Nahma Grade Multiuse Trail Culvert Installations Project Manual
This file is a project manual for the Nahma Grade Multiuse Trail Culvert Installations project, prepared by OHM Advisors for the State of Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division, located in Hancock, Michigan. The project involves the installation of a 14'-1" by 6'-2" corrugated aluminum four-sided box culvert approximately 40.5 feet in length at a water crossing on the Nahma Grade Multiuse Trail. Associated work includes site clearing of approximately one acre, machine grading, excavation of earth and peat material, placement of subbase and aggregate surface courses, installation of riprap erosion control materials, geotextile fabric installation, topsoil restoration with seeding and mulch application, temporary and permanent erosion and sedimentation control measures, and dewatering operations. The project quantities include 350 cubic yards of backfill for the structure, 60 cubic yards of subbase material, 160 square yards of aggregate surface course, 150 square yards of geotextile separator, 17 cubic yards of culvert bedding material, 110 cubic yards of riprap, four treated wood sign posts, and four object marker signs. The project file number is 7136-21-0010, and the site location is near US-2 and Nahma County Road 497 in Michigan's Upper Peninsula.
The project specifications incorporate the 2020 Michigan Department of Transportation (MDOT) Standard Specifications for Construction, the 2011 AASHTO Policy on Geometric Design of Highways and Streets, and the 2011 Michigan Manual of Uniform Traffic Control Devices. The contractor is responsible for all utility location verification through Miss Dig at least three working days prior to excavation, water control and dewatering operations, soil erosion and sedimentation control compliance including employment of a Michigan EGLE-certified storm water operator due to the disturbance of five or more acres, and protection of all existing utilities with hand-digging verification before excavation. Subbase and base course materials must be compacted to 95 percent maximum unit weight according to ASTM D698 or D1557 standards, and trail surface subgrades must meet tolerances of plus or minus 0.5 inch. The culvert design shall be based on 1.2 times the AASHTO LRFD HL-93 Modified Loading criteria, with the structure requiring a manufacturer's representative present during assembly and installation. Permanent slope stabilization for slopes less than 2:1 shall use topsoil and mulch blankets, while steeper slopes exceeding 2:1 require high velocity mulch blankets. All surplus excavated material becomes contractor property for disposal, and the project includes final closeout requirements including Certificate of Substantial Completion, all required permits and bonds, as-built drawings, and evidence of SESC and storm water permit closure.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P
L
U
R I
B U
E
S
U
N
U
M
C
I
R
C
U M
S
P
I
C
E
S
I
Q
U
E
R
E
I S
P E
N I
N
S U
L
A M
A
M
O E
N
A
M
ARCHITECTS. ENGINEERS. PLANNERS
OHM-ADVISORS.COM
P:
\71
_7
0\7
0_ na hm a_ gr ad e_ mu ltiu se
_tr ail
\D ra wi ng s\C ivi l\M isc
\21
NO
T.
dw g S ep
, 2
1 - 4:
pm
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
FA
CI
LI
TI
ES
A
N D
B U
SI
N
ES
S
SE
RV
IC
ES
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
424 HANCOCK STREET
HANCOCK, MICHIGAN 49930
PH. 906.482.0535
F 906.482.6453
7136-21-0010
AGGREGATE SURFACE CONSTRUCTION
1. NEW AGGREGATE MATERIAL FOR ROAD AND TRAIL SURFACE SHALL MEET THE REQUIREMENTS OF SECTION
902 OF THE 2020 MDOT STANDARD SPECIFICATIONS FOR CONSTRUCTION AND SHALL BE MDOT CLASS 23A
OR AS APPROVED BY THE ENGINEER.
2. AGGREGATE MATERIAL FOR ROAD AND TRAIL SURFACE SHALL BE CONSTRUCTED PER SECTION 306 OF THE
2020 MDOT STANDARD SPECIFICATIONS FOR CONSTRUCTION.
UTILITY NOTES
1. THE CONTRACTOR SHALL BE FULLY RESPONSIBLE FOR THE LOCATION AND PROTECTION OF ALL
EXISTING UTILITIES. THE CONTRACTOR SHALL VERIFY ALL UTILITY LOCATIONS PRIOR TO
CONSTRUCTION BY CALLING MISS-DIG (811) AT LEAST 3 WORKING DAYS PRIOR TO EXCAVATION.
2. THE UTILITY LOCATIONS ARE BASED ON FIELD OBSERVATIONS AND A CAREFUL REVIEW OF UTILITY
RECORDS. HOWEVER, IT IS NOT POSSIBLE TO DETERMINE THE PRECISE SIZE, LOCATION, DEPTH, PRESSURE, OR ANY OTHER CHARACTERISTICS OF UNDERGROUND UTILITIES, TANKS OR SEPTIC
FIELDS WITHOUT EXCAVATION. THEREFORE, WE CANNOT GUARANTEE THE ACCURACY OR
COMPLETENESS OF THE BURIED UTILITY INFORMATION HEREON SHOWN. THE CONTRACTOR SHALL
HIRE A PRIVATE UTILITY LOCATOR TO LOCATE UTILITIES ON SITE. IT SHALL BE THE RESPONSIBILITY
OF THE CONTRACTOR TO VERIFY THESE UTILITY LOCATIONS PRIOR TO CONSTRUCTION AND MAKE
EVERY EFFORT TO PROTECT AND/OR RELOCATE THEM AS REQUIRED. THE CONTRACTOR SHALL
NOTIFY THE ENGINEER/SURVEYOR AS SOON AS POSSIBLE IN THE EVENT A DISCREPANCY IS FOUND.
3. THE CONTRACTOR SHALL ASSUME RESPONSIBILITY FOR THE PROTECTION OF ALL EXISTING
UTILITIES DURING CONSTRUCTION. ALL UTILITIES DAMAGED DURING CONSTRUCTION SHALL BE
REPAIRED WITH LIKE MATERIAL. THE EXACT LOCATION OF EXISTING UTILITIES SHALL BE LOCATED
BY HAND DIGGING.
ALGER DELTA ELEC ELECTRIC
426 N 9TH STREET, GLADSTONE, MI 49837
SHANNON PRIEBE
906-428-4141
SPRIEBE@ALGERDELTA.COM
AT&T TELECOM
211 E B ST, IRON MOUNTAIN, MI 49801
MARSHA BERTOLDI
906-396-9488
MB8983@ATT.COM
REMOVAL
1. ALL TEMPORARY SOIL EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE IN PLACE PRIOR
TO STARTING REMOVALS.
2. REMOVALS SHALL BE DONE AS SHOWN ON THE PLANS OR AS DIRECTED BY THE ENGINEER.
3. SAW CUTTING FOR PAVEMENT REMOVAL AS SHOWN ON THE PLANS OR AS DIRECTED BY THE
ENGINEER SHALL BE TO THE DEPTH REQUIRED FOR NEAT REMOVAL OF PAVEMENT OR CONCRETE. DO
NOT OVERCUT PAST ENDS OR CORNERS. REPAIR/RESTORE ALL DAMAGED AREAS.
4. SAW CUTTING DEPTH SHALL BE ADEQUATE TO PREVENT SPALLING, CHIPPING, OR DAMAGE TO
EXISTING PAVEMENT EDGES LEFT IN PLACE AS DIRECTED.
