SOW_CGC BEAR FY26 DD.pdf

PDF 1 MB Posted

Attached to
DRY DOCK USCG BEAR FY26 UPDD Federal contract opportunity
Solicitation number
70Z08026QMECP0008
Issued by
Department of Homeland Security US Coast Guard

About this file

This document is a Specification for Unplanned Drydock Repairs for the USCGC BEAR (WMEC-901), a 270-foot Medium Endurance Cutter operated by the United States Coast Guard. Developed by Allison J Waters and released on December 5, 2025 (Rev-0), this specification outlines requirements for vessel repairs to be performed at a commercial contractor facility during Fiscal Year 2026.

The contract encompasses three primary work items: (1) Tanks, Ballast, Repair and Preserve 100 Percent—requiring repair and preservation of three ballast tanks (4-228-1-W, 4-228-2-W, and 4-242-0-W) including approximately 900 square feet of steel plating renewal, manhole ring replacement, baffle fabrication, ladder renewal, 500 ultrasonic thickness measurements, and interior/exterior coating using systems specified in SFLC Standard Specification 6310; (2) Drydock—requiring the contractor to dock and undock the vessel, provide pre-award calculations for blocking arrangements, perform underwater hull cleaning within four hours of docking using high-pressure fresh water wash (3,500-7,000 psi), and accommodate potential modifications to the standard docking plan to maintain preservation and inspection requirements; and (3) Temporary Services—including parking, electrical power (400A/450V, 3-phase), potable water (5,000 gallons per day at 40 psig), cooling water, firemain system, hazardous waste disposal (4,000 gallons bilge water), and 48 hours of heavy lift equipment. The specification references SFLC Standard Specifications 0000, 0740, 6310, 8634, and 8635, along with Coast Guard drawings and applicable ASTM, CFR, and military standards. Government-furnished property limited to a transducer cover plate (PN: FL-184-002, DET 15-E) valued at $50.00 must be returned upon availability completion. The specification mandates quality assurance inspection forms, tank assessment documentation, preservation checklist compliance, environmental protection measures, and 24-hour advance notification prior to tank closure.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC BEAR (WMEC 901)

SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS

FY2026

Developed By: Allison J Waters

(Rev-0, 5 December 2025)

USCGC BEAR (WMEC-270A) UNPLANNED AVAILABILITY FY2026

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .................................................................................. v Consolidated List of Critical Inspection Items ............................................................................................. vi Principal Characteristics ............................................................................................................................. vii General Requirements WORK ITEM 1: Tanks, Ballast, Repair and Preserve 100 Percent WORK ITEM 2: Drydock WORK ITEM 3: Temporary Services, Provide - Cutter iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 901 WMEC 111-002, Rev G, Shell Exp Aft 182

Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182

Coast Guard Drawing 901 WMEC 131-002, Rev J, Mn Dk Pl & Fr, Aft 182

Coast Guard Drawing 901 WMEC 141-002, Rev H, 1st Platf Pltg & Framing, Aft 182

Coast Guard Drawing 901 WMEC 529-001, Rev N, Ballasting & Emer Bilge Drainage Sys Diagram

Coast Guard Drawing 901 WMEC 562-005, Rev K, A & B Class Rudder Stock And Steering Gear A & D

Coast Guard Drawing 901 WMEC 801-012, Rev B, Curves of Form

Coast Guard Drawing 901 WMEC 801-022, Rev L, Docking Plan

Coast Guard Drawing FL 184-002, Rev B, SS60 Transducer Install Adapter Assy

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses

OTHER REFERENCES

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

MIL-PRF-16173, Oct 2017, Corrosion Preventive Compound, Solvent Cutback, Cold Application v (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

2 Y *Transducer Cover

Plate PN: FL-184-002, DET 15-E 1 ea. 50.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vi (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4 (Inspection report particulars)):

This section is not applicable to this package.

vii (Rev-0)

PRINCIPAL CHARACTERISTICS

270' WMEC (A-CLASS)

PHYSICAL

Length overall 270' 0" Length between perpendiculars 255' 0" Beam molded 38' 0" Depth molded, main deck amidships 01 level amidships

23' 6" 31' 4"

Full load displacement 1,902.2 long tons Draft, full load to baseline amidships 14' 3" Highest projection above baseline *height approximated

≈ 110' 0"

Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase Frame spacing 1' 0"

MACHINERY

Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,600 BHP each Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-

1350 Generators. 475 KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle

Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4- 1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle

Number of propellers 2 Propeller diameter 9' 0" Number of blades, Each 4 Pitch Controllable Shaft RPM 260 Shaft diameter 10.55" at exit of hull Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each

TANK CAPACITIES

Diesel fuel total (95%) 79,210 gal.

JP-5 total (95%) 25,890 gal.

Potable water total (100%) 8,553 gal.

