About this file

This document is a Sample Non-Routine Statement of Work (SOW) for a federal contract opportunity to replace sewage ejection pumps at an FDA facility in Irvine, California. The scope of work includes removing the existing pumps, furnishing and installing new premium efficient explosion proof pumps, making necessary adjustments, and restoring the system to service within 30 calendar days. The contractor must be certified, follow all applicable codes and regulations, and provide a one-year warranty on the work. The related federal contract opportunity is for a broader set of operations and maintenance services, janitorial, landscaping, waste management, and non-routine services at the FDA's Los Angeles District Office, Pacific Southwest Food and Feed Laboratory, and Pacific Southwest Medical Products Laboratory facilities in Irvine. The contract will be an 8(a) small business set-aside with a hybrid Indefinite Delivery/Indefinite Quantity structure.

View the file

Other files

File Type Posted
Amendment Four 75F40124R00001 07232024.pdf PDF
Attachment 20 SF 30 Amendment Three 07192024 and Continuation Page with amended Attachment Table. .pdf PDF
Attachment 8 Pricing Table Revision 07192024 .xlsx XLSX spreadsheet
Attachment 8 Pricing Table Revision 07162024 Amendment Two.xlsx XLSX spreadsheet
Attachment 19 SF 30 Amendment Two OC-2024-124543 07162024.pdf PDF
Attachment 18 Amendment Two Question and Answers OC-2024-124543 07162024.pdf PDF
Attachment 15 Site Roster LOSDO JUN 27 2024 Rev 1..pdf PDF
AMENDMENT TWO CB SYNOPSIS SOL_75F40124Q00001_A00002 07162024.pdf PDF
Attachment 13 Landscape Map 07122024 REV.pdf PDF
Attachment 17 SF 1449 07262024 2PM ET.pdf PDF
Attachment 9 Key Personnel Qualifications Amend 1 vs 07112024.pdf PDF
Attachment 12 Pictures for Question and Answers Amend 1.pdf PDF
Attachment 16 SF 30 A00001 OC-2024-116543 07122024.pdf PDF
Attachment 5 TO 1 Statement of Work 07102024 REVISED VS1.pdf PDF
Attachment 17 SF 1449 1.pdf PDF
Amendment 1 CB SYNOPSIS SOL_75F40124Q00001_0001 07112024.pdf PDF
Attachment 15 SiteVisit Roster LOSDO JUN 27 2024.pdf PDF
Attachment 14 Equipment Maintenance Schedule List.pdf PDF
Attachment 8 Pricing Table Revision 07112024 Amendment One.xlsx XLSX spreadsheet
Attachment 11 Question and Answers 75F40124R00001_A00001.pdf PDF
ATTACHMENT 7 Wage Determination No 2015-5645 05022024.pdf PDF
Attachment 3 Past Performance Questionnaire.docx DOCX document
Attachment 1 Rules-of-Behavior 06102024.pdf PDF
Attachment 8 Pricing Table OC-2024-116543 06112024.xlsx XLSX spreadsheet
Attachment 4 Irvine Equipment List 06102024.pdf PDF
Attachment 5 TO 1 Statement of Work.pdf PDF
Attachment 2 3398 Non-Public Info.pdf PDF
CB SYNOPSIS SOL_OC-2024-116543 06132024.pdf PDF
Attachment 6 Sample Non-Routine SOW 06102024.pdf PDF
SF 1449 75f40124R00001 .pdf PDF
Attachment 10 FDA Non Disclosure Agreement Site Visit .pdf PDF
Attachment 9 Key Personnel Qualifications.pdf PDF
Attachment 7 Wage Determination.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2006-5A-024 Page 1

Attachment 6 Sample Non-Routine Statement of Work (SOW) 75F40124R00001

Sample Non-Routine SOW

Location: Irvine California

Project Title

Sewage Ejection Pump Repair

Description of Work

Background

An incident occurred with other warning light for the sewage system illuminated/alarmed. After numerous attempts at repairs and resetting the system, a contractor was dispatched and confirmed that both pumps require replacement. The 2.9 HP/460 vac pump is 20 years old and we’ve only had problems with the floats on and off over the last 12-18 months. Since then, the light has continued to illuminate as a warning. Engineering has been able to utilize one of the existing pumps (the better of the two) to maintain operation of the system. The goal is to complete this repair as quickly as possible to evade sewage back up in the building and possibly further damage.

Scope of Work

The Contractor shall provide all necessary materials, labor, evaluation, permits, disposal arrangements, hauling, and removal of demolished work, clean ups, shipping, delivery, and supervision to replace the Sewage Ejection Pump. The contractor shall protect existing work and other Government property. The contractor shall also be certified and ensure all work adheres to current industry standards as well as all applicable local, county, OSHA, NEC, AQMD and ASME 17, codes and specifications. In the event a conflict arises over workmanship the more stringent code shall be adhered to.

The contractor shall be responsible for the following:

1. Checking in with the customer and performing a job safety inspection;

2. Remove existing pumps

3. Furnish and install new premium efficient explosion proof pumps per manufacturer requirements

4. Make individual adjustments for safe operation and reliability

5. Furnish and install new elapsed time meters to accommodate new motors

6. Provide required submissions to all governing authorities and a copy to the customer

7. Test sewage ejection pumps for operation and performance

8. Return system to service

9. Upon completion, submit an engineering report summarizing the work completed for review and records.

2006-5A-024 Page 2

All work will be completed adhering to FDA Design Guidelines, all Local City, County, State, ASME, ASTM, NFPA, OSHA, UL, ANSI, IEEE, IRWD, AQMD rules and regulations and standards set forth by these organizations. Contractor must provide final cleaning and one year warranty on all work.

Quality Control

The Contractor shall be solely responsible for the quality of his work.

Deficiencies and omissions shall be corrected prior to final inspection and performed by the Contractor at no cost to the Government.

Notice to Proceed

The Contractor shall begin the planning stage of the project upon receipt of notice to proceed from the Contracting Officer (CO). The Contractor services planning, and construction shall be performed within 30 calendar days. Upon receipt of notice to proceed from the CO the contractor shall notify the government 10 day prior to utilities shut down.