5. CLEARING OF ALL VEGETATION WHERE PROPOSED CONSTRUCTION WARRANTS SHALL BE PAID FOR BY
CLEARING THE BRUSH AND TREES LESS THAN 30" IN DIAMETER. CONTRACTOR SHALL REVIEW
CLEARING LIMITS WITH THE ENGINEER PRIOR TO THE CLEARING OPERATION.
6. ANY ADDITIONAL TREE REMOVALS, CLEARING, GRADING, ETC. NEEDED FOR THE CONTRACTOR'S
STAGING AND/OR WORK OPERATIONS SHALL BE COMPLETED AND AREA RESTORED TO THE
SATISFACTION OF THE OWNER WITHOUT ADDITIONAL COMPENSATION.
7. ADDITIONAL WORK OUTSIDE OF THE LIMITS AS SHOWN ON THE PLAN SHALL BE SUBMITTED TO THE
ENGINEER FOR APPROVAL PRIOR TO STARTING THE ADDITIONAL WORK.
8. MATERIALS REMOVED SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR AND BE PROPERLY
DISPOSED OF AT AN OFF SITE LOCATION.
EARTHWORK, GRADING & RESTORATION
1. THE CONTRACTOR SHALL RESTORE ALL ADJACENT AREAS UPON COMPLETION OF THE PROJECT.
2. ALL DISTURBED AREAS SHALL BE BROUGHT TO FINAL GRADE AND STABILIZED AS SOON AS POSSIBLE
AFTER BEING DISTURBED. PERMANENT SOIL EROSION AND SEDIMENTATION CONTROL MEASURES
SHALL BE INSTALLED WITHIN FIVE CALENDAR DAYS OF COMPLETING FINAL GRADING.
3. ALL PERMANENT SLOPES LESS THAN 2:1 SHALL BE STABILIZED USING TOPSOIL & MULCH BLANKETS.
4. ALL PERMANENT SLOPES STEEPER THAN 2:1 SHALL BE STABILIZED USING HIGH VELOCITY MULCH
BLANKET.
5. CONTRACTOR SHALL PLACE SALVAGED AND ADDITIONAL TOPSOIL, SEED AND MULCH ON ALL
DISTURBED AREAS NOT UNDER PAVEMENT OR OTHERWISE LABELED, AS DIRECTED BY THE ENGINEER
TO PROVIDE A MINIMUM 3" THICKNESS. SEED MIX DESIGN FOR ALL SLOPE RESTORATION SHALL BE PER
TABLE 816-1 & 917-1 OF THE MICHIGAN DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONS
FOR CONSTRUCTION.
6. ALL FILL SHALL BE CLEAN INERT MATERIAL.
7. ALL EXCAVATIONS UNDER OR WITHIN 3 FEET OF PUBLIC PAVEMENT, EXISTING OR PROPOSED, SHALL BE
BACKFILLED AND COMPACTED WITH SAND (MDOT CLASS II).
8. SURPLUS EXCAVATED MATERIAL MAY BE USED TO FLATTEN FILL SLOPES AS DIRECTED BY THE
ENGINEER. ANY SURPLUS OR UNSUITABLE MATERIAL, INCLUDING PEAT EXCAVATION, UNABLE TO BE
USED SHALL BECOME THE PROPERTY OF THE CONTRACTOR FOR DISPOSAL.
9. CONTRACTOR SHALL SUBMIT LOCATIONS OF MATERIAL STOCKPILES TO THE ENGINEER FOR APPROVAL.
PROTECT ADJACENT AREAS WITH SILT FENCE AS REQUIRED.
SOIL EROSION AND SEDIMENTATION CONTROL
1. SOIL EROSION AND SEDIMENTATION CONTROL SHALL BE IN ACCORDANCE WITH THE 2020 MICHIGAN
DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATION FOR HIGHWAY CONSTRUCTION, AND THE
CONTRACTOR SHALL COMPLY WITH LOCAL RULES AND REGULATIONS FOR SOIL EROSION AND
SEDIMENTATION CONTROL.
2. ALL SOIL EROSION AND SEDIMENTATION CONTROLS SHALL BE IN ACCORDANCE WITH MDOT STANDARD
PLAN R-96 SERIES.
3. THE CONTRACTOR SHALL EMPLOY A MICHIGAN DEPARTMENT OF ENVIRONMENT GREAT LAKES & ENERGY
(EAGLE) CERTIFIED STORM WATER OPERATOR ON ALL SITES WITH A DISTURBANCE OF FIVE OR MORE
ACRES (PERMIT-BY-RULE). THE OPERATOR SHALL COMPLETE ALL INSPECTIONS AND REPORTS TO COMPLY
WITH SESC PERMIT REQUIREMENTS. THE PROJECT COVERS APPROXIMATELY X ACRES.
4. THE CONTRACTOR SHALL CONDUCT HIS OPERATIONS IN SUCH A MANNER AS TO MINIMIZE THE AREAS LEFT
BARREN DURING CONSTRUCTION AND TO DISTURB ONLY THOSE AREAS ABSOLUTELY REQUIRED FOR THE
CONSTRUCTION OF THE PROJECT.
5. EROSION CONTROL ITEMS SHALL BE INSTALLED AND MAINTAINED ON A REGULAR BASIS AS DIRECTED BY
THE ENGINEER AND SHALL BE REMOVED WHEN NO LONGER EFFECTIVE AS DETERMINED BY THE ENGINEER.
TEMPORARY EROSION CONTROL MEASURES SHALL BE MAINTAINED UNTIL PERMANENT SOIL CONTROL IS IN
PLACE AND STABILIZED. NO SEPARATE PAYMENT SHALL BE ALLOWED FOR EITHER MAINTENANCE OF
REMOVAL OF THE EROSION CONTROL ITEMS.
6. THE CONTRACTOR SHALL REMOVE SEDIMENT COLLECTED IN CULVERTS AND SUMPS OF ALL DRAINAGE
STRUCTURES IN THE VICINITY OF THE PROJECT WHEN SUCH SEDIMENT EXCEEDS ½ OF THE SUMP DEPTH
OR CULVERT DIAMETER. THE ENGINEER WILL INSPECT CULVERTS, SUMPS, AND ALL SESC ITEMS AFTER
STORM EVENTS AND DIRECT THE CONTRACTOR TO CLEAN OUT ALL CULVERTS, SUMPS, AND ALL SESC
ITEMS. CLEANING PIPING AND SUMPS FOR SEDIMENTATION CONTROL SHALL NOT BE PAID FOR
SEPARATELY. DEBRIS REMOVED SHALL BE DISPOSED OF IN ACCORDANCE WITH APPLICABLE
REGULATIONS.
7. THE CONTRACTOR SHALL FOLLOW LOCAL RULES AND REGULATIONS FOR SOIL EROSION AND
SEDIMENTATION CONTROL FOR ALL MATERIALS THAT ARE DISPOSED OF OFF THE PROJECT SITE.
8. IF THE PROJECT OR ANY CONSTRUCTION ACTIVITY IS STOPPED FOR ANY LENGTH OF TIME OTHER THEN
THAT ENCOUNTERED IN A NORMAL WORK WEEK, EVERY PRECAUTION SHALL BE TAKEN TO PROTECT THE
UNCOMPLETED WORK FROM EROSION, INCLUDING THE PLACEMENT OF RIP RAP, HAY BALES OR OTHER
ACCEPTABLE TEMPORARY PRECAUTION.