Hydraulic & lube oil total (95%) 2,237 gal.

1 (Rev-0)

00000_0725_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must

3 (Rev-0) be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

4 (Rev-0)

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 Not applicable.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

5 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

6 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

7 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /

TIME

8 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

9 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

10 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

11 (Rev-0)

4.2 Tank and Void Assessment form.

12 (Rev-0)

13 (Rev-0)

63110_ESD_0723_FLT

REC_12316_FLT_270’ WMEC ‘A’ Class (ALL) (0320)

S25_0008_12100_AJW_1125_901

WORK ITEM 1: Tanks, Ballast, Repair and Preserve 100 Percent

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to repair internal structure, and prepare and coat 100% of the surfaces of the following tank(s):

TABLE 1 - TANKS

TYPE OF STRUCTURE LOCATION CAPACITY - 95%

(gallons)

LOW SUCTION

(gallons)

Ballast 4-228-1-W 3,521 282 Ballast 4-228-2-W 3,521 282 Ballast 4-242-0-W 2,989 239

NOTE

Tanks also used for storing grey water – considered immediately dangerous to life and health (IDLH).

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 901 WMEC 111-002, Rev G, Shell Exp Aft 182

Coast Guard Drawing 901 WMEC 121-001, Rev D, Long Tank Bhds, Aft 182

Coast Guard Drawing 901 WMEC 131-002, Rev J, Mn Dk Pl & Fr, Aft 182

Coast Guard Drawing 901 WMEC 141-002, Rev H, 1st Platf Pltg & Framing, Aft 182

Coast Guard Drawing 901 WMEC 529-001, Rev N, Ballasting & Emer Bilge Drainage Sys Diagram

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

14 (Rev-0)

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary Hull Accesses

OTHER REFERENCES

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Diesel Oil Tanks 4-207-0-F, 4-207-1-F, 4-207-2-F, and 2-228-1-F (total capacity 28,826 gallons)

EDG

Steering system

3.1.5 Temporary access openings. Due to limited access to work areas, the Contractor may, with express permission of the KO (via submission of a CFR), cut access holes to facilitate accomplishment of the work specified herein. Perform all work required to open and close the access openings in accordance with SFLC Std Spec 8636.

NOTE

Any ballast tanks being listed for preservation will have been pumped down to low suction by ship’s force prior to arrival at the Contractor facilities.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR.

TLI’s for tanks listed in paragraph 1.1

3.3 Content removal. The Contractor must remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations. Plug all inlet and outlet piping in the tank to prevent contaminants from entering the tank. Use plugs with an attached lanyard, ring or other system that

15 (Rev-0) will ensure plugs are not lost in the pipe openings. Maintain a plug accountability log outside the tank(s) to prevent any of the installed temporary plugs from being lost inside the tank or forgotten inside at tank closure.

3.4 Repair. The Contractor must perform the following repairs, as designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740 crop and Coast Guard Drawings 901 WMEC 141-002.

Crop and renew approximately 300 square feet of steel plating and internal structure, (including but not limited to the tank top and supporting structure below the EDG) in 4-228- 1-W

Crop and renew all manhole rings and corresponding covers for tanks: 4-228-1-W, 4-242-0- W, and (forward manhole only) 4-228-2-W

Fabricate and install the missing baffle beneath the EDG in 4-228-1-W

Crop and renew approximately 300 square feet of steel plating and internal structure in 4- 228-2-W

Crop and renew approximately 300 square feet of steel plating and internal structure in 4- 242-0-W

Crop and renew two ladders, including all mounting points and hardware.

3.4.1 Ultrasonic thickness (UT) measurement. The Contractor must take a total of 500 UT measurements in accordance with SFLC Std Spec 0740, Appendix C in locations designated by the Coast Guard Inspector and using Coast Guard Drawings 901 WMEC 111-002, 901 WMEC 121-001, 901 WMEC 131- 002, and 901 WMEC 141-002 as guidance. Submit a CFR.

3.4.2 In addition to the UT measurements, take a total of 25 pit-depth measurements, using a suitable pit depth gauge

3.5 Surface preservation. The Contractor must accomplish the following tasks for the tanks listed in paragraph 1.1 (Intent):

3.5.1 The Contractor must remove and retain the tank manhole cover(s).

3.5.2 The Contractor must prepare and coat all tank interior surfaces (including internal surfaces of manhole cover(s), manhole cover hull ring(s) extending outward to the weld line that ties the hull ring into the tank plating on the tank exterior) using the system specified for "Tanks and Voids, Ballast Tanks;

Option I or II " in SFLC Std Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems). Select finish/top coat color to match existing.

3.5.3 The Contractor must prepare and coat all manhole cover external surfaces to match existing adjacent surfaces, using the system specified for “Tanks and Voids (Grey Water, Sewage, and CHT Tanks), Option II, in SFLC Std Spec 6310 Appendix B (Cutter Boat Interior Painting Systems). Select finish/top coat color to match existing adjacent surfaces.

