This is a Selective Demolition specification section (024119) for the Crownpoint Health Care Facility Medical Gas Upgrade project under Indian Health Service Order No. HHSI16103024T.

The specification establishes requirements for demolition and removal of selected building elements, including walls, ceilings, and floors necessary to accommodate new construction. Demolition waste becomes the contractor's property unless otherwise indicated. Key submittals include a protection measures report with drawings showing dust and noise control barriers, a schedule of demolition activities with start and end dates, and pre-demolition photographs or video. The contractor must maintain the facility in operational status during selective demolition, arrange the schedule to avoid disruption to owner operations, and protect existing utilities and fire-protection systems. Utilities must be disconnected and capped before demolition begins, with the owner arranging service shutoff when requested. The contractor is responsible for providing temporary protection and barricades to prevent injury and damage to adjacent structures. Demolition methods must use hand tools or small power tools for cutting rather than hammering or chopping; cutting torches are prohibited until work areas are cleared of flammable materials, and portable fire-suppression devices must be maintained during flame-cutting operations. All demolition must comply with EPA notification regulations, ASSE A10.6, and NFPA 241 standards. Demolition waste must be removed from the site and disposed of at an EPA-approved construction and demolition waste landfill, with materials not allowed to accumulate on-site or be burned. Adjacent structures must be cleaned of dust, dirt, and debris, returning areas to their pre-demolition condition.

View the file

Other files

File Type Posted
B05 Amdnment A0004-75H70126R00028.pdf PDF
B01 RFP 75H70126R00028 Crownpoint Medical Gas Upgrade Amended by A0004.pdf PDF
B05 Amdnment A0003-75H70126R00028.pdf PDF
B05 Amdnment A0002-75H70126R00028.pdf PDF
B01 RFP 75H70126R00028 Crownpoint Medical Gas Upgrade Amended by A0002.pdf PDF
B01 Attachment J02-f As-Built P-7.pdf PDF
B01 RFP 75H70126R00028 Crownpoint Medical Gas Upgrade Amended by A0001.pdf PDF
B01 Attachment J02-a Crownpoint Med Gas Renovation ADDENDUM 1.pdf PDF
B05 Amdnment A0001-75H70126R00028.pdf PDF
B01 Attachment J02-d As-Built P-3.pdf PDF
B01 Attachment J02-e As-Built P-5.pdf PDF
B01 Attachment J02-b 9024T IHS Crownpoint Med Gas_Project Specifications.pdf PDF
B01 Attachment J02-c As-Built P-1.pdf PDF
B03 Site Visit Sign-In sheet.pdf PDF
B01 RFP 75H70126R00028 Crownpoint Medical Gas Upgrade.pdf PDF
B01 Attachment J03 Self Performed Calculation Sheet (Construction).docx DOCX document
B01 Attachment J04 Company Specialized Experience Construction Form.pdf PDF
B01 Attachment J02 Crownpoint Medical Code Update Report.pdf PDF
B01 Attachment J06 IHS IEE Representation Form.pdf PDF
B01 Attachment J01 Wage Determination NM20260024 20260518.pdf PDF
B01 Attachment J05 Past Performance Questionnaire.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Crownpoint Health Care Facility Medical Gas Upgrade

Indian Health Service

Order No. HHSI16103024T

SELECTIVE DEMOLITION 024119 - 1

SECTION 024119

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected elements.

2. Wall, ceiling, and floor demolition as necessary for new work.

1.2 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

1.3 PREINSTALLATION MEETINGS

A. Pre-demolition Conference: Conduct conference at Project site.

1.4 SUBMITTALS

A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.

B. Schedule of selective demolition activities with starting and ending dates for each activity.

C. Pre-demolition photographs or video.

1.5 FIELD CONDITIONS

A. Facility will remain open during construction, immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by

Owner as far as practical.

C. Notify Rock Gap Engineering of discrepancies between existing conditions and

Drawings before proceeding with selective demolition.

D. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

E. Arrange selective demolition schedule so as not to interfere with Owner's operations.

SELECTIVE DEMOLITION 024119 - 2

1.6 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations. Coordinate demolition and removal with the staff and utility company.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated services/systems when requested by

Contractor.

2. Arrange to shut off utilities with utility companies.

3. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

3.3 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

B. Remove temporary barricades and protections where hazards no longer exist.

SELECTIVE DEMOLITION 024119 - 3

3.4 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensions required.

Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

2. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

3. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

3.5 CLEANING

A. Remove demolition waste materials from Project site and dispose of them in an

EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Burning: Do not burn demolished materials.

C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 024119