9. THE CONTRACTOR SHALL SWEEP PAVED ROADS AND OTHER PAVED SURFACES DAILY, OR AS REQUESTED
BY THE ENGINEER, TO REMOVE TRACKED SOIL AND DEBRIS.
10. THE CONTRACTOR SHALL INSTALL SILT FENCES AND ROCK FILTERS AS TEMPORARY EROSION AND
SEDIMENTATION CONTROL IN DISTURBED AREAS AS REQUIRED AND AS SHOWN ON THE PLANS.
11. THE CONTRACTOR SHALL INSTALL NON-WOVEN FILTER FABRIC ON ALL CATCH BASINS DURING
CONSTRUCTION TO FILTER MATERIALS ENTERING CATCH BASINS.
12. THE CONTRACTOR SHALL CLEAN OUT ALL CATCH BASINS AND FLUSH OUT ALL LINES AT THE COMPLETION
OF THE PROJECT.
13. THE CONTRACTOR SHALL SUBMIT PROPOSED STOCK PILE AND SPOIL PILE LOCATIONS TO THE ENGINEER
FOR APPROVAL PRIOR TO STOCKPILING MATERIAL ON SITE.
14. SPOIL PILES SHALL BE GRADED SO THAT THE SLOPES ARE NOT STEEPER THEN 3:1 AND SHALL BE SEEDED
AND MULCHED.
15. SPOIL PILES SHALL HAVE SILT FENCE PLACED AT THE BASE OF THE SPOIL PILES TO RETAIN SOIL UNTIL
VEGETATION IS ESTABLISHED.
16. THE CONTRACTOR SHALL BE RESPONSIBLE FOR SECURING ALL NECESSARY PERMITS FOR THE PROJECT
INCLUDING THE SOIL EROSION AND SEDIMENTATION CONTROL PERMIT AS REQUIRED BY CVT HAVING
JURISDICTION.
GENERAL NOTES
1. IT IS THE CONTRACTOR'S RESPONSIBILITY TO SECURE ALL PERMITS AND POST ALL BONDS PRIOR
TO CONSTRUCTION, OR ENSURE THAT ALL REQUIRED PERMITS AND BONDS HAVE BEEN OBTAINED
PRIOR TO CONSTRUCTION.
2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROTECTING CORNERS WHEN WORKING WITHIN
THE ROW OF XXX.
3. CONTRACTOR SHALL KEEP ALL PUBLIC STREETS ADJACENT TO THE SITE FREE OF CONSTRUCTION
DEBRIS AND SEDIMENT. DUST SHALL BE CONTROLLED ON SITE AT ALL TIMES BY WATERING OR
OTHER NECESSARY MEANS.
4. THE CONTRACTOR SHALL BE LIABLE FOR ANY DAMAGE TO STREETS, SIDEWALKS OTHER
STRUCTURES AND ADJACENT AREAS CAUSED BY DEMOLITION, HAULING, OR OTHER PERFORMANCE
OF THE WORK.
5. THE CONTRACTOR SHALL TAKE ALL NECESSARY ACTIONS TO ENSURE WORKER SAFETY AND
COMPLIANCE WITH MI-OSHA GUIDELINES.
6. CONTRACTOR IS RESPONSIBLE FOR FIELD VERIFYING ALL DIMENSIONS PRIOR TO CONSTRUCTION.
ADJUST WORK AS REQUIRED TO MEET FIELD DIMENSIONS AT NO ADDITIONAL COST TO THE OWNER.
DISCREPANCIES SHALL BE BROUGHT TO THE ATTENTION OF THE ENGINEER AS SOON AS POSSIBLE.
7. THE IMPROVEMENTS COVERED BY THESE PLANS SHALL BE DONE IN ACCORDANCE WITH THE
PROPOSAL AND ACCOMPANYING SPECIFICATIONS FOR THIS PROJECT INCLUDING THE 2020 MDOT
STANDARD SPECIFICATIONS FOR CONSTRUCTION, AASHTO'S 2011 POLICY ON GEOMETRIC DESIGN
OF HIGHWAYS AND STREETS, THE 2011 MICHIGAN MANUAL OF UNIFORM TRAFFIC CONTROL
DEVICES AND CVT HAVING JURISDICTION.
8. THE CONTRACTOR SHALL CONDUCT OPERATIONS IN SUCH A MANNER AS TO COMPLY WITH ALL
FEDERAL, STATE, AND LOCAL CODES FOR NOISE LEVELS, HOURS OF OPERATION FOR
CONSTRUCTION ACTIVITY, VIBRATIONS, OR ANY OTHER RESTRICTIONS. NO ADDITIONAL
COMPENSATION WILL BE DUE TO THE CONTRACTOR FOR ANY WINTER PROTECTION MEASURES
THAT MAY BE REQUIRED TO COMPLY WITH THE CONTRACT DOCUMENTS.
9. COORDINATION BY THE CONTRACTOR; NO ADDITIONAL COMPENSATION SHALL BE PAID TO THE
CONTRACTOR FOR ANY DELAY OR INCONVENIENCE DUE TO MATERIAL SHORTAGES OR DELAYS DUE
TO THE OPERATIONS OF SUCH OTHER PARTIES DOING WORK INDICATED OR SHOWN ON THE PLANS
OR IN THE PROPOSAL OR FOR ANY DELAYS IN CONSTRUCTION DUE TO THE ENCOUNTERING OF
EXISTING UTILITIES THAT MAY OR MAY NOT BE SHOWN ON THE PLANS.
10. ANY QUANTITIES AND DIMENSIONS SHOWN IN PLANS ARE PROVIDED FOR INFORMATION ONLY, CONTRACTOR SHALL FIELD VERIFY PRIOR TO CONSTRUCTION.
CULVERT TRENCH
1. BEDDING UNDER THE CULVERT SHALL BE AS SPECIFIED AND THE UNDERCUT MATERIAL REPLACED WITH
GRANULAR MATERIAL CLASS IIIA. BACKFILLING SHALL BE IN ACCORDANCE TO THE PROJECT SPECIFICATIONS
AND MANUFACTURER'S REQUIREMENTS.
2. BACKFILL FOR CULVERT TRENCHES ABOVE GRANULAR MATERIAL CLASS II SHALL BE PLACED AS FOLLOWS:
2.1. GRANULAR MATERIAL MDOT CLASS II SHALL BE USED TO BACKFILL TRENCHES UNDER ROADS/TRAILS
AND SHALL BE COMPACTED TO NOT LESS THAN 95% OF ITS MAXIMUM UNIT WEIGHT.
2.2. GRANULAR MATERIAL MDOT CLASS II SHALL BE USED TO BACKFILL CULVERT TRENCHES OUTSIDE THE
ROADS/TRAILS BUT WITHIN THE 1:1 ZONE OF INFLUENCE AND SHALL BE COMPACTED TO NOT LESS THAN
95% OF ITS MAXIMUM UNIT WEIGHT.
2.3. SATISFACTORY MATERIAL EXCAVATED FROM THE CULVERT TRENCHES SHALL BE USED TO BACK FILL
CULVERT TRENCHES OUTSIDE THE LIMITS OF THE 1:1 ZONE OF INFLUENCE AND COMPACTED TO NOT
LESS THAN 95% OF ITS MAXIMUM UNIT WEIGHT.