3.6 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces).

NOTE

Surfaces being preserved are considered “critical-coated surfaces”.

16 (Rev-0)

3.7 Inspection. After surface preparation and before coating application, the Contractor must visually inspect all tank interior and manhole cover surfaces; including, but not limited to bulkheads, floor and overhead plating, structural members, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:

Structural condition.

Inaccessible areas.

Tank level indicator (TLI) and/or float switch condition.

Sounding tube and striker plate condition.

Suction and discharge piping.

Fastener condition.

3.8 Tank closing. The Contractor must ensure that the tank(s) remain open for at least 24 hours after completion of the tasks specified above. Notify the COR at least 24 hours prior to closing the tank(s).

3.8.1 After satisfactory inspection by the Coast Guard Inspector and after all authorized repairs, accomplish the following:

Reinspect all TLIs, as applicable, to verify proper operation. Submit CFR.

Close tank manhole cover(s) with new gasket material conforming to ASTM D1330 and new cotton grommets on all studs (as applicable). Chase threads on studs to ensure even installation of the access covers.

3.8.2 The Contractor must renew 100% of nylon insert/nylock nuts and washers.

4. NOTES

This section is not applicable to this work item.

17 (Rev-0)

86340_ESD_0425_FLT

REC 86340_FLT_270A WMEC (ALL) (0925)

WORK ITEM 2: Drydock

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to drydock the vessel, undock the vessel, and perform various drydocking-related tasks.

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

Y *Transducer Cover Plate PN: FL-184-002, DET 15-E 1 ea. 50.00

*Government-loaned property, which must be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 901 WMEC 562-005, Rev K, A & B Class Rudder Stock And Steering Gear A & D

Coast Guard Drawing 901 WMEC 801-012, Rev B, Curves of Form

Coast Guard Drawing 901 WMEC 801-022, Rev L, Docking Plan

Coast Guard Drawing FL 184-002, Rev B, SS60 Transducer Install Adapter Assy

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2022, Drydocking

OTHER REFERENCES

MIL-PRF-16173, Oct 2017, Corrosion Preventive Compound, Solvent Cutback, Cold Application

18 (Rev-0)

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Anchor assembly

Load conditions

U/W body appendages

3.2 Key personnel. The Contractor must determine key personnel and require their presence during all drydocking phases as required by SFLC Standard Spec 8634. Submit list of key personnel to the COR.

3.3 Docking and undocking. The Contractor must perform drydock and undock in accordance with SFLC Std Spec 8634, using Coast Guard Drawing 901 WMEC 801-022 for guidance.

3.4 Cutter conditions. The Contractor must use the Full Load Condition values listed below all in inches, for purposes of performing Pre-Award calculations as described in Appendix A (Requirements for Calculations) of SFLC Std Spec 8634.

Displacement (LT FW): 1890

VCG (FT ABL): 16.62

LCG (FT AFT MS): 4.62

LCF (FT AFT MS): 14.14

Trim (FT by stern): 0.734

MT1” (LT-FT/Inch): 272.76

3.4.1 Blocking. The Contractor must facilitate docking the vessel in designated block position by arranging keel and side blocks and ensuring minimum block heights as shown on the vessel's docking plan.

TABLE 1 – BLOCKING

POS. #

BLOCK HEIGHT ABOVE DOCKING

FACILITY DECK

STEEL

PLATE

SITUATION

AWARENESS

FIN

STABILIZERS ADDITIONAL

19 (Rev-0)

MIN.

RUDDER

REMOVAL

PROPELLER

REMOVAL

SHAFT

REMOVAL

1 48" NA 30' 0"

minimum from stern for shaft removal

NA NA If the drydock has a sliding block arrangement, the Dockmaster must exercise special care and/or set side blocks between frames 96 and 104 (fin stabilizer area) by a different method which clears the fin stabilizers.

None

3.5 Pre-award calculations. The Contractor must provide to the KO a set of pre-award calculations, as described in SFLC Std Spec 8634 Appendix A.

3.5.1 Provide vertical side/bilge block offsets for any side blocks placed in a location where vertical offsets are not already defined by the docking plan.

3.5.2 Submit an alternate blocking arrangement, as part of the pre-award calculation submission, to compensate for any changes from the docking plan.

3.5.2.1 If the alternate blocking arrangement interferes with U/W hull plate inspection or 100% preservation of U/W body surfaces required under separate work items in this specification package, the Contractor must include a plan of how inspection/preservation will be accomplished. Plan must include any modifications necessary to the prescribed docking plan including removing, shifting, repositioning blocks, or fleeting the vessel at no additional cost to the Government.

