy season and during all phases of construction.
H. Site Specific– Not Applicable
I. Total Maximum Daily Load (TMDL) – Not Applicable
J. Mitigation for Temporary Impacts
1. The Permittee shall restore all areas of temporary impacts, including Project site upland areas, which could result in a discharge to waters of the state to pre-construction contours and conditions upon completion of construction activities.
2. The Central Valley Water Board may extend the monitoring period beyond the requirements of the restoration plan upon a determination by Executive Officer that the performance standards have not been met or are not likely to be met within the monitoring period.
3. If restoration of temporary impacts to waters of the state is not completed within 90 days of the impacts, compensatory mitigation may be required to offset temporal loss of waters of the state.
4. Total required Project compensatory mitigation information for temporary impacts is summarized in Table 4. [Establishment (Est.), Re-establishment
(Re-est.), Rehabilitation (Reh.), Enhancement (Enh.), Preservation (Pres.), Unknown].
Table 4: Required Project Mitigation Quantity for Temporary Impacts by Method
Aquatic Resource
Type
Mitigation Type
Units Est.
Re-est.
Reh. Enh. Pres. Unknown
Stream Channel
Permittee Responsible
Acres 0.008
K. Compensatory Mitigation for Permanent Impacts:
Compensatory Mitigation is for permanent physical loss and permanent ecological degradation of a water of the state.
1. Purchase of Mitigation Credits by Permittee for Compensatory Mitigation
a. A copy of the fully executed agreement for the purchase of mitigation credits shall be provided to the Central Valley Water Board prior to commencing authorized impacts.
b. The Permittee shall retain responsibility for providing the compensatory mitigation and long-term management until Central Valley Water Board staff has received documentation of the credit purchase and the transfer agreement between the Permittee and the seller of credits.
2. Total Required Compensatory Mitigation
a. The Permittee is required to provide compensatory mitigation for the authorized impact to 0.10 acre of stream channel by purchasing 0.10 Aquatic Resource Credits in the Kaweah/Tule Rivers Aquatic Resource Watershed Service Area. Required credits shall be purchased from the National Fish and Wildlife Foundation (NFWF)’s Sacramento District California In-Lieu Fee Program.
b. Total required Project compensatory mitigation information for permanent physical…