EGLE-WRD
WRP031521 v1.0
Approved Issued On:11/09/2021
Expires On:11/09/2026
P
U
R I
B U
E
S
U
N
U
M
C
I
R
C
U M
S P
I
C
E
S
I
Q
U
E
R E
I
S
P E
N I
N S
U L
A
M
A
M
O
E
N
A
M
ARCHITECTS. ENGINEERS. PLANNERS
OHM-ADVISORS.COM
P:
\71
_7
0\7
0_ na hm a_ gr ad e_ mu ltiu se
_tr ail
\D ra wi ng s\C ivi l\M isc
\21
LE
G.
dw g S ep
, 2
1 - 4:
pm
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
FA
CI
LI
TI
ES
A
N D
B U
SI
N
ES
S
SE
RV
IC
ES
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
424 HANCOCK STREET
HANCOCK, MICHIGAN 49930
PH. 906.482.0535
F 906.482.6453
7136-21-0010
CURB AND GUTTER, REM
GUY WIRE
CONIFEROUS TREE
CONIFEROUS SHRUB
DECIDUOUS TREE
DECIDUOUS SHRUB
ELECTRIC RISER
ELECTRIC METER
GAS METER
GAS RISER
GAS VALVE
GUY POLE
IRON ROD/PIPE
LIGHT/DECOR LAMP POLE
PK NAIL
SOIL BORING
SECTION CORNER
SIGN
STUMP
TRANSFORMER PAD
SURVEY TRAVERSE POINT
PRIVATE UTILITY MANHOLE
UTILITY POLE
RIPRAP
SURVEY BENCHMARK
ELECTRICAL *
GAS\OIL
ROW
SECTION
HEDGE/TREE
FENCE
GUARDRAIL
CENTERLINE OF DITCH
SALVAGE
BULKHEAD
ABANDON
CLEARING
REMOVE
PROPERTY/PARCEL
FLOW DIRECTION
SIDEWALK REMOVAL
PAVEMENT REMOVAL
HMA SURFACE REMOVAL
WETLAND/EDGE OF WATER
CENTERLINE OF DITCH
FENCE
CABLE/TELEPHONE *
RIPRAP
SIGN
FLOW DIRECTION
STRUCTURE NUMBER
WM SAN STM
UTILITY POLE W/LIGHT
RELOCATE
RECONSTRUCT
RELOCATE BY OTHERS
ADJUST BY OTHERS
B
A
C
R
REL
REC
REL B/O
ADJ B/O
CL 1
CL 2
CL 3
1" TO 5"
6" TO 17"
18" TO 35"
CL 4 36" AND UP
TREE, REM
PROPOSED SPOT GRADE
EX AND PROP PARKING SPACE COUNT
EX AND PROP BARRIER FREE PARKING SPACE
749.25 FG
EXISTING SPOT GRADE
FLOW DIRECTION
EXISTING CONTOUR
PROPOSED CONTOUR
ASPHALT
CONCRETE
CONCRETE
SILT FENCE
INLET FILTER
CHECK DAM, STONE
LAWN
SPECIALTY SEED
SPECIALTY SEED
SPECIALTY SEED
GRAVEL
TRAIL REMOVAL / GRADING
SIGN, REM
ASPHALT, HEAVY
SLOPE RESTORATION
EXCAVATION LIMITS
CLEARING
ADJ ADJUST
APPROX APPROXIMATELY
ASPH ASPHALT
B/BANK BOTTOM OF BANK
CONC CONCRETE
CT CURB TRANSITION
C&G CURB AND GUTTER
CVT CITY, VILLAGE, TOWNSHIP
DIA DIAMETER
DW DOMESTIC WATER
EA EDGE OF ASPHALT
ELEC ELECTRIC
ELEV ELEVATION
EX EXISTING
F/C FACE OF CURB
FF FINISH FLOOR
FG FINISHED GRADE
FT FEET
HDCP HANDICAP
INV INVERT ELEVATION
OB OBSERVATION WELL
OBS OBSERVED
OH OVERHEAD
OT OVER TOPPING
PROP PROPOSED
R RADIUS
RES RESET
RIM TOP OF UTILITY/DRAINAGE STRUCTURE
ROW RIGHT-OF-WAY
SAN SANITARY
SP SPRING WATER
SQFT SQUARE FEET
STM STORM
SYD SQUARE YARD
TC TOP OF CURB
TELE TELEPHONE
TP TRAVERSE POINT
TS&M TOPSOIL, SEED & MULCH
TYP TYPICAL
T/BANK TOP OF BANK
UG UNDER GROUND
UNO UNLESS NOTED OTHERWISE
WEL WELL LINES
W# WELL LINE
WM WATER MAIN
WTR WATER
YBT YELLOW BENCH LINE
D50 RIPRAP SIZE WHERE 50% OF STONES
ARE LARGER
DMAX MAX STONE SIZE/AVG DEPTH OF
RIPRAP
OM3 SIGN1
COMPACTED 6A STONE
FINISHED GRADE
DRILL 2
"Ø HOLE, CENTERED
6" X 6" WOLMANIZED WOOD POST
MUTCD OM3-L (LEFT APPROACH), OM3-R (RIGHT APPROACH)
WATTLES
FOOT PATH TRAIL AGGREGATE
18" HDPE PIPE
EGLE-WRD
WRP031521 v1.0
Approved
S
F
S
F
S
F
S
F
S
F
S
F
S
F
S
F
S
F
S
F
NAHMA
C
O
U
N
T
Y
R
O
A
D
US-2
NAHMA
C
O
U
N
US-2
QUANTITIES THIS SHEET (FOR REFERENCE ONLY)
UNIT DESCRIPTION
Acre
Clearing
Cyd Excavation, Earth
Cyd Excavation, Peat
Cyd Erosion Control, Maintenance, Sediment Rem
Ea
Erosion Control, Sand Bag
Ea
Erosion Control, Sediment Trap
Ft
Erosion Control, Silt Fence
LSUM
_Dewatering Including SESC
LSUM
_Temporary Bypass Channel
Know what's below.
before you dig.Call
R feetGRAPHIC SCALE: FULL feetHALF
3020105
P
L
U
R I
B U
E
S
U
N
U
M
C
I
R
C
U M
S P
I
C
E
S
I
Q
U
E
R E
I
S
P E
N I
N S
U L
A
M
A
M
O
E
N
A
M
ARCHITECTS. ENGINEERS. PLANNERS
OHM-ADVISORS.COM
P:
\71
_7
0\7
0_ na hm a_ gr ad e_ mu ltiu se
_tr ail
\D ra wi ng s\C ivi l\R em ov al\
RE
M.
dw g S ep
, 2
1 - 4:
pm
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
FA
CI
LI
TI
ES
A
N D
B U
SI
N
ES
S
SE
RV
IC
ES
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
424 HANCOCK STREET
HANCOCK, MICHIGAN 49930
PH. 906.482.0535
F 906.482.6453
7136-21-0010
NORTH WATER CROSSING - EXISTING1
EXCAVATION LIMITS
CLEARING LIMITS, TYP
REMOVE SURFACE SOILS/ORGANICS
AND EXCAVATE FOR NEW STRUCTURE
REMOVE SURFACE SOILS/ORGANICS
AND EXCAVATE FOR NEW STRUCTURE
KEY PLAN
WATER DIVERSION NOTES:
1. CONTRACTOR HAS THE OPTION ON HOW TO DIVERT THE WATER. THE
FLOW CAN EITHER BE DIVERTED WITH A TEMPORARY BYPASS
CHANNEL, OR THE WATER CAN BE BYPASS PUMPED.