NOTE

1. The USCG has established several approved alternate docking plans for each vessel-class, to facilitate complete access to the entire U/W body structure, for periodic comprehensive inspection and/or 100% preservation.

This inspection and preservation pattern and periodicity is a configuration management concern that is a vital requirement of the contract. Intention to deviate from these plans (fewer blocks, block spacing, additional blocks, etc) is to be identified on pre-award calculations (Paragraph 3.5.2); an alternate docking plan and mitigation strategy will be provided to maintain preservation and inspection configuration.

20 (Rev-0)

2. Pre-award calculations may be deemed unsatisfactory - and may adversely affect contract award if they are submitted with the following detrimental factors:

a. No methods have been proposed that meet the requirements for the specified docking plan.

b. Proposed block shifting or fleeting risk-mitigating plan may result in delays in period of performance.

c. Proposed alternate docking plan violates USCG configuration management policies.

3.6 Unplanned availability: Underwater body cleaning-removal of marine growth. The Contractor must accomplish the work in this paragraph in lieu of the work described in SFLC Std Spec 8634 paragraphs

3.5.4.1 and 3.5.4.2. Within four hours after the vessel has been docked, the Contractor must start cleaning the entire underwater hull from the upper edge of the boot top down, including sea chest gratings, sea chest interiors, fairwaters, rope guards, rudder, shaft strut, z-drive, thruster tunnel, and zinc anodes, as applicable. The Contractor must remove all marine growth, fouling, salt, and dirt from the underwater hull by High Pressure Fresh Water Wash, using a minimum pressure at the nozzle of 3,500 psi and maximum pressure of 7,000 psi. Complete the hull cleaning before marine growth hardens. Removal of gratings is not required.

WARNING

Do not use chemical additives in the freshwater wash. Take extreme care to avoid damaging or removing existing intact underwater body coating.

3.7 Fuel offloading. The Contractor must be aware that fuel offloading is not mandatory to drydock the vessel.

3.8 Fleeting. Not required.

4. NOTES

4.1 Arrival conditions. The COR will advise the Contractor of the actual tank and draft readings when the vessel arrives, and will discuss with the Contractor any liquid loading changes necessary.

21 (Rev-0)

86350_ESD_1021_FLT

REC_86350_FLT_270A WMEC (ALL) (1110)

WORK ITEM 3: Temporary Services, Provide - Cutter

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to provide temporary services to the Cutter, during the performance of this availability.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary Services

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

22 (Rev-0)

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Temporary service particulars. The Contractor must provide the below listed temporary services, in accordance with SFLC Std Spec 8635.

TABLE 1 - SERVICE SELECTION

*SUB-

PARAGRAPH

TITLE

Y/N

3.3.1 Office space N

3.3.2 Telephone and internet access N

3.3.3 Parking Y

3.3.4 Duty section berthing N

3.3.5 Electrical power (including all requirements in associated sub-paragraphs) Y

3.3.6 Hull grounding straps (not applicable when cutter is waterborne) N

3.3.7 Compressed air (including all requirements in associated sub-paragraphs) N

3.3.8 Hazardous material/hazardous waste disposal (see Tables 2 and 3 below) Y

3.3.9 Heavy lift equipment: 48 hours Y

3.3.10 Water supply

3.3.10.1 Potable water: 5,000 gallons per day, at 40 psig Y

3.3.10.2 Hot-circulating water N

3.3.10.3 Cooling water (including 2-1/2” supply and return lines for the ASW system) Y

3.3.10.4 Firemain system (including all requirements in associated sub-paragraphs) Y

3.3.11 Steam (including all requirements in associated sub-paragraphs) N

3.3.12 Refuse disposal N

3.3.13 Sewage and grey water disposal (including all requirements in associated sub-paragraphs) Y

3.3.14 Storage – General (including all requirements in associated sub-paragraphs):

3.3.14 Dry stores. N

3.3.14 Paint and flammable stores. N

3.3.14 Refrigerated stores. N

3.3.15 Small boat storage (including all requirements in associated sub-paragraphs) N *Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 8635.

TABLE 2 - HAZARDOUS WASTE DISPOSAL – LIQUIDS (GALLONS)

PAINT THINNERS ENGINE COOLANT BILGE WATER

N/A N/A 4,000

TABLE 3 - HAZARDOUS WASTE DISPOSAL – SOLIDS

OILY

FILTERS

OILY RAGS

(LBS)

EMPTY 1-GAL

CONTAINER*

EMPTY 5-GAL

CONTAINER*

EMPTY 55-GAL

CONTAINER*

N/A N/A N/A N/A N/A *Previously housed hazardous materials.

3.3 Extended temporary services. If the performance period of the contract is extended by the KO, the contractor must continue to provide all temporary services as specified herein for the extension period.

23 (Rev-0)

4. NOTES

This section is not applicable to this work item.

File details come from the government source that posted it. Updated .