This document summarizes an amendment to a solicitation for construction services. The amendment provides responses to offeror questions, revises site visit details, and extends the proposal due date from June 22, 2020 to June 26, 2020. The solicitation is for construction of a water main and appurtenances, new pumphouse piping and plumbing on the Mescalero Apache Reservation in New Mexico. The Department of Health and Human Services Indian Health Service is the contracting agency. The amendment answers fifteen questions from offerors seeking clarification on technical requirements, permits, security procedures, and project scope.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A0004
The purpose of this amendment is to:
1) Answer questions from prospective offerors
2) Update FAR Clause 52.236-27 with site visit information.
3) Extend the proposal due date from June 22, 2020, 2:00PM CDT to June 26, 2020, 2:00PM CDT .
Indian Health Service (IHS) Division of Engineering Services (DES) 1301 Young Street, Suite 840 Dallas, TX 75202
75H701-20-R-00032
AL-17-A79 & AL-17-A82
1 5
06/10/2020
05/08/2020
SF30 CONTINUATION OF BLOCK NARRATIVE
SUMMARY OF CHANGES
The solicitation is hereby amended to address the following:
1. Revise FAR Clause 52.236-27 Site Visit (Construction) as follows:
FAR 52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions
Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for—
Time: Tuesday, June 16, 2020 at 10:30AM Mountain Time (US and Canada)
(c) Participants will meet at –
Mescalero Tribal Utility Office
556 Soldier Canyon Road, Mescalero NM, 88340.
Participants will be required to sign-in at the checkpoint and wear Personal Protective Equipment throughout the site visit.
See attached map on Page 5 for location details.
(End of Provision)
2. Respond to inquiries received in addressing the solicitation package. The questions and answers are being consolidated and are presented and answered as follows:
QUESTIONS FROM AMENDMENT A0001
QUESTION 0001: On sheet 01 of 13, for the South Tulie Canyon water main, the vicinity map indicates that there is an existing pump house at the north end of the line and another at the south end, both to be refurbished.
Sheet 11 of 13 shows only one existing pump house. How many existing pump houses are there to be refurbished?
RESPONSE PROVIDED: Sheet 01 incorrectly shows that the south pumphouse needs to be refurbished.
Please see revised Sheet 01 of Attachment 2 – South Tularosa Drawings. As per Sheet 11, only the north pumphouse is to be refurbished under this contract.
QUESTION 0002: On sheet 11 of 13, details show the pump house as existing with a small addition to be built by others. Supplemental Technical provisions, page 4/46 say the scope of this project include furnishing all labor, materials and incidentals to construct a new pump house. Which is correct?
RESPONSE PROVIDED: Per the scope of work, bid schedule, and drawings, constructing a new pumphouse is not part of the contract. All references to new pumphouse have been removed. See revised
Attachment 01 - Supplemental Technical Provisions.
QUESTION 0003: Will there be a mandatory/non-mandatory pre-bid meeting? If so when do you anticipate scheduling?
RESPONSE PROVIDED: Pre-bid meeting will be held on May 27, 2020 at 9AM Mountain Time. The meeting will be held via zoom. Please see FAR Clause 52.236-27 above for further information. While the pre-bid meeting is not mandatory, it is highly encouraged for all prospective offerors to attend.
Individual site visits won’t be held, but you are allowed to drive to the site at your convenience.
QUESTION 0004: Per H.22 of the RFB, what type of Permits/Licenses will be required of the contracting company to obtain?
RESPONSE PROVIDED: As stated in FAR 52.236-7, the Contractor without any additional expense to the Government, is required to obtain any necessary licenses and permits for the performance of the work.
This is the responsibility of the firm to investigate the permits/licenses required.
QUESTION 0005: Per H.9 and H.43 of the RFB, are badges and a security clearances mandatory for the contracting company's staff, or does this pertain to other contracts?