GENERAL NOTES:
1. WATER CONTROL DURING CONSTRUCTION SHALL BE THE
RESPONSIBILITY OF THE CONTRACTOR.
2. SURVEY DATA WAS COLLECTED 05/13/21, IN NAD83 MICHIGAN STATE
PLANES, NORTH ZONE, INTERNATIONAL FOOT (MI83-NIF).
3. USFS ROAD 2141 CAN BE IMPROVED FOR ACCESS IF REQUIRED.
CLEARING LIMITS SHALL BE LIMITED TO 16' WIDE AND 14' TALL. RUTS
SHALL BE REPAIRED AND GRADED PRIOR TO LEAVING THE SITE.
AGGREGATES USED TO IMPROVE THE ROUTE REMAIN IN PLACE.
SITE LOCATION
PROPOSED TRAIL
TO USFS ROAD 2141
EGLE-WRD
WRP031521 v1.0
Approved
NAHMA
C
O
U
N
US-2
BEGIN CONSTRUCTION
ALIGN STA 180+60.00
N 403592.543
E 26321339.616
BEGIN CONSTRUCTION
ALIGN STA 181+60.00
N 403679.820
E 26321290.802
C
QUANTITIES THIS SHEET (FOR REFERENCE ONLY)
TOTAL UNIT DESCRIPTION
1 Sta
Machine Grading
Cyd Backfill, Structure, CIP
0.24 Sta
Ditch, Intercepting
Cyd Subbase, CIP
Syd Aggregate Surface Cse, 6 inch
Syd Geotextile, Separator
Cyd Culv Bedding, Box Culv
40.5 Ft
_Culv, Aluminum, 14'-1" x 6'-2"
4 Ea
_Wood Sign Post, 6"x6" Treated
4 Ea
_Object Marker Sign
Cyd Riprap, Plain, LM
Know what's below.
before you dig.Call
R
P
L
U
R I
B U
E
S
U
N
U
M
C
I
R
C
U M
S P
I
C
E
S
I
Q
U
E
R E
I
S
P E
N I
N S
U L
A
M
A
M
O
E
N
A
M
ARCHITECTS. ENGINEERS. PLANNERS
OHM-ADVISORS.COM
P:
\71
_7
0\7
0_ na hm a_ gr ad e_ mu ltiu se
_tr ail
\D ra wi ng s\C ivi l\p lan s_ co ns t\2
0C
ON
.dw g
S ep
, 2
1 -
4:
pm
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
FA
CI
LI
TI
ES
A
N D
B U
SI
N
ES
S
SE
RV
IC
ES
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
424 HANCOCK STREET
HANCOCK, MICHIGAN 49930
PH. 906.482.0535
F 906.482.6453
7136-21-0010
NORTH WATER CROSSING - PROPOSED1
feetGRAPHIC SCALE: FULL feetHALF
3020105
MACHINE GRADING
AGGREGATE SURFACE COURSE
SUBBASE, CIP
RIPRAP, PLAIN
RIPRAP, PLAIN
KEY PLAN
TO USFS ROAD 2141
40 LF - CORRUGATED
ALUMINUM CULVERT
14'-1" x 6'-2"
SIGN, OM-3
SITE LOCATION
PROPOSED TRAIL
EGLE-WRD
WRP031521 v1.0
Approved
0.00%
179+50 180+00
181+00
182+00
182+50
0+00
0+63
Know what's below.
before you dig.Call
R
P
L
U
R I
B U
E
S
U
N
U
M
C
I
R
C
U M
S P
I
C
E
S
I
Q
U
E
R E
I
S
P E
N I
N S
U L
A
M
A
M
O
E
N
A
M
ARCHITECTS. ENGINEERS. PLANNERS
OHM-ADVISORS.COM
P:
\71
_7
0\7
0_ na hm a_ gr ad e_ mu ltiu se
_tr ail
\D ra wi ng s\C ivi l\p lan s_ co ns t\2
0C
ON
.dw g
S ep
, 2
1 -
4:
pm
D
EP
A
RT
M
EN
T O
F
TE
CH
N
O
LO
G Y
, M A
N A
G
EM
EN
T
A N
D B
U D
G
ET
ST
A
TE
O
F M
IC
H
IG
A
N
A D
A M
P . L
A C
H , R
A , D
IR
EC
TO
R
FA
CI
LI
TI
ES
A
N D
B U
SI
N
ES
S
SE
RV
IC
ES
A D
M
IN
IS
TR
A
TI
O N
D
ES
IG
N
A N
D C
O N
ST
R
U C
TI
O
N D
IV
IS
IO
N
424 HANCOCK STREET
HANCOCK, MICHIGAN 49930
PH. 906.482.0535
F 906.482.6453
7136-21-0010
NORTH WATER CROSSING PROPOSED CULVERT PROFILE3
NORTH WATER CROSSING PROPOSED TRAIL CENTERLINE PROFILE4
APPROX EXC LIMITS
14'-1" x 6'-2" CORRUGATED
ALUMINUM 4 SIDED
6" 6A (CRUSHED) STONE
2" LEVELING COURSE OF 34R OR
" CHIPS
US300NW FILTER FABRIC
ENCLOSING BEDDING
UPSTREAM INVERT: 594.10
14"-1" x 6'-2" CORRUGATED
ALUMINUM 4 SIDED
6" 6A (CRUSHED) STONE
2" LEVELING COURSE
OF 34R OR
" CHIPS
US300NW FILTER FABRIC
ENCLOSING BEDDING
24" THICK LAYER OF RIPRAP
RIPRAP
DOWNSTREAM INVERT: 594.10
TYPICAL TRAIL SECTION - PROPOSED2
SALVAGE AND REUSE TOPSOIL.
PLACE SEED AND MULCH.
EXISTING TRAIL SURFACE
TRAIL
6" 23A SURFACE CSE AGG, COMPACTED TO 97% MAX DENSITY
12" MDOT CL II SUBBASE COMPACTED TO 95% MAX DENSITY
COMPACT SUBGRADE TO 95% MAX DENSITY.
STA 0+12
INVERT: 594.10'
STA 0+52
INVERT: 594.10'
STA 0+32,
CENTERLINE OF TRAIL
EXISTING STREAM BED
ELEVATION: 595.83
(PROPOSED TO MATCH
EXISTING)
SLOPE MEASURED
TO POINT ON
CULVERT CLOSEST
TO TRAIL EDGE
CL OF TRAIL ELEVATION: 603.97
EDGE OF WATER 597.68
OBSERVED 05/13/2021
MINIMUM 2.1' OF COVER
OHWM ELEVATION: 598.00
100 YR WATER ELEV: 602.22
PROPOSED SLOPE
APPROX EXISTING SLOPE
2.0'
RIPRAP, PLAIN
SLOPE RESTORATION, TYPE C
TYPICAL DITCH SECTION - PROPOSED1
18"
4.0'
EGLE-WRD
WRP031521 v1.0
Approved
C
O
S E
O U
T R
E Q
U
IR
E M
E N
S
Contractor Close Out Check List Pink Sheet Attachment
Substantial Completion – Minimum Requirements o Certificate of Substantial Completion - A punch list and a final completion date are required.
o Certificate of Occupancy - Temporary Certificate of Occupancy or Partial Certificate of Occupancy o Final Code Permit Approvals - Local city or county government may have delegated authority for elevator approvals.
