This is Amendment A00003 to a Request for Quote (RFQ) for the USCGC Anvil Dry Dock services issued by the Surface Force Logistics Center, United States Coast Guard. The amendment, effective November 10, 2026, provides clarifications and responses to quoter questions regarding the technical requirements and pricing for the Ice Breaker, Buoy & Construction Tender (IBCT) dry dock work. The requisition number is 70Z08527QIBCT0001, and quoters must acknowledge receipt of this amendment prior to the hour and date specified in the original solicitation or submit changes via letter or electronic communication referencing both the solicitation and amendment numbers.

The amendment addresses four primary clarifications: (1) the 10-page technical narrative requirement may address only the first six of eleven required bullets, with the remaining five bullets acceptable elsewhere in the submission; (2) Work Item 62 shall be priced by square foot, with quoters to assume interferences have been removed, the abated area is accessible, and lead paint is likely present at 24% by weight; (3) Work Item 52 for non-machinery space preservation shall assume 500 square feet will require preservation; and (4) the correct period of performance is May 12, 2027 through July 20, 2027. The amendment indicates the total contract price remains unchanged. One copy of the amendment must be returned with acknowledgment, and the contractor is required to sign and return one copy to the issuing office.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1

1. CONTRACT ID CODE

I

PAGE OF PAGES

I

3. EFFECTIVE DATE

5. PROJECT NUMBER (If applicable)

11/10/2026

CODE CODE I

2. AMENDMENT/MODIFICATION NUMBER

A00003

6. ISSUED BY

Surface Force Logistics Center United States Coast Guard

4. REQUISITION/PURCHASE REQUISITION NUMBER

70Z08527QI BCT0001

7. ADMINISTERED BY (If other than Item 6)

Surface Force Logistics Center United States Coast Guard

Ice Breaker, Buoy & Construction Tender (IBCT) Ice Breaker, Buoy & Construction Tender (IBCT) C&P2 Branch Building 55, Base Alameda C&P2 Branch Building 55, Base Alameda

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) SA. AMENDMENT OF SOLICITATION NUMBER

70Z08527QI BCT0001

SB. DATED (SEE ITEM 11)

11/10/2026

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE I FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

[8J The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers D is extended. [8J is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor Dis not [8] is required to sign this document and return __ 1 __ copies to the issuing office.

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

(Signature of person authorized to sign)

Previous edition unusable

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of the amendment is to answer USCGC Anvil DD RFQ request for clarification questions. Please see the attached continuation page.

Except as provided herein, all terms and conditions of the document referenced in Item SA or 1 OA, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of Contracting Officer)

STANDARD FORM 30 (REV.11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

(a) Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

(b) Item 3 (Effective date).

(1) For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

(2) For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

(3) For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

(4) For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

(5) For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(c) Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

(d) Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

(e) Items 9, (Amendment of Solicitation Number Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

(f) Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(1) Accounting classification _____ _ Net increase $ ____ _

(2) Accounting classification Net decrease $

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

(g) Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

(h) Item 14 (Description of AmendmenUModification).

(1) Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

(2) Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $ __ _

(ii) Total contract price decreased by$ __ _

(iii) Total contract price unchanged.

(3) State reason for modification.

(4) When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(5) When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(6) Include subject matter or short title of solicitation/contract where feasible.

(i) Item 168. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

STANDARD FORM 30 (REV. 11/2016) BACK

Continuation from Amendment 00003 Block 14:

1. Quoters shall provide a written narrative of no more than ten (10) pages providing amplifying information regarding the Quoter's technical capabilities to complete all work within the prescribed performance period. At a minimum the written narrative should explain the following: The paragraph follows with 11 bullets of required information.

Providing the required information in these 11 bullets will vastly exceed the 10 page limit. Much of this information is in a format dictated by the requirements and/or certifying 3rd party (insurance, AWS, SFLC Std spec 8634, etc).

Request you remove the 10 page limit or reduce the required information subject to the limit.

- For the 10-Page narrative, it is acceptable to only address the first 6 bullets. The remaining 5 bullets could be addressed elsewhere in the submission. They do not need to be in the written narrative but they do need to be included in the submission.

2. The wording of paragraph 1.1, Intent, indicates that the requirements contained in this work item are in support of other work items in the specification which may require Lead and/or Asbestos remediation to accomplish. As such, we expected the price schedule of services would indicate this work item is NSP, similar to WI 63 & 64.

The price schedule indicates the government desires a price per sq ft to meet the requirements of WI 62. It appears this per sq ft price is independent of other work items. It is impossible to estimate a per sq ft price without knowing the specifics of the location to be remediated.

Recommend this be changed to NSP and we will incorporate the costs to remediate into the specific work item where it is a part of the requirements.

- For Work Item 62, to validate the market rate for work, this work item was decided to be priced by SQFT. For this work item, you may assume interferences have been removed from the completion of other work items and that the abated area is accessible. If lead paint is present, it is likely 24% by weight. Please estimate this work item by SQFT with the above in mind.

3. In WI 52, “Non-Machinery Space(s), Preserve Bilges, Partial,” there is no specified surface area to be preserved. Partial preservation is typically considered to be 33% of the surface area, post ship check, more than 33% of the area would need to be prepped. To ensure an even field amongst all KTR, could a specified percentage or square footage be given for estimating purposes?

- For Work Item 52, assume 500sqft will require preservation.

4. The correct PoP is 5/12/2027 - 7/20/2027