This document is a Questions and Answers (Q&A) file from a site visit for a C-5 Scaffolding Rental federal contract opportunity. The document details specific scaffolding requirements for two aircraft models (C-Model and M-Model), including internal and external scaffolding configurations, setup procedures, and technical specifications. Key details include scaffolding placement (8' from top center for C-Model, 7" for M-Model), required width of 14' for both models, and a 75" height from ground to aircraft belly when jacked.
Additional contractual requirements include following OSHA safety standards, mandatory EGRES and Confined Spaces training for contractors, requirement for engineer-stamped final drawings, and prevailing wage compliance with Houston County, Georgia. The scaffolding work will be sequential, with one aircraft processed at a time, and requires a spotter during construction. The government will provide a forklift and driver, and no specific government safety standards were specified beyond industry OSHA regulations. A bridge connection is needed on the fore and aft ends of the aircraft to connect external scaffolding, and internal scaffolding can be built on the aircraft floor or existing walkways with additional decking.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C-5 SCAFFOLDING RENTAL
Site Visit
10 April 25
Questions and Answers:
Q: Will both aircrafts be worked at the same time?
A: No. One will come in and be worked on. Then once that one leaves the dock the next one will come in.
Q: Will both aircrafts be in the same configuration?
A: No. The first aircraft in will be the C-Model, which will have internal sca olding in the inside cargo area between sections 1573-2100. The second aircraft will be the M-Model, which will have the internal sca olding inside the Hayloft between sections 2101-2573.
Q: Will the sca olding be set up externally and then once that work is complete the internal will be set up?
A: No. The sca olding is needed to be set up concurrently.
Q: Are there specific government safety standards to follow?
A: No. Industry OSHA standards are to be followed.
Q: When the aircraft is in the jacked configuration, what is the height from the ground to the belly of the aircraft?
A: 75”
Q: How should the access to the working deck on the external sca olding be configured?
A: Stair tower.
Q: Is a “bridge” over the aircraft needed to connect the external sca olding?
A: Yes. A bridge on the fore and aft end of the aircraft to connect the sca olding.
Q: On the C-Model, can the sca olding in the inside of the cargo area be built up on the floor of the aircraft itself?
A: Yes.
Q: On the M-Model, can the sca olding in the hayloft area be built up on the existing flooring?
A: There is a walkway that goes down the center of the hayloft area that the sca olding legs can be set on. To the sides of the walkway there are ribs spaced 20” apart that a decking needs to be placed for the sca olding to sit on.
Q: On the inside of the C-Model, how far from the top center does the sca olding need to be in the cargo area?
A: The sca olding needs to be 8’ from the top center of the aircraft.
Q: On the inside of the M-Model, how far from the top center does the sca olding need to be in the hayloft area?
A: The sca olding needs to be 7” from the top center.
Q: Will the contractor need to bring a forklift for unloading the material?
A: No. We can provide a forklift and driver.
Q: Is a spotter needed when building the sca olding?
A: Yes. A Spotter is required per safety regulations.
Q: Will any trainings be required for the contractors?
A: Yes. EGRES and Confined Spaces trainings will be required. The awarded contractor will be notified of the day and time for the trainings.
Q: Will the awarded contractor need to submit stamped drawings?
A: Yes. Final drawings submitted must be stamped by an engineer.
Q: Are prevailing wages a factor?
A: Yes. Must be in accordance with the prevailing wages of Houston County, Ga.
Q: On the inside of the C-Model, what is the width needed for the sca olding?
A: The width needs to be 14’.
Q: On the inside of the M-Model, what is the width needed for the sca olding?
A: The width needs to be 14’.