• May include General Building Permit, Plumbing, Mechanical, Electrical, HVAC, site work, elevator division o Final Health Department Approval - Including water testing, equipment approvals, backflow preventer testing, etc.
o Final Fire Marshall (Office of Fire Safety) Approval - Local fire departments may have delegated authority.
o Final HVAC and Water Balancing - reports if required o Final Fire Alarm and Sprinkler System Certifications o Agency Training - Complete all specified training.
o Operator & Maintenance Manuals - A minimum of one complete O&M manual must be provided at the time of
Substantial Completion. Remaining specified copies must be submitted for Final Completion.
o Turnover Special Tools and Equipment - turned over to the agency on or before the date of Substantial
Completion o Keys/Locksets - temporary of permanent lock cores and the submission of all specified keys to agency representative o Commissioning - final operational testing, startup reports or testing reports
Final Completion o Final Payment - DTMB-440 o Final Bond Company/Surety Release for Final Payment o Completion of All Punch List Work o General Guarantee/Warrantees - DTMB-437 o Extended Guarantees/Warrantees - all specified material/equipment extended warranties o Final Contract Change Order - includes final adjustments to unit price work, allowances, liquidated damages, time extensions and extended general conditions if applicable o As Built Drawings - record documents including a final site survey when required; submit per the contract o Disposal Records - Submit copies of disposal records, as specified, for materials being removed from the project.
o Maintenance Agreements - Submit all specified agreements for elevators, kitchen equipment or specialized systems.
o Operator & Maintenance Manuals - submission of the remaining copies specified that were not submitted at
Substantial Completion o SESC and Storm Water Permits - submit evidence of final closure o Extra Material/Spare Parts - submit evidence of turnover to the agency of all specified materials and parts o Demobilization - final cleaning, removal of all temporary measures and restoration of project site
• No salvage or surplus material may be sold or burned on the agency project site
• The contractor shall recycle or properly dispose of all surplus or salvage material
DTMB-0437 (R 04/19)
GUARANTEE AND INDEBTEDNESS STATEMENT
RETURN TO: DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration
Design and Construction Division
Mailing Address: P.O. Box 30026, Lansing, MI 48909
Street Address: 3111 W. St. Joseph Street, Lansing, MI 48917
This form is required to receive final payment for the contract. Upon completion, submit a completed form to the address above. Authority: 1984 PA 431
The undersigned provides the following statements covering the work defined in the contract dated:
SIGMA CODING
AGENCY NUMBER
FILE NUMBER
CONTRACT NUMBER
DEPARTMENT/AGENCY
PROJECT NAME
GUARANTEE
We guarantee that all labor and materials furnished and the Work performed by us in connection with the subject work are in accordance with the plans and specifications, authorized alterations and additions that should any defects develop or become apparent for a period of __________ year(s) from date of acceptance ______________________________ the same shall, upon written notice, be made good by us without expense to the Owner, and that any other Work, affected in correcting such defects shall also be made good. In addition to the above guarantee, the following additional items are guaranteed as noted:
INDEBTEDNESS STATEMENT
We certify that all payrolls, material bills, and other indebtedness connected with the work on the subject project have been paid in full.
COMPANY NAME AND CONTRACTOR'S SIGNATURE DATE
WITNESS SIGNATURE DATE
cc: Agency
Designer
DTMB-0445 (R 04/19)
CERTIFICATE OF SUBSTANTIAL COMPLETION
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration
Design and Construction Division
DATE OF SUBSTANTIAL COMPLETION:__ ______________________
FINAL COMPLETION DATE:____ ____________________
The work performed under the subject contract between the State of Michigan and the contractor named at the location listed, has been inspected and found to be in compliance with the contract documents, including duly authorized changes, except for the list of the exceptions noted. The Contractor agrees to complete or correct these items on or before (date):
SIGMA CODING
AGENCY NUMBER
FILE NUMBER
CONTRACT NUMBER
DEPARTMENT/AGENCY
PROJECT NAME
CONTRACT PRICE
CONTRACTOR NAME AND ADDRESS
PROFESSIONAL
1. SCOPE: This Certificate of Substantial Completion is for the entire Work or the parts of the Work listed in Attachment A .
2. DIVISION OF RESPONSIBILITIES: The responsibilities between the Owner and Contractor for security, operation, safety, maintenance, heat and utilities, insurance and warranties and guarantees, pending final payment (or Substantial Completion of the entire
Work), shall be as shown on Attachment B.
3. DOCUMENTS ATTACHED: The following documents are attached to and made a part of this Certificate:
PUNCH LIST
Provide all Closeout Documents
APPROVALS
AGENCY REPRESENTATIVE DATE
CONTRACTOR DATE
STATE FACILITIES ADMINISTRATION DATE
PROFESSIONAL DATE
White - Contract Green - Project Manager Canary - Professional Service Contractor Pink - Contractor Goldenrod - Agency
Items of work must be completed before final payment can be made and the contract close out. Authority: 1984 PA 431.
E C
H N
IC
A
L S
P E
C
IF
IC
A
T
IO
N S
SUBMITTAL ITEM CONTRACTOR DATE FIRM DUE DATE
SUBCONTRACTOR SENT DATE REC'D
010000 FIELD TESTING
Tests Performed
312000 EARTH MOVING
Product Data
Material Test Reports
312319 DEWATERING
Shop Drawings
329200 TURF AND GRASSES
Certification of Grass Seed
Product Certificates
334100 STORM UTILITY DRAINAGE PIPING
Product Data
Shop Drawings
D A
TE
R
ET
U
R N
ED
C O
N
TR
A C
TO
R
O W
N
ER
FI
EL
D
FI
LE
N O
T A
P P
'D
SUBMITTAL LOG
PROJECT: Nahma Grade Multiuse Trail
OWNER: MI DTMB/DNR
PROJECT NO: 7136-21-0010
CONTRACTOR:
OTHER REVIEWER ACTION COPIES TO
D A
TE
R
EC
'D
SP
EC
IF
A
TI
O
N S
EC
TI
O N
N O
N O
. R
EC
EI
V
ED
N O
. C O
P
IE
S
A P
P R
O V
ED
A P
P R
O V
ED
A
S N
O
TE
D
R
EV
IS
E
R
ES
U
B M
IT
To Be Performed
Table of Contents Generated by SpecBuilder: 5/24/2023
Division
Section Title
Pages
DIVISION 31
EARTHWORK
31 10 00
SITE CLEARING
31 20 00
EARTH MOVING
31 23 19
DEWATERING
31 25 00
EROSION AND SEDIMENTATION CONTROLS
DIVISION 32
EXTERIOR IMPROVEMENTS
32 92 00
TURF AND GRASSES
DIVISION 33
UTILITIES
33 41 00
STORM UTILITY DRAINAGE PIPING
END OF TABLE OF CONTENTS
DTMB/DNR
Nahma Grade Multiuse Trail DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
SITE CLEARING
31 10 00 - Page 1 of 3
05/24/2023
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
SECTION 31 10 00 - SITE CLEARING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Removing existing vegetation.
