This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the United States Coast Guard Surface Facility Logistics Center (SFLC) Alameda for the USCGC Juniper DD FY26 vessel maintenance and repair solicitation (70Z08526QIBCT0026).
Amendment No. 0001, effective April 1, 2026, addresses 17 contractor questions and clarifications regarding technical documentation, work item specifications, and the Schedule of Supplies and Services. Key responses include: confirmation that revised drawing 225-WLB_583_4_1_-_D and Coast Guard Technical Publication (TP) 3943 for the Twin Pivot Arm Davit are available from the Tech Librarian; clarification that "Calibrate TLI" requires verification of tank level accuracy against sounding tape and MPCMS display; and confirmation that the specification and Schedule of Supplies and Services have been updated and corrected to address discrepancies regarding work item numbering, missing CIR (Contractor Information Report) requirements, duplicate work items, and incomplete pricing sheets. The amendment consolidates responses to questions concerning missing reference drawings, clarification of work scope, option versus definite line items, and alignment of work item titles between the specification and pricing documentation. The contracting officer's responses indicate that the Activity Project Manager (APM) has updated and corrected all referenced documents, with corrected versions available as attachments to this amendment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Questions
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
USCGC JUNIPE DD FY26
The purpose of this amendment is to answer all these questions, please see page 2 for more details.
USCG SFLC ALAMEDA
BASE ALAMEDA, Building 55 Alameda, CA 94501
70Z08526QIBCT0026
04/0 /2026
9B. DATED (SEE ITEM 11)
04/0 /2026
70Z08526QIBCT0026
USCGC JUNIPER DD FY26
Amendment No. 0001
1. Work Item reference titled "Coast Guard Drawing 225-WLB 583-002, Rev E, MMA Installation of Dual Point Davit" was not included in the provided technical package. Will USG provide?
Answer: The DWG was revised to this 225-WLB_583_4_1_-_D. and the Coast Guard Technical Publication (TP) 3943, Twin Pivot Arm Davit - Type Tw.Piv 5.0B - Ref. No. 5558-l Thru 5558-15, they are requesting is active and the Tech Librarian can send it to them.
2. Work Item reference titled "Coast Guard Technical Publication (TP) 3943, Twin Pivot Arm Davit - Type Tw.Piv 5.0B - Ref.
No. 5558-l Thru 5558-15" was not included in the provided technical package. Will USG provide?
Answer: The DWG was revised to this 225-WLB_583_4_1_-_D. and the Coast Guard Technical Publication (TP) 3943, Twin Pivot Arm Davit - Type Tw.Piv 5.0B - Ref. No. 5558-l Thru 5558-15, they are requesting is active and the Tech Librarian can send it to them.
3. Under Inspection paragraph 3.6, "Calibrate TLI" is included. Will USG clarify what work this requirement entails?
Answer: Calibrate will be to verify the tank levels throughout the range is accurate to the sounding tape and MPCMS display.
4. Work items from 30 and onward did not match the title for CIRs needing submittal in the first 25% of the avail. Please clarify if the work item number or title requires the CIR.
5. Para 3.5 has blanks for the required quantity of UT measurements and the associated reference drawing. Will USG provide?
6. The provided Schedule of Supplies and Services indicate Items 58 and 59 are both definite, and Items 61 and 62 are both definite. KTR expects Items 58 and 61 to be option items. Will USG clarifies?
7. The specification contains Item title "Controllable Pitch Propeller, System Maintenance, Perform" as Item 30 but it is missing from the provided Schedule of Supplies and Services which shows Item title "Controllable Pitch Propeller Hub, General Maintenance with EAL, Perform" for D-030. Will USG clarify?
8. Para 3.2 is missing a referenced drawing. Will USG provide?
9. Contractor notes that Juniper (WBL) RO BLANK SOSS & Juniper DD FY REV0 SPEC 16 MAR 2026 table of contents and pricing sheet include 93 total items. However, the full package includes 94 total items including options. Can you Coast Guard provide a corrected pricing sheet (Juniper (WBL) RO BLANK SOSS )?
10. Work Item "Controllable Pitch Propeller, System Maintenance, Perform" is not included in the pricing schedule. In the spec, it is Work Item 30. Every work item number in the 25% list AFTER 29 is one less than the actual spec and Table of Contents.
11. Work Item 72 and Work Item 77 are duplicates: WORK ITEM 72: ATON Tie Down Installation, WORK ITEM 77: ATON Tie-down Install
12. Work Item 49: Anchor Windlass, Inspect and Service Task 3 has a placeholder for Task Type <<GEARBOX_TASK>>
13. WORK ITEM 69: Drydock Is in 25% list but no CIR is present in spec
14. WORK ITEM 72: ATON Tie Down Installation WI is in 25% list and "3.1.1 CIR" specifies CIR for paragraph 3.2.3. The paragraph 3.2.3 in spec has no CIR. It says submit a CFR
15. WORK ITEM 76: Welin Lambie Dual Point Davit TWPIV 5.0B, Renew Work Item is in 25% list. "3.1.1" has CIR specified for Task 1, but Task 1 in Table 1 does not have a CIR
16. WORK ITEM 86: Pilot House Windows and Frame, Repair and Reseal Work Item is on 25% CIR list, but no CIR is present in Work Item
17. WORK ITEM 87: Tanks, MP Fuel Stowage and Overflow, Clean and Inspect Work Item is in 25% list. "3.1.1 CIR" lists paragraph "3.9 UT measurements & Submit CIR." There is no 3.9 paragraph in the work specification Answer from 4 -17: APM has updated and corrected the SPEC and the SOSS, please see attachments.
All other terms and conditions remain in full force and effect
File details come from the government source that posted it. Updated .