This document is an Amendment (Standard Form 30) for Solicitation 75H70125R00016, issued by the Division of Engineering Services in Seattle, Washington, with an effective date of 09/19/2025. The amendment's primary purpose is to answer vendor questions regarding specific technical details of a construction project.
The Questions and Answers section clarifies three key points: (1) specific grade beams on grid lines 6, 4, and 12 that are to be replaced, with others remaining existing; (2) a previously referenced chain link fence label should be disregarded as it was a left-over from a previous design iteration; and (3) handrails and a ramp are confirmed to not be part of the current project scope. The solicitation number matches 75H70125R00016, and the amendment is numbered A00001, indicating this is the first amendment to the original solicitation.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A00001
The reason for this amendment on this solicitation is to answer questions from vendors.
See Q&A below.
Division of Eng. Services Seattle 701 Fifth Avenue, Suite 1600 Seattle WA 98104
See block 6
75H70125R00066
BI25NC201C06
1 2
09/19/2025
08/08/2025
Solicitation: 75H70125R00016 Amendment 00001
QUESTIONS AND ANSWERS
Q1. Looking at sheet S101, Are we replacing Grade Beams (GB) on grid lines 6,4 and 12 or do those remain as existing?
A1. As noted on S101 Foundation Plan General Notes #5 – GB Denotes grade beam to be designed by precast manufacturer. Therefore:
• Grade beams on Line 6 between N and O are to be replaced.
• Grade beams on line 4 between M and O are to be replaced.
• Grade beams on Line 12 between F.5 and G are to be replaced.
Grade beams that remain are denoted as existing.
Q2. On C201 there reference to a chain link fence, but doesn’t show its location. The next the chain link fence it references a 8’‐6” location of something? See below cut out from C201.
A2. The reference to the chainlink fence can be disregarded. This was a left‐over label from the previous design that included the conductive concrete and electrical components.
Q3. There were discussions on replacing the handrails. They’re not noted on the plans, but also there is a good plan sheet where you can show these. Can you confirm and maybe have the design team add a detail and footage of what they want?
A3. The ramp and rail are not included as part of this project.