2. Clearing and grubbing.
3. Stripping and stockpiling topsoil.
B. Related Requirements:
1. Section 31 25 00 "Eroision and Sedimentation Controls" for temporary erosion- and sedimentation-control measures.
1.2 DEFINITIONS
A. Subsoil: Soil beneath the level of subgrade; soil beneath the topsoil layers of a naturally occurring soil profile, typified by less than 1 percent organic matter and few soil organisms.
B. Surface Soil: Soil that is present at the top layer of the existing soil profile. In undisturbed areas, surface soil is typically called "topsoil," but in disturbed areas such as urban environments, the surface soil can be subsoil.
C. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface soil; the zone where plant roots grow.
D. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface soil; the zone where plant roots grow. Its appearance is generally friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects larger than 2 inches in diameter; and free of weeds, roots, toxic materials, or other nonsoil materials.
E. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1.3 MATERIAL OWNERSHIP
A. Except for materials indicated to be stockpiled or otherwise remain Owner's property, cleared materials shall become Contractor's property and shall be removed from Project site.
1.4 FIELD CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.
2. Provide alternate routes around closed or obstructed trafficways if required by Owner or authorities having jurisdiction.
B. Utility Locator Service: Notify Miss Dig for area where Project is located before site clearing.
C. Do not commence site clearing operations until temporary erosion- and sedimentation-control measures are in place.
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
SITE CLEARING
31 10 00 - Page 2 of 3
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
D. Soil Stripping, Handling, and Stockpiling: Perform only when the soil is dry or slightly moist.
PART 2 - PRODUCTS
2.1 (NOT USED)
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect and maintain benchmarks and survey control points from disturbance during construction.
B. Protect existing site improvements to remain from damage during construction.
1. Restore damaged improvements to their original condition, as acceptable to Owner.
3.2 EXISTING UTILITIES
A. Interrupting Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others, unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Engineer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Engineer's written permission.
3.3 CLEARING AND GRUBBING
A. Remove obstructions, trees, shrubs, and other vegetation to permit installation of new construction.
1. Do not remove trees, shrubs, and other vegetation indicated to remain or to be relocated.
2. Grind down stumps and remove roots larger than 2 inches in diameter, obstructions, and debris to a depth of 12 inches below exposed subgrade.
B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless further excavation or earthwork is indicated.
1. Place fill material in horizontal layers not exceeding a loose depth of 8 inches, and compact each layer to a density equal to adjacent original ground.
3.4 TOPSOIL STRIPPING
A. Strip topsoil to depth of 6 inches in a manner to prevent intermingling with underlying subsoil or other waste materials.
1. Remove subsoil and nonsoil materials from topsoil, including clay lumps, gravel, and other objects larger than 2 inches in diameter; trash, debris, weeds, roots, and other waste materials.
B. Stockpile topsoil away from edge of excavations without intermixing with subsoil or other materials. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust and erosion by water.
1. Limit height of topsoil stockpiles to 72 inches .
2. Stockpile surplus topsoil to allow for respreading deeper topsoil.
3.5 SITE IMPROVEMENTS
A. Remove structures and aggregate base as indicated.
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
SITE CLEARING
31 10 00 - Page 3 of 3
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
3.6 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste materials including trash and debris, and legally dispose of them off Owner's property.
END OF SECTION 31 10 00
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
EARTH MOVING
31 20 00 - Page 1 of 9
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
SECTION 31 20 00 - EARTH MOVING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Excavating and filling for rough grading the Site.
2. Preparing subgrades for trails, box culverts, and turf and grasses .
3. Excavating and backfilling for structures.
4. Bedding and leveling course for box culverts.
5. Subbase course and base course for trails and walks.
6. Aggregate surface course for multi-use trails and roads.
7. Aggregate surface course for foot paths and walks.
B. Related Requirements:
1. Section 31 10 00 "Site Clearing" for site stripping, grubbing, stripping and stockpiling topsoil, and removal of above- and below-grade improvements and utilities.
2. Section 32 92 00 "Turf and Grasses" for finish grading in turf and grass areas, including preparing and placing planting soil for turf areas.
1.3 DEFINITIONS
A. Backfill: Soil material or controlled low-strength material used to fill an excavation.
1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.
2. Final Backfill: Backfill placed over initial backfill to fill a trench.
B. Base Course: Aggregate layer placed between the subbase course and surface course or structures.
C. Bedding Course: Aggregate layer placed on the excavated subgrade, supporting the box culvert.
D. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.
E. Drainage Course: Aggregate layer that minimizes upward capillary flow of pore water.
F. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.
1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Engineer. Authorized additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work.
2. Bulk Excavation: Excavation more than 10 feet in width and more than 30 feet in length.
3. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Engineer. Unauthorized excavation, as well as remedial work directed by Architect, shall be without additional compensation.
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
EARTH MOVING
31 20 00 - Page 2 of 9
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
G. Fill: Soil materials used to raise existing grades.
H. Leveling Course: Aggregate layer placed over the bedding course in a trench before laying pipe or setting structures.
I. Structures: Buildings, footings, bridges, box culverts, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface.
J. Subbase Course: Aggregate layer placed between the subgrade and base course, or aggregate layer placed between the subgrade and aggregate surface course.
K. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase, bedding course, drainage fill, drainage course, or topsoil materials.
L. Multi-Use Surface Course: Aggregate layer placed on top of base or subbase serving as the finished/top surface on trails and roads.
M. Foot Path Surface Course: Aggregate layer placed on top of base or subbase serving as the finished/top surface on foot paths and walks.
N. Utilities: On-site underground pipes, conduits, ducts, and cables as well as underground services within buildings.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of the following manufactured products required:
1. Geotextiles.
2. Controlled low-strength material, including design mixture.
3. Particle size distribution (gradation) according to ASTM D6913.
1.5 INFORMATIONAL SUBMITTALS
A. Material Test Reports: For each borrow soil material proposed for fill and backfill as follows:
1. Classification according to ASTM D2487.
2. Laboratory compaction curve according to ASTM D698 or ASTM D1557.
3. Density/compaction field testing results.
1.6 FIELD CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth-moving operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.
2. Provide alternate routes around closed or obstructed traffic ways if required by Owner or authorities having jurisdiction.
B. Improvements on Adjoining Property: Authority for performing earth moving indicated on property adjoining Owner's property will be obtained by Owner before award of Contract.
1. Do not proceed with work on adjoining property until directed by Engineer.
C. Utility Locator Service: Notify Miss Dig for area where Project is located before beginning earth-moving operations.
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
EARTH MOVING
31 20 00 - Page 3 of 9
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
D. Do not commence earth-moving operations until temporary site fencing and erosion- and sedimentation-control measures specified in 31 25 00 "Erosion and Sedimentation Controls" are in place.
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.
B. Satisfactory Soils: Soil Classification Groups GW, GP, GM, SW, SP, and SM according to ASTM D2487 , or a combination of these groups; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.
C. Unsatisfactory Soils: Soil Classification Groups GC, SC, CL, ML, OL, CH, MH, OH, and PT according to ASTM D2487 , or a combination of these groups.
1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction.
D. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 90 percent passing a 1- 1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.
E. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 95 percent passing a 1-1/2-inch sieve and not more than 8 percent passing a No. 200 sieve.
F. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 90 percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.
G. Leveling Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; except with 100 percent passing a 1/2-inch sieve and not more than 3 percent passing a No. 200 sieve.
H. Bedding Course: Narrowly graded mixture of washed crushed stone, or crushed or uncrushed gravel; ASTM D448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and zero to 2 percent passing a No. 8 sieve.
I. Drainage Course: Narrowly graded mixture of washed crushed stone, or crushed or uncrushed gravel; ASTM D448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and zero to 5 percent passing a No. 8 sieve.
J. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone and natural sand; ASTM D448; coarse-aggregate grading Size 67; with 100 percent passing a 1-inch sieve and zero to 5 percent passing a No. 4 sieve.
K. Sand: ASTM C33/C33M; fine aggregate.
L. Multi-Use Surface Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with 100 percent passing a 1-inch sieve and not more than 16 percent passing a No. 200 sieve.
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
EARTH MOVING
31 20 00 - Page 4 of 9
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
M. Foot Path Surface Course: Meeting USFS 35A (Wigger Mix Formula) gradation:
1. Size Specifications (% passing): 3/8": 100%, No. 4: 70-75%, No. 8: 45-55%, No. 16: 30-
35%, No. 30: 20-25%, No. 50: 15-20%, No. 100: 10-15%, No. 200: 7-12%.
N. Impervious Fill: Clayey gravel and sand mixture capable of compacting to a dense state.
2.2 GEOTEXTILES
A. Subsurface Drainage Geotextile: Nonwoven needle-punched geotextile, manufactured for subsurface drainage applications, made from polyolefins or polyesters; with elongation greater than 50 percent; complying with AASHTO M 288 and the following, measured per test methods referenced:
1. Survivability: Class 2; AASHTO M 288.
2. Survivability: As follows:
a. Grab Tensile Strength: 90 lbf; ASTM D4632.
b. Sewn Seam Strength: 142 lbf; ASTM D4632.
c. Tear Strength: 45 lbf; ASTM D4533.
d. Puncture Strength: 45 lbf; ASTM D4833.
3. Apparent Opening Size: No. 70 sieve, maximum; ASTM D4751.
4. Permittivity: 0.5 per second, minimum; ASTM D4491.
5. UV Stability: 50 percent after 500 hours' exposure; ASTM D4355.
B. Separation Geotextile: Woven geotextile fabric, manufactured for separation applications, made from polyolefins or polyesters; with elongation less than 50 percent; complying with AASHTO M 288 and the following, measured per test methods referenced:
1. Survivability: Class 2; AASHTO M 288.
2. Survivability: As follows:
a. Grab Tensile Strength: 247 lbf; ASTM D4632.
b. Sewn Seam Strength: 222 lbf; ASTM D4632.
c. Tear Strength: 90 lbf; ASTM D4533.
d. Puncture Strength: 90 lbf; ASTM D4833.
3. Apparent Opening Size: No. 40 sieve, maximum; ASTM D4751.
4. Permittivity: 0.02 per second, minimum; ASTM D4491.
5. UV Stability: 50 percent after 500 hours' exposure; ASTM D4355.
2.3 CONTROLLED LOW-STRENGTH MATERIAL
A. Produce low-density, controlled low-strength material with the following physical properties:
1. Compressive Strength: 140 psi , when tested according to ASTM C495/C495M.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth-moving operations.
B. Protect and maintain erosion and sedimentation controls during earth-moving operations.
C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials.
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
EARTH MOVING
31 20 00 - Page 5 of 9
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
3.2 DEWATERING
A. Provide dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit excavation and construction to proceed on dry, stable subgrades.
B. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.
C. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.
1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.
D. Dispose of water removed by dewatering in a manner that avoids endangering public health, property, and portions of work under construction or completed. Dispose of water and sediment in a manner that avoids inconvenience to others.
3.3 EXPLOSIVES
A. Explosives: Do not use explosives.
3.4 EXCAVATION, GENERAL
A. Classified Excavation: Excavate to subgrade elevations. Material to be excavated will be classified as earth and rock. Do not excavate rock until it has been classified and cross sectioned by Engineer. The Contract Sum will be adjusted for rock excavation according to the Contract Documents. Changes in the Contract Time may be authorized for rock excavation.
1. Earth excavation includes excavating pavements and obstructions visible on surface;
underground structures, utilities, and other items indicated to be removed; and soil, boulders, and other materials not classified as rock or unauthorized excavation.
a. Intermittent drilling; blasting, if permitted; ram hammering; or ripping of material not classified as rock excavation is earth excavation.
3.5 EXCAVATION FOR STRUCTURES
A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections.
1. Excavations for Footings and Foundations: Do not disturb bottom of excavation. Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.
2. Excavation for Underground Tanks, Basins, and Mechanical or Electrical Utility Structures:
Excavate to elevations and dimensions indicated within a tolerance of plus or minus 1 inch.
Do not disturb bottom of excavations intended as bearing surfaces.
3.6 EXCAVATION FOR TRAILS
A. Excavate surfaces under trails to indicated lines, cross sections, elevations, and subgrades.
DTMB File #751/20155.JBB
OHM PROJECT # 7136-21-0010
EARTH MOVING
31 20 00 - Page 6 of 9
Copyright © 2023 by the American Institute of Architects. Warning: This AIA MasterSpec-based document is protected by U.S. Copyright Law and International Treaties.
It was created by "OHM Advisors" for "Nahma Grade Multiuse Trail". A valid, current MasterSpec license is required for editing and use of this document for any other project.(15195)
3.7 UNAUTHORIZED EXCAVATION
A. Fill unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Lean concrete fill, with 28-day compressive strength of 2500 psi, may be used when approved by Engineer.
1. Fill unauthorized excavations under other construction, pipe, or conduit as directed by
Engineer.
3.8 STORAGE OF SOIL MATERIALS
A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.
3.9 BACKFILL
A. Place and compact backfill in excavations promptly, but not before completing the following:
1. Construction below finish grade including, where applicable, subdrainage, dampproofing, waterproofing, and perimeter insulation.
2. Surveying locations of underground utilities for Record Documents.
3. Testing and inspecting underground utilities.
4. Removing concrete formwork.
5. Removing trash and debris.
6. Removing temporary shoring, bracing, and sheeting.
7. Installing permanent or temporary horizontal bracing on horizontally supported walls.
B. Place backfill on subgrades free of mud, frost, snow, or ice.
3.10 UTILITY TRENCH BACKFILL
A. Place backfill on subgrades free of mud, frost, snow, or ice.
B. Place and compact bedding course on trench bottoms and where indicated. Shape bedding course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits.
C. Backfill voids with satisfactory soil while removing shoring and bracing.
D. Initial Backfill:
1. Soil Backfill: Place and compact initial backfill of subbase material , free of particles larger than 1-1/2 inches in any dimension, to a height of 12 inches over the pipe or conduit.
a. Carefully compact initial backfill under pipe haunches and compact evenly up on both sides and along the full length of piping or conduit to avoid damage or displacement of piping or conduit. Coordinate backfilling with utilities testing.
E. Final Backfill:
1. Soil Backfill: Place and compact final backfill of satisfactory soil to final subgrade elevation.
3.11 SOIL FILL
A. Plow, scarify,…