RESPONSE PROVIDED: Per Clause H.9, all personnel are required to wear security badges. Per
Clause H.43, only the superintendent is subject to pass the IHS background investigation and security clearance review, but the contractor is still responsible, at his discretion, for completing investigations and background checks for all employees, including sub-contractors and their employees that perform work under this contract on the job site.
QUESTION 0006: Is there a Tribal TERO tax for this project?
RESPONSE PROVIDED: No, there is no Tribal/TERO tax for this project.
QUESTIONS FROM AMENDMENT A0002
QUESTION 0007: Sheet 12 of 13, Site Electrical. What is the distance between the source of the 480 volt, 3 phase power and the pumphouse. There is no dimension or scale, just a one-line schematic.
RESPONSE PROVIDED: Contractor is responsible for verifying location of all existing utilities. Refer to sheet 2 of 13, general notes 2, “The contractor shall visit the site and determine the actual conditions with regard to the existence of fences, driveways, trees, sidewalks, culverts, utilities …”
QUESTION 0008: Is there any Tribal tax or fee to be paid for this project?
RESPONSE PROVIDED: No, there is no Tribal/TERO tax for this project. The contractor will need to contact Mr. Chris Little, Mescalero Utility Department, (575) 973-2304 for water consumption fees.
QUESTION 0009: Sheet 13 of 13, detail 1A, Typical Trench Section. As there is no geotechnical report, how are we to determine whether or not special embedment will be required?
RESPONSE PROVIDED: B01 Attachment 10 – Technical Provisions, Section 01, TP-107.A, Section 5 and TP107.B specifies that special pipe embedment is not anticipated. If special pipe embedment is required after award, a request for proposal will be issued and a modification will be done to the contract to incorporate this change.
QUESTIONS FROM AMENDMENT A0003
QUESTION 0010: Do either of you know what the liquidated damages will be on this project (Mescalero Well
Connection & Water Main Extension, Solicitation Number 75H701-20-R-00032)? I need that to order the bid bond.
RESPONSE PROVIDED: Liquidated damages will not be assessed on this project.
QUESTION 0011: Can the due date for questions be revised to 4 days after the site visit?
RESPONSE PROVIDED: Per this Amendment, the due date for questions is now COB Monday, June
15, 2020. Site visit information will be forthcoming in the next Amendment.
QUESTION 0012: I’m reviewing the chlorination spec – their requesting a dosing pump that does 2 GPM – 60
GPM, this is extremely large. I don’t have a pump that can do 3600 GPH on the high end. Do you think they have a typo and it should be 2-60 GPH??...which is still a HUGE range. Their tank called out is 55 Gallons, so they’d be pumping that down completely in less than a min. Could this be a typo please confirm?
RESPONSE PROVIDED: The 2gal/min to 60 gal/min is a rating for the carrier pipe. The dosing pump shall be able to treat a pipeline carrying water flowing at 2gal/min to 60 gal/min.
QUESTIONS FROM AMENDMENT A0004
QUESTION 0013: Was the site visit that was held on May 27th mandatory or optional?
RESPONSE PROVIDED: The site visit that was held on May 27th was not mandatory.
QUESTION 0014: Is there a recording of the site visit that we could view?
RESPONSE PROVIDED: Unfortunately, it was not recorded.
QUESTION 0015: Was there a sign in sheet for attendees and is that available now?
RESPONSE PROVIDED: Please see Amendment No. A0003 which contains the sign in sheet for the attendees.
This amendment extends the proposal due date/time from Monday, June 22, 2020, 2:00PM CDT to Friday, June 26, 2020. Inquiries are to be sent by email to Shaukat.syed@ihs.gov and must be received no later than COB
Friday, June 19, 2020 to allow time for response.
NOTICE TO OFFERORS: Offerors must acknowledge receipt of any and all amendments by number and date on their cover letter in their offer or by submitted a signed copy of the SF30. All other terms and conditions remain unchanged.
mailto:Shaukat.syed@ihs.gov
END OF SUMMARY OF CHANGES